RB'A78 Powering Procedure - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

RB'A78 Powering Procedure

Description:

This operation is fully transparent to the sequencer, it is only used to set the step passed ... Seq: Make the PC simulate a Powering Failure. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 30
Provided by: hccWe
Category:

less

Transcript and Presenter's Notes

Title: RB'A78 Powering Procedure


1
RB.A78 Powering Procedure
Not explained in this document
Mirko Pojer Matteo Solfaroli
Version from 15/06/2007
2
MTF STEP 095 HCA PCC
  • Configuration of the power converters
  • Field Engineer OK to AB/PO for pre-test of the
    power converters
  • Field Engineer Include converter in the Special
    Test SOC
  • AB/PO Pre-test of the converter
  • Field Engineer Set step passed (or not) in the
    Sequencer
  • This operation is fully transparent to the
    sequencer, it is only used to set the step passed
  • AB/PO will indicate in the daily meetings the
    converters they want to pre-test.
  • The Field Engineer (HCC) is the responsible for
    the proper flow of information and keeping the
    Special Test SOC and the LSA DB updated.

3
PIC2
  • Seq or Op Pre-test of converters finished? IF
    NOT stop test

4
MTF STEP 28 HCA PLI1.1
  • MTF Step 28-HCA PLI1.1 Current Cycle I_INJECTION
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_INJECTION at
    DIDT_P2N.
  • Seq When I I_INJECTION Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq Switch off the converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 1 Current Cycle
5
MTF STEP 30 HCA PLI1.2
  • MTF Step 30-HCA PLI1.2 Energy Extraction
    Discharge
  • Extraction through QPS application (simulating a
    bus-bar quench)
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INJECTION at
    DIDT_P2N.
  • Seq When I I_INJECTION Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Request QPS EXPERT to Provoke an Extraction
    Discharge.
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 2 Extraction Discharge
6
MTF STEP 32 HCA PLI1.3
  • MTF Step 32-HCA PLI1.3 Powering Failure from PC
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INJECTION at
    DIDT_P2N.
  • Seq When I I_INJECTION Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Make the PC simulate a Powering Failure.
  • Seq Wait creation of Post-Mortem data from PIC
    and Converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP) .
  • Seq Send MTF data.

Sequence Type 3 Powering Failure
7
MTF STEP 34 HCA PLI1.4
  • MTF Step 34-HCA PLI1.4 Fast Power Abort from PIC
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INJECTION at
    DIDT_P2N.
  • Seq When I I_INJECTION Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Make the PIC provoke a Fast Power Abort
    (FPA).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 4 FPA
8
MTF STEP 36 HCA PLI1.5a,b,c,d
  • MTF Step 36-HCA PLI1.5a,b,c,d Heater Firing
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INJECTION at
    DIDT_P2N.
  • Seq When I I_INJECTION Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Op Pop-up window - Ask the QPS expert to fire
    all the quench heaters of the magnets in the
    list provided by MPP (one for each test).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP) and
    a comment about on which magnet the quench
    heaters were fired.
  • Seq Send MTF data.

Sequence Type 5 Heater Firing
9
MTF STEP 40 HCA PLI1.7
  • MTF Step 40-HCA PLI1.7 No Icing Verification
  • Seq Pop-up window - Did the current leads
    perform properly during the PLI1 tests?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 6 Icing
10
MTF STEP 42 HCA PLI2.1
  • MTF Step 42-HCA PLI2.1 Current Cycle I_INTERM_1
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_1 at
    DIDT_P2N.
  • Seq When I I_INTERM_1 Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq Switch off the converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 1 Current Cycle
11
MTF STEP 44 HCA PLI2.2
  • MTF Step 44-HCA PLI2.2 Energy Extraction
    Discharge
  • Extraction through QPS application (simulating a
    bus-bar quench)
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_1 at
    DIDT_P2N.
  • Seq When I I_INTERM_1 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Request QPS EXPERT to provoke an Extraction
    Discharge.
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 2 Extraction Discharge
12
MTF STEP 45 HCA PLI2.2b
  • MTF Step 45-HCA PLI2.2b Slow Power Abort from
    PIC
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_1 at
    DIDT_P2N.
  • Seq When I I_INTERM_1 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Make the PIC provoke a Slow Power Abort
    (SPA).
  • Seq Wait creation of Post-Mortem data from PIC
    and Converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 7 SPA
13
MTF STEP 46 HCA PLI2.3a,b,c,d
  • MTF Step 46-HCA PLI2.3a,b,c,d Heater Firing
    I_INTERM_1
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_1 at
    DIDT_P2N.
  • Seq When I I_INTERM_1 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Op Pop-up window - Ask the QPS expert to fire
    all the quench heaters of the magnets in the
    list provided by MPP (one for each test).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP) and
    a comment about on which magnet the quench
    heaters were fired.
  • Seq Send MTF data.

Sequence Type 5 Heater Firing
14
MTF STEP 48 HCA PLI2.4
  • MTF Step 48-HCA PLI2.4 No Icing Verification
  • Seq Pop-up window - Did the current leads
    perform properly during the PLI2 tests?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 6 Icing
15
MTF STEP 42 HCA PLI2.1a
  • For Sector 7-8 the tests stop at I_INTERM_1 and
    step 42 has to be repeated to check for magnets
    stability.
  • MTF Step 42-HCA PLI2.1 Current Cycle I_INTERM_1
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_1 at
    DIDT_P2N.
  • Seq When I I_INTERM_1 Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq Switch off the converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 1 Current Cycle
16
MTF STEP 500 HCA PLI3.1a
  • MTF Step 500-HCA PLI3.1a Current Cycle
    I_INTERM_2
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_2 at
    DIDT_P2N.
  • Seq When I I_INTERM_2 Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq Switch off the converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 1 Current Cycle
17
MTF STEP 52 HCA PLI3.2
  • MTF Step 52-HCA PLI3.2 Energy Extraction
    Discharge
  • Extraction through QPS application (simulating a
    bus-bar quench)
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_2 at
    DIDT_P2N.
  • Seq When I I_INTERM_2 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Request QPS EXPERT to provoke an Extraction
    Discharge.
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 2 Extraction Discharge
18
MTF STEP 58 HCA PLI3.3a,b,c,d
  • MTF Step 58-HCA PLI3.3a,b,c,d Heater Firing
    I_INTERM_2
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_2 at
    DIDT_P2N.
  • Seq When I I_INTERM_2 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Op Pop-up window - Ask the QPS expert to fire
    all the quench heaters of the magnets in the
    list provided by MPP (one for each test).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP) and
    a comment about on which magnet the quench
    heaters were fired.
  • Seq Send MTF data.

Sequence Type 5 Heater Firing
19
MTF STEP 60 HCA PLI3.4
  • MTF Step 60-HCA PLI3.4 No Icing Verification
  • Seq Pop-up window - Did the current leads
    perform properly during the PLI3 tests?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 6 Icing
20
MTF STEP 500 HCA PLI3.1a
  • MTF Step 500-HCA PLI3.1a Current Cycle
    I_INTERM_2
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_2 at
    DIDT_P2N.
  • Seq When I I_INTERM_2 Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq Switch off the converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP).
  • Seq Send MTF data.

Sequence Type 1 Current Cycle
21
MTF STEP 62 HCA PLI4.1
  • MTF Step 62-HCA PLI4.1 Energy Extraction
    Discharge
  • Extraction through QPS application (simulating a
    bus-bar quench)
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_INTERM_3 at
    DIDT_P2N.
  • Seq When I I_INTERM_3 Wait for
    TIME_PLATEAU_ZERO (30 s).
  • Seq Request QPS EXPERT to provoke an Extraction
    Discharge.
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 2 Extraction Discharge
22
MTF STEP 64 HCA PLI4.2
  • MTF Step 64-HCA PLI4.2 No Icing Verification
  • Seq Pop-up window - Did the current leads
    perform properly during the PLI4 tests?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 6 Icing
23
MTF STEP 66 HCA PNO.1
  • MTF Step 66-HCA PNO.1 Current Loop Stability
    PC Fail
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s).
  • Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
  • Seq When I I_PNO Wait for at least
    TIME_PLATEAU_2 (240 s).
  • Op/Seq Pop-up window - during this waiting time,
    the operator asks OK from AB/PO to go ahead
    with the tests (current loop stability
    confirmation). If the waiting time is longer
    than TIME_PLATEAU_2 keep waiting.
  • Seq PLEP from I_INJECTION to I_MIN_OP at
    -DIDT_P2N.
  • Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
    (120 s).
  • Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
  • Seq Make the PC simulate a Powering Failure.
  • Seq Wait creation of Post-Mortem data from PIC
    and Converter.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO expert and MPP) .
  • Seq Send MTF data.

Sequence Type 8 Current Cycle
24
MTF STEP 68 HCA PNO.2
  • MTF Step 68-HCA PNO.2 Fast Power Abort from PIC
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
  • Seq When I I_PNO Wait for TIME_PLATEAU_ZERO
    (30 s).
  • Seq Make the PIC provoke a Fast Power Abort
    (FPA).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP).
  • Seq Send MTF data.

Sequence Type 4 FPA
25
MTF STEP 70 HCA PNO.3a,b,c,d
  • MTF Step 70-HCA PNO.3a,b,c,d Heater Firing
  • Seq Switch on the power converter and go to
    I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s).
  • Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
  • Seq When I I_PNO Wait for TIME_PLATEAU_ZERO
    (30 s).
  • Op Pop-up window - Ask the QPS expert to fire
    all the quench heaters of the magnets in the
    list provided by MPP (one for each test).
  • Seq Wait creation of Post-Mortem data from PIC,
    Converter and QPS.
  • Seq Pop-up window - Test passed or failed?
  • Op Enter reply (AB/PO, QPS experts and MPP) and
    a comment about on which magnet the quench
    heaters were fired.
  • Seq Send MTF data.

Sequence Type 5 Heater Firing
26
MTF STEP 72 HCA PNO.4
  • MTF Step 72-HCA PNO.4 DCCT Calibration
  • Seq Pop-up window - Did PO perform properly the
    DCCT Calibration?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 9 DCCT
27
MTF STEP 78 HCA PNO.7
  • MTF Step 78-HCA PNO.7 No Icing Verification
  • Seq Pop-up window - Did the current leads
    perform properly during the PNO tests?
  • Op Enter reply
  • Seq Send MTF data

Sequence Type 6 Icing
28
Parameters
29
Magnets to quench in Sector 7-8
Write a Comment
User Comments (0)
About PowerShow.com