Aftermath of the INES3 Incident at Paks NPP on 10th April, 2003'

presentation player overlay
1 / 11
About This Presentation
Transcript and Presenter's Notes

Title: Aftermath of the INES3 Incident at Paks NPP on 10th April, 2003'


1
Aftermath of the INES-3 Incident at Paks NPPon
10th April, 2003.
  • Lajos Vöröss
  • Hungarian Atomic Energy Authority
  • 7th Annual Meeting of NERS
  • IAEA, Vienna, 23-24, September 2004.

2
(No Transcript)
3
Main Tasks to Perform
  • After having stabilised the situation inside the
    reactor hall there have been two main tasks to
    perform
  • 1. Recovery of service shaft No.1 of Unit 2. (SS)
    where the incident occurred
  • 2. Restart of Unit 2. as soon as possible

4
Recovery of SS
- Recovery project and team established at Paks
NPP - Tendering process won by Russian
consortium led by TVEL FRAMATOM had bidden as
well - 6-8 months preparatory, 2-3 months
implement phases planned, excluded licensing time
- significant delay now - Special tools for
manual removal of debris are to be used -
Manipulation is to be carried out from a movable
platform placed above the cleaning tank - Some
experiments to clarify behaviour of debris for
planned removal actions performed
5
Recovery outline FRA / GER
crane
control panel
  • 2 versions
  • removal of the cleaning tank and fuel in one step
    (dismissed later difficult, does not give final
    solution)
  • removal of the cleaning tank and fuel in parts
    with clips, bending tools, manipulators, vacuum
    soakers, cutters

air filter
suction
working rod
manipulator
container
cleaning tank
6
winner
Recovery outline RUS
mostly manual removal
shell
different - water level, - boron concent-
ration, - contami- nation
??? ?????
moving platform
?? ???????
?? ??????
structure
?? ????
container
7
Recovery of SS (contd)
  • - Separation of SS from spent fuel pond and from
    other
  • systems of Unit 2.became necessary
  • - Autonomous cooling device and emergency boron
  • injection system for SS have been installed
  • - Mobile water cleaning device (NURES,Finland)
    was used
  • to clean the water especially from the uranium
    and trans-uranium isotopes

8
Recovery of SS (contd)
  • - Reliable neutron flux and boron concentration
    measurement in SS installed
  • - Increased radwaste storage capacity
    constructed
  • - Free positions made available for
    capsules/cartridges containing debris in spent
    fuel pool
  • - Preparatory actions for regulatory licensing
    process
  • - regulatory requirements for recovery
    developed
  • - review and assessment in large number of
    modifications and fabrication of equipment
    performed

9
Restart of Unit 2.
  • - After long-term shut-down status with intact
    main equipment but contaminated by uranium and
    trans-uranium isotopes - special cleaning was
    necessary (completed)
  • - Interrupted refuelling and maintenance
    occurred during the incident
  • - RPV used as temporary storage tank of spent
    fuel assemblies
  • - Low enrichment fresh FE supply and
    rearrangement of spent fuel pool became necessary
  • - Reuse of cleaned spent fuel assemblies is
    limited

10
Restart of Unit 2. (contd)
  • - Conception for short term operation cycle
    developed
  • - refuelling and yearly maintenance completed
  • - suitable core for operation during the
    preparatory phase of the recovery is possible
    (about 4 months long)
  • - regulatory requirements for
    restart/operation phases developed, licence given
    on 16. July, 2004.
  • - nearly full power operation started on 02
    Sept. 2004.
  • - Keen interest from media and public follows


11
International Assistance
  • - IAEA - two international missions provided at
    Paks NPP
  • - GAN (Russian Regulator) - on basis of
    contractual arrangement, focuses to review QA of
    Russian contractors
  • - US NRC/IAEA - gives advice to review
    conditions of restart of Unit 2.
  • NOTE In spite of the incident, lifetime
    extension and power uprating of the units are
    still insisted on
Write a Comment
User Comments (0)
About PowerShow.com