MA DG Collaborative - PowerPoint PPT Presentation

About This Presentation
Title:

MA DG Collaborative

Description:

Year 1 report 5/31/05. New interconnection process is working well ... QFs under PURPA. Which policy can they use? Year 1 report 5/31/05. DG and Distribution Planning ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 10
Provided by: rou2
Category:

less

Transcript and Presenter's Notes

Title: MA DG Collaborative


1
MA DG Collaborative Year 1
  • Tim Roughan
  • Director of Distributed Resources
  • Timothy.Roughan_at_us.ngrid.com
  • June 17, 2005
  • Restructuring Roundtable

2
Background
  • Different interconnection polices among the four
    MA utilities
  • Perception that customers not getting assumed
    benefits of DG
  • MA DTE issued 02-38 order in 2002
  • Authorized DG collaborative to standardize
    interconnection process
  • DTE approved statewide interim standard April
    2004
  • Authorized two year collaborative
  • Further enhance interconnection policy
  • Review DG and distribution planning
  • Additional work regarding network
    interconnections
  • Meter ownership

3
Year 1 report 5/31/05
  • New interconnection process is working well
  • 144 (18.5 MWs) applications from 4/1/04 to
    3/31/05
  • In MECo 13 requests 2003, 32 in 2004
  • NStar had 62 of all requests
  • Extensive tracking of projects
  • Tracking timelines and costs
  • Have suggested some process changes to
    interconnection tariff
  • If the ISO has to study a project, timelines may
    be extended
  • Requirement for wiring inspection
  • P1547 is now IEEE Standard 1547-2003

4
Year 1 report 5/31/05
  • Network system interconnection
  • Multiple primary sources feeding one or more
    customers
  • Issue arose whether you can delay protective
    functions to allow DG breaker to trip, however MA
    Utilities will not delay network protectors
    because it violates basic protection strategies
  • Need to find another solution
  • Meter ownership
  • QFs already can own their meter
  • QFs under PURPA
  • Which policy can they use?

5
Year 1 report 5/31/05
  • DG and Distribution Planning
  • Distribution Planning reviews
  • MECo 1,115 feeders, 295 substations
  • NSTAR 1,300 feeders, 300 substations
  • WMECo 271 feeders 43 substations
  • FGE 44 feeders 17 substations
  • Total 2,730 feeders 655 substations
  • Approximate allocation of capital budgets
  • Asset Replacement 25-40
  • Reliability 25-35
  • Capacity 30-45
  • To make the budget, projects typically have to
    resolve 2 or more of the above issues

6
Year 1 report 5/31/05
  • Beginning to work through some paper pilots to
    determine value and costs of DG installations in
    certain areas
  • Value to DG customer is reduced energy costs,
    which is a cost to the utility
  • Value from the utility is typically only from
    deferral for capacity projects in low-growth
    areas
  • Unless real sustained capacity is realized non-DG
    ratepayers likely will not benefit from DG
    installations
  • This may involve utility control of the DG
  • Or, enough DG to use diversity on a feeder by
    feeder basis
  • Could result in cross-subsidization by non-DG
    customers

7
Year 2 work plan
  • Any additional streamlining of tariff
  • Look at new FERC small gen process and how the
    ISO-NE will implement
  • Additional investigation of interconnecting to
    network systems
  • Are there other cost-effective solutions besides
    violating basic fault protection practices?
  • Continue working through the costs and benefits
    to all parties for DG on the distribution system

8
Year 2 work plan
  • Utility Congestion Relief Pilot (UCRP)
  • MTC is interested in testing DG value
  • Looking to work within MECos Lowell area
    targeted load response project
  • MECo pays 50/kWh for load shed, plus 3/kW for
    summer months as a retainer
  • Must be customer gt 200 kWs
  • Other possibilities being discussed for smaller
    customers including residential
  • MTC interested in projects with other utilities

9
Summary
  • A lot more time required than was assumed
  • This is not a simple issue, and it takes time to
    do it right
  • Need involvement from real customers
  • Need perspective of people who are not in the
    industry
  • New FERC rules will affect us
  • LICAP demand response customers can earn back
    their LICAP contribution
  • Small Generator rule how will this interact?
  • Comments due 6/23 to MA DTE on report
  • http//www.mtpc.org/renewableenergy/public_policy/
    DG/2005_annualreport.htm
Write a Comment
User Comments (0)
About PowerShow.com