Title: RB'A78 Powering Procedure
1RB.A78 Powering Procedure
Not explained in this document
Mirko Pojer Matteo Solfaroli
Version from 15/06/2007
2MTF STEP 095 HCA PCC
- Configuration of the power converters
- Field Engineer OK to AB/PO for pre-test of the
power converters - Field Engineer Include converter in the Special
Test SOC - AB/PO Pre-test of the converter
- Field Engineer Set step passed (or not) in the
Sequencer - This operation is fully transparent to the
sequencer, it is only used to set the step passed - AB/PO will indicate in the daily meetings the
converters they want to pre-test. - The Field Engineer (HCC) is the responsible for
the proper flow of information and keeping the
Special Test SOC and the LSA DB updated.
3PIC2
- Seq or Op Pre-test of converters finished? IF
NOT stop test
4MTF STEP 28 HCA PLI1.1
- MTF Step 28-HCA PLI1.1 Current Cycle I_INJECTION
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_INJECTION at
DIDT_P2N. - Seq When I I_INJECTION Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq Switch off the converter.
- Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 1 Current Cycle
5MTF STEP 30 HCA PLI1.2
- MTF Step 30-HCA PLI1.2 Energy Extraction
Discharge - Extraction through QPS application (simulating a
bus-bar quench) - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INJECTION at
DIDT_P2N. - Seq When I I_INJECTION Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Request QPS EXPERT to Provoke an Extraction
Discharge. - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 2 Extraction Discharge
6MTF STEP 32 HCA PLI1.3
- MTF Step 32-HCA PLI1.3 Powering Failure from PC
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INJECTION at
DIDT_P2N. - Seq When I I_INJECTION Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Make the PC simulate a Powering Failure.
- Seq Wait creation of Post-Mortem data from PIC
and Converter. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP) .
- Seq Send MTF data.
Sequence Type 3 Powering Failure
7MTF STEP 34 HCA PLI1.4
- MTF Step 34-HCA PLI1.4 Fast Power Abort from PIC
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INJECTION at
DIDT_P2N. - Seq When I I_INJECTION Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Make the PIC provoke a Fast Power Abort
(FPA). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 4 FPA
8MTF STEP 36 HCA PLI1.5a,b,c,d
- MTF Step 36-HCA PLI1.5a,b,c,d Heater Firing
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INJECTION at
DIDT_P2N. - Seq When I I_INJECTION Wait for
TIME_PLATEAU_ZERO (30 s). - Op Pop-up window - Ask the QPS expert to fire
all the quench heaters of the magnets in the
list provided by MPP (one for each test). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP) and
a comment about on which magnet the quench
heaters were fired. - Seq Send MTF data.
Sequence Type 5 Heater Firing
9MTF STEP 40 HCA PLI1.7
- MTF Step 40-HCA PLI1.7 No Icing Verification
- Seq Pop-up window - Did the current leads
perform properly during the PLI1 tests? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 6 Icing
10MTF STEP 42 HCA PLI2.1
- MTF Step 42-HCA PLI2.1 Current Cycle I_INTERM_1
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_INTERM_1 at
DIDT_P2N. - Seq When I I_INTERM_1 Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq Switch off the converter.
- Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 1 Current Cycle
11MTF STEP 44 HCA PLI2.2
- MTF Step 44-HCA PLI2.2 Energy Extraction
Discharge - Extraction through QPS application (simulating a
bus-bar quench) - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_1 at
DIDT_P2N. - Seq When I I_INTERM_1 Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Request QPS EXPERT to provoke an Extraction
Discharge. - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 2 Extraction Discharge
12MTF STEP 45 HCA PLI2.2b
- MTF Step 45-HCA PLI2.2b Slow Power Abort from
PIC - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_1 at
DIDT_P2N. - Seq When I I_INTERM_1 Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Make the PIC provoke a Slow Power Abort
(SPA). - Seq Wait creation of Post-Mortem data from PIC
and Converter. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 7 SPA
13MTF STEP 46 HCA PLI2.3a,b,c,d
- MTF Step 46-HCA PLI2.3a,b,c,d Heater Firing
I_INTERM_1 - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_1 at
DIDT_P2N. - Seq When I I_INTERM_1 Wait for
TIME_PLATEAU_ZERO (30 s). - Op Pop-up window - Ask the QPS expert to fire
all the quench heaters of the magnets in the
list provided by MPP (one for each test). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP) and
a comment about on which magnet the quench
heaters were fired. - Seq Send MTF data.
Sequence Type 5 Heater Firing
14MTF STEP 48 HCA PLI2.4
- MTF Step 48-HCA PLI2.4 No Icing Verification
- Seq Pop-up window - Did the current leads
perform properly during the PLI2 tests? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 6 Icing
15MTF STEP 42 HCA PLI2.1a
- For Sector 7-8 the tests stop at I_INTERM_1 and
step 42 has to be repeated to check for magnets
stability. - MTF Step 42-HCA PLI2.1 Current Cycle I_INTERM_1
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_INTERM_1 at
DIDT_P2N. - Seq When I I_INTERM_1 Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq Switch off the converter.
- Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 1 Current Cycle
16MTF STEP 500 HCA PLI3.1a
- MTF Step 500-HCA PLI3.1a Current Cycle
I_INTERM_2 - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_INTERM_2 at
DIDT_P2N. - Seq When I I_INTERM_2 Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq Switch off the converter.
- Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 1 Current Cycle
17MTF STEP 52 HCA PLI3.2
- MTF Step 52-HCA PLI3.2 Energy Extraction
Discharge - Extraction through QPS application (simulating a
bus-bar quench) - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_2 at
DIDT_P2N. - Seq When I I_INTERM_2 Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Request QPS EXPERT to provoke an Extraction
Discharge. - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 2 Extraction Discharge
18MTF STEP 58 HCA PLI3.3a,b,c,d
- MTF Step 58-HCA PLI3.3a,b,c,d Heater Firing
I_INTERM_2 - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_2 at
DIDT_P2N. - Seq When I I_INTERM_2 Wait for
TIME_PLATEAU_ZERO (30 s). - Op Pop-up window - Ask the QPS expert to fire
all the quench heaters of the magnets in the
list provided by MPP (one for each test). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP) and
a comment about on which magnet the quench
heaters were fired. - Seq Send MTF data.
Sequence Type 5 Heater Firing
19MTF STEP 60 HCA PLI3.4
- MTF Step 60-HCA PLI3.4 No Icing Verification
- Seq Pop-up window - Did the current leads
perform properly during the PLI3 tests? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 6 Icing
20MTF STEP 500 HCA PLI3.1a
- MTF Step 500-HCA PLI3.1a Current Cycle
I_INTERM_2 - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_INTERM_2 at
DIDT_P2N. - Seq When I I_INTERM_2 Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq Switch off the converter.
- Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP).
- Seq Send MTF data.
Sequence Type 1 Current Cycle
21MTF STEP 62 HCA PLI4.1
- MTF Step 62-HCA PLI4.1 Energy Extraction
Discharge - Extraction through QPS application (simulating a
bus-bar quench) - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_INTERM_3 at
DIDT_P2N. - Seq When I I_INTERM_3 Wait for
TIME_PLATEAU_ZERO (30 s). - Seq Request QPS EXPERT to provoke an Extraction
Discharge. - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 2 Extraction Discharge
22MTF STEP 64 HCA PLI4.2
- MTF Step 64-HCA PLI4.2 No Icing Verification
- Seq Pop-up window - Did the current leads
perform properly during the PLI4 tests? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 6 Icing
23MTF STEP 66 HCA PNO.1
- MTF Step 66-HCA PNO.1 Current Loop Stability
PC Fail - Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_1 (120 s). - Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
- Seq When I I_PNO Wait for at least
TIME_PLATEAU_2 (240 s). - Op/Seq Pop-up window - during this waiting time,
the operator asks OK from AB/PO to go ahead
with the tests (current loop stability
confirmation). If the waiting time is longer
than TIME_PLATEAU_2 keep waiting. - Seq PLEP from I_INJECTION to I_MIN_OP at
-DIDT_P2N. - Seq When I I_MIN_OP Wait for TIME_PLATEAU_1
(120 s). - Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
- Seq Make the PC simulate a Powering Failure.
- Seq Wait creation of Post-Mortem data from PIC
and Converter. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO expert and MPP) .
- Seq Send MTF data.
Sequence Type 8 Current Cycle
24MTF STEP 68 HCA PNO.2
- MTF Step 68-HCA PNO.2 Fast Power Abort from PIC
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
- Seq When I I_PNO Wait for TIME_PLATEAU_ZERO
(30 s). - Seq Make the PIC provoke a Fast Power Abort
(FPA). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP).
- Seq Send MTF data.
Sequence Type 4 FPA
25MTF STEP 70 HCA PNO.3a,b,c,d
- MTF Step 70-HCA PNO.3a,b,c,d Heater Firing
- Seq Switch on the power converter and go to
I_MIN_OP. Wait for TIME_PLATEAU_ZERO (30 s). - Seq PLEP from I_MIN_OP to I_PNO at DIDT_P2N.
- Seq When I I_PNO Wait for TIME_PLATEAU_ZERO
(30 s). - Op Pop-up window - Ask the QPS expert to fire
all the quench heaters of the magnets in the
list provided by MPP (one for each test). - Seq Wait creation of Post-Mortem data from PIC,
Converter and QPS. - Seq Pop-up window - Test passed or failed?
- Op Enter reply (AB/PO, QPS experts and MPP) and
a comment about on which magnet the quench
heaters were fired. - Seq Send MTF data.
Sequence Type 5 Heater Firing
26MTF STEP 72 HCA PNO.4
- MTF Step 72-HCA PNO.4 DCCT Calibration
- Seq Pop-up window - Did PO perform properly the
DCCT Calibration? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 9 DCCT
27MTF STEP 78 HCA PNO.7
- MTF Step 78-HCA PNO.7 No Icing Verification
- Seq Pop-up window - Did the current leads
perform properly during the PNO tests? - Op Enter reply
- Seq Send MTF data
-
Sequence Type 6 Icing
28Parameters
29Magnets to quench in Sector 7-8