Title: Aftermath of the INES3 Incident at Paks NPP on 10th April, 2003'
1Aftermath of the INES-3 Incident at Paks NPPon
10th April, 2003.
- Lajos Vöröss
- Hungarian Atomic Energy Authority
- 7th Annual Meeting of NERS
- IAEA, Vienna, 23-24, September 2004.
2(No Transcript)
3 Main Tasks to Perform
- After having stabilised the situation inside the
reactor hall there have been two main tasks to
perform - 1. Recovery of service shaft No.1 of Unit 2. (SS)
where the incident occurred - 2. Restart of Unit 2. as soon as possible
-
-
-
-
4Recovery of SS
- Recovery project and team established at Paks
NPP - Tendering process won by Russian
consortium led by TVEL FRAMATOM had bidden as
well - 6-8 months preparatory, 2-3 months
implement phases planned, excluded licensing time
- significant delay now - Special tools for
manual removal of debris are to be used -
Manipulation is to be carried out from a movable
platform placed above the cleaning tank - Some
experiments to clarify behaviour of debris for
planned removal actions performed
5Recovery outline FRA / GER
crane
control panel
- 2 versions
- removal of the cleaning tank and fuel in one step
(dismissed later difficult, does not give final
solution) - removal of the cleaning tank and fuel in parts
with clips, bending tools, manipulators, vacuum
soakers, cutters
air filter
suction
working rod
manipulator
container
cleaning tank
6winner
Recovery outline RUS
mostly manual removal
shell
different - water level, - boron concent-
ration, - contami- nation
??? ?????
moving platform
?? ???????
?? ??????
structure
?? ????
container
7 Recovery of SS (contd)
-
- - Separation of SS from spent fuel pond and from
other - systems of Unit 2.became necessary
- - Autonomous cooling device and emergency boron
- injection system for SS have been installed
- - Mobile water cleaning device (NURES,Finland)
was used - to clean the water especially from the uranium
and trans-uranium isotopes
8Recovery of SS (contd)
- - Reliable neutron flux and boron concentration
measurement in SS installed - - Increased radwaste storage capacity
constructed - - Free positions made available for
capsules/cartridges containing debris in spent
fuel pool - - Preparatory actions for regulatory licensing
process - - regulatory requirements for recovery
developed - - review and assessment in large number of
modifications and fabrication of equipment
performed -
9 Restart of Unit 2.
- - After long-term shut-down status with intact
main equipment but contaminated by uranium and
trans-uranium isotopes - special cleaning was
necessary (completed) - - Interrupted refuelling and maintenance
occurred during the incident - - RPV used as temporary storage tank of spent
fuel assemblies - - Low enrichment fresh FE supply and
rearrangement of spent fuel pool became necessary - - Reuse of cleaned spent fuel assemblies is
limited
10 Restart of Unit 2. (contd)
- - Conception for short term operation cycle
developed - - refuelling and yearly maintenance completed
- - suitable core for operation during the
preparatory phase of the recovery is possible
(about 4 months long) - - regulatory requirements for
restart/operation phases developed, licence given
on 16. July, 2004. - - nearly full power operation started on 02
Sept. 2004. - - Keen interest from media and public follows
11 International Assistance
- - IAEA - two international missions provided at
Paks NPP - - GAN (Russian Regulator) - on basis of
contractual arrangement, focuses to review QA of
Russian contractors - - US NRC/IAEA - gives advice to review
conditions of restart of Unit 2. -
- NOTE In spite of the incident, lifetime
extension and power uprating of the units are
still insisted on -
-