Programmed dumps (incl. inject - PowerPoint PPT Presentation

About This Presentation
Title:

Programmed dumps (incl. inject

Description:

Assuming only safe beam can be used ... The XPOC needs to acquire and check data associated with beam dump action. ... BT (i.e. Etienne) will build the new HW ... – PowerPoint PPT presentation

Number of Views:13
Avg rating:3.0/5.0
Slides: 22
Provided by: GODD3
Category:

less

Transcript and Presenter's Notes

Title: Programmed dumps (incl. inject


1
Programmed dumps (incl. inject dump)
  • LBDS functional architecture
  • Use-case overviews
  • Inject and dump between 0 1000 turns
  • Inject and dump between 0.1 and 1000 seconds
  • Programmed dumps during injection process
  • Programmed dump at end-of-fill
  • Programmed dump of one beam
  • Requirements on other systems
  • Implementation
  • Annex (use-case details)

2
LBDs functional architecture
  • LBDS interfaces for arming, triggering and energy
    tracking
  • DCCTs in 4 of the LHC arcs, and in IR6, for the
    BETS
  • RF system, for the abort gap fast timing
  • injection interlock system, to allow the dump to
    be armed
  • BIS beam interlock system via the local BIC
    client interface
  • redundant IR6 beam loss system, to trigger LBDS
    independently of BIS
  • access system, to dump beam without passing
    through BIS

3
Inject and dump I 0 1000 turns
  • For injection setting-up with screens, and
    studies requiring less than 100 ms of circulating
    beam, e.g. aperture measurements in
    injection/extraction channel.
  • Will use a dedicated hardware system to trigger
    the beam dump via the BIS
  • Necessary to dump after less than one full turn,
    to ensure that injection setting up with screens
    can be performed with a single beam impact.
  • To protect the screens, maximum number of turns
    has to be limited.
  • Preferable that this mode limited to Safe Beam
    from SPS if not, then procedure is more
    complicated, requiring pilot injection prior to
    high-intensity injection, to ensure circulating
    beam condition is met.
  • The other entry conditions are that the LHC
    machine is at injection energy, that the beam
    permit for the selected ring is TRUE.
  • Use a timing event at 100 ms (or even few ms
    after the requested number of turns) to provide
    redundancy for increased screen protection

4
Inject and dump II 0.1 1000 seconds
  • This mode is required for longer delays between
    injecting and dumping
  • Will use the timing system to trigger the beam
    dump via the BIS.
  • Screens are NOT allowed to be in the beam
  • Again, for simplicity, it would be preferred that
    this mode can only be used with the Safe Beam
    from the SPS, but this is less important since
    interlocking should anyway ensure that the
    screens cannot be used

5
Dump of intermediate beam during injection
  • A programmed dump during the nominal injection
    sequence is required to dispose of the
    intermediate beam injected after the pilot bunch
    (cannot be dumped parasitically onto the TDI
    injection collimator).
  • Will use the timing system to trigger the beam
    dump via the BIS.
  • Variations on the theme will be needed, according
    to whether both rings are filled alternately or
    sequentially, and on the details of the
    adjustment and filling phases.
  • The question of whether the BIS/LBDS should
    enforce a dump of both rings in the event of a
    beam permit FALSE for one ring still needs to be
    decided it would increase the operational
    flexibility, but reduce the safety, since some
    interlock channels with separate signals for beam
    1 and beam 2 may be cross-connected. Work in
    progress with interlock team e.g. on making this
    conditional on machine mode.

6
Dump of both beams at end-of-fill
  • A programmed dump at the end-of-fill will be
    required, for example when the specific
    luminosity is low enough that the machine
    requires refilling.
  • Will use the timing system to trigger the beam
    dump via the BIS.
  • The dump request will be managed by the
    sequencer, which must make sure that the entry
    conditions are satisfied, and that any
    preparatory steps concerning e.g. the
    experiments, the movable devices etc. are first
    executed

7
Dump of one beam
  • A programmed dump of one beam is a possible
    requirement, for example for machine studies at
    the end of a fill.
  • Will use the timing system to trigger the beam
    dump via the BIS.
  • The dump request will be managed by the
    sequencer, which must make sure that the entry
    conditions are satisfied, and that any
    preparatory steps concerning e.g. the
    experiments, the movable devices etc. are first
    executed.
  • Condition under which this is possible need
    definition

8
Protection of BTV screens at injection
  • Inject and Dump I mode needed to ensure
    protection of screens only used when LHC is in
    this mode AND turns requested less than safe
    limit (depends on screen type (Al2O3 or Ti) and
    intensity)
  • Assuming only safe beam can be used
  • Al2O3 screens withstand 1013 p/mm2, and Ti
    screens 1014 p/mm2. For nominal optics, p
    density at screen for injected nominal batch of
    3.3?1013 p is 1.1?1013 P/mm2.
  • Assuming that the safe beam limit is 1012 p at
    450 GeV, safe number of turns for Ti screens is
    300, and for Al2O3 screens 30.
  • Taking ?3 margin, max. turns with safe beam
    should be 100 for Ti and 10 for Al2O3 screens.
  • To be implemented in SW interlock which uses
    number of turns requested and screen position to
    allow or inhibit injection.
  • HW interlock from screens to inhibit user permit
    for unsafe beam, if screen in beam.
  • Assuming any beam can be used
  • Product of turns ? intensity must not exceed
    1013 for Al2O3, and 1014 for Ti screen (i.e. 3
    turns with full intensity, or 2?104 turns with
    pilot bunch).
  • To be implemented in SW interlock which uses
    measured beam intensity (in SPS), number of turns
    requested and screen position to allow or inhibit
    injection.
  • Additional protection measures
  • Limit the maximum number of turns to 1000 in
    Inject Dump I HW
  • In this mode always include a timing event at 100
    ms (or more closely linked to turns requested).
  • As a real HW interlock with no software
    dependence, use BLMs at each screen, with
    interlock threshold at an appropriate integration
    time, to dump beam if losses detected exceed
    dangerous level.

9
Interlock and dump systems
  • BIS used to trigger beam dump for all programmed
    dumps. BIS must therefore provide a reliable and
    deterministic response to interrupt in IR6 coming
    from Inject and Dump I system, such that beam can
    reliably be dumped after programmed number of
    turns.
  • BIS must also provide an automatic reset for
    certain machine modes, in order that repeated
    injection or injection sequence can continue.
    (Alternatively such functionality could be
    provided by sequencer which works in a quasi
    real-time loop?)
  • The following functionalities are required
  • Triggering via timing system (delay can be of the
    order of a few turns)
  • Automatic reset conditional on machine mode (from
    SMP)
  • SW input channel for XPOC inhibit
  • LBDS must be re-armed after every action, which
    is foreseen to be requested by the sequencer.
  • LBDS IPOC and XPOC results must be positive and
    beam permit loop is then forced close during a
    short period, while LBDS inhibits injection and
    forces its own user permit true.

10
Timing, RF and SMP systems
  • The timing system will be used for the Inject and
    Dump II mode and for the other programmed dump
    events. The following timing system
    functionalities are required
  • Distributing Programmed dump
  • Distributing XPOC request events (tbc)
  • Distributing PM request events conditional on
    machine mode and dump type
  • The following RF system functionalities are
    required
  • Injection prepulse to IR6 (RA63/67) assume 10
    ?s before injection (tbc). Needs new fibres.
  • Revolution frequency to IR6 (RA63/67) already
    exists to LBDS TSU
  • For the Safe Machine Parameters the LHC mode must
    be distributed to the BIS, for conditioning the
    automatic reset (alternatively mode must be
    available to the sequencer which will manage
    reset).
  • The mode is also needed for the screens, to
    prevent any movement while beam can be injected
    or present.

11
Beam screens and SW interlocks
  • The beam screens must be protected against
    damage, and this requires interlocking on their
    position, conditional on the machine mode and
    intensity.
  • The following functionalities are required
  • HW interlock if moving
  • HW interlock if unsafe beam (tbc depending if
    Inject Dump I limited to safe beam)
  • Read of screen position and type (for SW
    interlock)
  • Dedicated interlock BLMs with thresholds adapted
    to protect the screens
  • Movement inhibited in any machine mode where beam
    can be present
  • The following SW interlocks are required
  • Inhibit injection if screens moving
  • Inhibit injection if screens in beam and unsafe
    beam (tbc)
  • Inhibit injection if screens in beam and machine
    mode ltgt Inject and Dump I
  • Inhibit injection if screens in beam and ID I
    system turns gt100
  • Inhibit injection if screens in beam and turns ?
    intensity gt 1013 (Al2O3) or 1014 (Ti)

12
Sequencer and XPOC
  • The sequencer must provide the high-level
    management of the inject and dump machine modes
    and of the other programmed dumps. The following
    functionalities are required
  • managing machine mode changes
  • configuring all the systems to meet the entry
    conditions
  • checking that the entry conditions are met
  • generating the timing events with the correct
    delays
  • setting the turn counter value
  • requesting checks before injection is enabled
  • requesting the correct beam from the SPS
  • reading the XPOC result
  • arming and re-arming the LBDS
  • re-arming the BIS (tbc)
  • The XPOC needs to acquire and check data
    associated with beam dump action. The process
    must inhibit beam permit via a software channel
    while busy. The XPOC needs to return an answer
    within about 10 s, in order to allow for repeated
    injections in Inject and Dump mode.

13
Implementation
  • BT (i.e. Etienne) will build the new HW
  • Schematic architecture of LBDS with new inject
    and dump crate shown below

14
New Inject Dump HW
  • Assumed HW located in a rack or racks in point 6
    underground, in RA63/67, to minimise the reaction
    times with the beam permit loop.
  • Present prepulse envisaged 10 ?s prior to
    injection, to minimise dead time of MKI when
    injection kick can no longer be stopped.
  • Detailed analysis of response times and signal
    delays to be made, to determine whether this is
    adequate for deterministic dumping on turn 0, or
    whether another separate prepulse needs to be
    generated with a longer delay to trigger this
    system.
  • The following functionalities are required
  • Triggering by RF prepulse
  • Turn counting via RF frequency
  • Interrupt of beam permit loop
  • Adjustable delay in order to trim the system
    synchronisation during setting up
  • Set requested turns via LSA (MCS?)
  • Read of requested turns via LSA (for SW
    interlocks)

15
Issues
  • Need a better name than Inject and Dump I
    system.
  • Limit inject and dump I mode (with 0 1000
    turns) to safe beam intensity?
  • Easier to implement safer for screens
  • Operational constraints?
  • Are the limits 0 1000 turns and 0.1 1000
    seconds reasonable?
  • Is 10 ms injection prepulse delay enough for 0
    turns?
  • Delay accounting and tests to be made
  • Otherwise need separate pre-pulse with few 100
    ms?
  • Is the proposed protection for the screens
    adequate?
  • Not clear that local private turn counters safer
    BLMs to be defined and feasibility checked
  • To be discussed in upcoming MPWG
  • Conditions to dump one beam? Arm inject with
    other beam permit false?
  • Automatic reset of BIS are we sure that this
    does not impact the reliability?
  • Sequencer work still to be done to define
    detailed requirements
  • Can this be used to reset the BIS?
  • XPOC and PM triggering, data acquisition and
    pathways work still needed
  • LHC machine mode details
  • Can Inject and dump I and Inject and dump II
    be combined? Interlocking implications?
  • Present definitions require extension links to
    sequencing and interlocking

16
Use-case details
17
Inject and dump I 0 1000 turns
  • i. Machine mode is changed to Inject and Dump I
    by the LHC sequencer
  • ii. Number of turns selected between 0 and 1000
    and loaded into Inject and Dump hardware by
    sequencer
  • iii. Request dump Timing event delay set at 100
    ms or corresponding value
  • iv. Checks made of screen positions and requested
    turns resident in the Inject and Dump hardware by
    the LHC sequencer - injection is inhibited if
  • a. screens are MOVING
  • b. OR the screens are IN and the mode is not
    Inject and Dump I
  • c. OR the number of turns requested exceeds the
    safe limit.
  • v. Safe beam is requested from the SPS by the LHC
    sequencer
  • vi. Beam is injected and the turn-counter
    triggered in the Inject and Dump hardware
  • vii. After the programmed number of turns, the
    Inject and Dump Hardware triggers beam dump via
    BIS
  • viii. The timing system generates a request
    XPOC timing event, after receiving a dump
    request associated with a request dump timing
    event while in Inject and Dump I mode OR
    specific shot-by-shot transient data logging data
    is acquired, associated with the injection and
    with the beam dump. No request PM event is
    issued
  • ix. The XPOC process inhibits the injection by
    the SW user permit channel of the BIS
  • x. The data required for the XPOC is transferred
    to the servers and analysed by the XPOC process
  • xi. If the dump action was correctly executed the
    XPOC process gives the user permit
  • xii. The BIS makes an automatic reset, possible
    for Inject and Dump I Machine Mode
  • xiii. The sequencer launches the arm LBDS
    sub-sequence

18
Inject and dump II 0.1 1000 seconds
  • i. Machine mode is changed to Inject and Dump
    II by the LHC sequencer
  • ii. Delay time selected between 0.1 and 1000
    seconds and loaded into the timing system by the
    LHC sequencer
  • iii. Checks are made of injection screen
    positions and screen types by the LHC sequencer -
    injection is inhibited if any screens are IN or
    MOVING
  • iv. Safe beam is requested from the SPS by the
    LHC sequencer
  • v. Beam is injected
  • vi. After the appropriate delay, the timing
    system issues an event which is received by the
    BIS and triggers the beam dump by opening the
    beam permit loop
  • No request PM event is issued. The timing
    system generates a request XPOC timing event,
    after receiving a dump request associated with a
    request dump timing event while in Inject and
    Dump II mode OR specific shot-by-shot
    transient data logging data is acquired,
    associated with the injection and with the beam
    dump.
  • The XPOC process inhibits the injection by the SW
    user permit channel of the BIS
  • ix. The data required for the XPOC is transferred
    to the servers and analysed by the XPOC process
  • x. If the dump action was correctly executed the
    XPOC process gives the user permit
  • xi. The BIS makes an automatic reset, possible
    for Inject and Dump II Machine Mode
  • xii. The sequencer launches the arm LBDS
    sub-sequence

19
Inject and dump II 0.1 1000 seconds
  • i. Normal Injection Sequence started by the LHC
    sequencer
  • ii. Pilot beam is injected and adjusted, then the
    intermediate beam is over-injected (in this case
    the pilot is deflected onto the TDI) and
    adjusted
  • iii. Once both rings of the machine are judged
    satisfactory with the intermediate beam, the
    Injection Sequence is launched
  • iv. Via the sequencer, generate and issue a
    timing event which is received by the BIS and
    triggers the beam dump for both rings by opening
    the beam permit loop
  • v. No request PM event is issued. The timing
    system generates a request XPOC timing event,
    after receiving a dump request associated with a
    request dump timing event while in Inject and
    Dump II mode OR specific shot-by-shot
    transient data logging data is acquired,
    associated with the injection and with the beam
    dump.
  • vi. The XPOC process inhibits the injection by
    the SW user permit channel of the BIS
  • vii. The data required for the XPOC is
    transferred to the servers and analysed by the
    XPOC process
  • viii. If the dump action was correctly executed
    the XPOC process gives the user permit
  • ix. The BIS makes an automatic reset, possible
    for Normal Injection Machine Mode
  • x. The sequencer launches the arm LBDS
    sub-sequence
  • xi. Inject a pilot bunch into Ring 1 and Ring 2
  • xii. Change to nominal beam in the SPS
  • xiii. Start injecting the nominal beam,
    over-injecting the pilots in Ring 1 and Ring 2

20
Dump of both beams at end-of-fill
  • i. Machine mode is set to Unstable
    Beams/Adjust by the LHC sequencer
  • ii. Preparatory steps executed by the LHC
    sequencer for machine, experiments, beam
  • iii. Generate and issue timing event(s) which is
    received by the BIS and triggers the beam dump
    for both rings by opening the beam permit loops
  • iv. The timing system generates a request PM
    timing event, after receiving a dump request
    associated with a request dump timing event.
    Possibly the specific shot-by-shot transient data
    logging data is still acquired, associated with
    the beam dump, depending on details of the XPOC
    data acquisition
  • v. The XPOC process inhibits the SW user permit
    channel of the BIS
  • vi. The data required for the XPOC is transferred
    to the servers and analysed by the XPOC process
  • vii. If the dump action was correctly executed
    the XPOC process gives the user permit
  • viii. The BIS does NOT make an automatic reset

21
Dump of one beam
  • i. Machine mode is set to Unstable
    Beams/Adjust/??? by the LHC sequencer
  • ii. Preparatory steps executed by the LHC
    sequencer (?)
  • iii. Generate and issue timing event(s) which is
    received by the BIS and triggers the beam dump
    for one rings by opening the beam permit loop
  • The timing system DOES NOT generates a request
    PM timing event. Possibly the specific
    shot-by-shot transient data logging data is still
    acquired, associated with the beam dump,
    depending on details of the XPOC data
    acquisition.
  • The XPOC process inhibits the SW user permit
    channel of the BIS for the appropriate beam
  • vi. The data required for the XPOC is transferred
    to the servers and analysed by the XPOC process
  • vii. If the dump action was correctly executed
    the XPOC process gives the user permit
  • viii. The BIS does NOT make an automatic reset
Write a Comment
User Comments (0)
About PowerShow.com