Title: Landfill Gas Case Study: Lessons Learned and Design Considerations
1Landfill Gas Case Study Lessons Learned and
Design Considerations
- Lori A. Winters and Sean C. Paulsen
- MWIA/ESD 2009 Solid Waste Conference
2Discussion Outline
- Chronology of Events
- Response Activities
- Future Plans and Steps
- Lessons Learned
3In the Beginning
- Groundwater Monitoring Data and Results
- Dissolved iron and manganese
- Other inorganic constituents
- Landfill Gas Monitoring Results
- Methane levels increase along western boundary
- Unable to tune field to control LFG
4Redox Sensitive Parameters
- Redox sensitive parameters generally unreliable
for monitoring - Field sampling variability
- Well construction materials
- Landfill construction
Dissolved Iron
Dissolved Manganese
5Inorganic Indicators
- Conservative parameters more reliable for
landfill impacts - Not influenced by oxidation processes
- PROBLEM only indicate leachate impact
Chloride
Dissolved Potassium
Nitrogen-Ammonia
Dissolved Sodium
610,000 Foot View
- Iron and manganese initially increased along
north - Oldest portion of the landfill in northwest
corner - Focus initial investigation on northwest
Zone of initial increases2004-2005
7Landfill Gas Contours
Percent Methane in Landfill Gas Extraction Wells
8Landfill Gas Contours
Percent Oxygen in Landfill Gas Extraction Wells
9Results of Contouring
- Northwest corner has relatively low gas
production - Oxygen levels in northwest corner are relatively
high - Pulling harder will create NSPS or plant problem
- Lack of gas wells in central portion of landfill
- Other potential sources for LFG?
1010,000 Foot View (Part 2)
- Iron and manganese begin to increase along south
landfill boundary - No migration issues along south unable to
control west - Change the focus of the investigation
- Relationship between the two areas?
Zone of initial increases2004-2005
Zone of later increaseslate 2007
11Redox Sensitive Parameters
- Redox sensitive parameters generally unreliable
for monitoring - No VOCs or gas parameters
- Added dissolved methane analyses
Dissolved Iron
Dissolved Manganese
12Groundwater Contour
- Channel Fill Aquifer stretches between two zones
where methane detected - Geology is an old stream channel
- Need to determine potential as a migration pathway
13Hydrogeologic Investigation
Cross-Section Location Map
14Hydrogeologic Investigation
- Two aquifer zones Channel Fill and Outwash
Aquifer - Channel Fill Aquifer also extends between west
and south boundaries - Clay lined cells in north and central portion of
landfill
Unsaturated zone
East-West Cross-Section
15Hydrogeologic Investigation
- Cells 1 and P are double-composite lined cell
- Cells N and O recompacted clay liner
- Is the construction of composite cells over clay
lined cells adding to the problem?
North-South Cross-section
16Piggyback Liner
Area with CompactedClay Liner
Area of PiggybackOverliner
Gas Well Location Map with Piggyback Liner Areas
17Problems
- Older, clay lined areas are overlain by composite
lined cells gas collection system essentially
abandoned during construction - Landfill gas in older portion of landfill is
trapped beneath lined areas - Rules dont allow penetration of piggyback liner
- Due to pressure build-up, landfill gas in older
cells moving through clay liner into subsurface
18Response Actions
- Source area appears to be central portion of
landfill - Met with MDEQ to discuss options
- Complete pilot boring using hollow stem auger and
split spoon samples - Locate depth of piggyback liner
- Monitor methane levels
- Grab samples to determine moisture content of
waste material
19Response Actions (cont.)
- Install first round of piggyback wells
- Single well only bentonite seal at and above
piggyback liner - Install dual extraction wells
- One above and one below liner
- Install out-of-waste collectors on west side
20Completion of Pilot Borings
- Piggyback liner settled an average of 10
- Waste material located above piggyback liner very
dry - Waste material below piggyback liner variable
moisture - Incr. moisture content incr. gas production
21Dual Gas Well Detail
- Both wells constructed of Schedule 80 PVC
- Ten foot thick bentonite seal placed at piggyback
liner 5 above and below - 1 to 3 stone backfill placed around slotted
portion - Minimum 2 between slots and seal
22Installation of Dual Gas Wells
- Six dual wells total of ten piggyback wells
- Two wells installed in each 36 diameter boring
- 6 well is shallow installed above liner
- 8 well is deeper below liner
23Install Out-of-Waste Collectors
- Continued control issues with subsurface landfill
gas levels along western boundary - Methane concentrations further indicate source is
not northwest corner, but newer waste - Installed 3 out of waste collectors along western
boundary to control methane - Collectors have been successfully controlling gas
for approx. 2.5 months - Condensate sump critical and very active
24Out-of-Waste Collectors
- Three wells along west perimeter to intersect
Channel Fill - 200 foot spacing
- 3 PVC well with 2 well head
- Condensate sump is the key to system operation
25Next Steps
- Continue Gas Extraction from New Gas Wells
- Since new wells, gas production increased from
1400 to 1900 scfm - Half of the difference from piggyback wells
- May need additional piggyback wells?
- Continue Out-of-Waste Collection
- Maintain gas levels along landfill boundary
- Continue Monitoring Sensitive Parameters
- Dissolved iron and manganese
- Dissolved methane
26Landfill Gas Contours
Percent Methane in Landfill Gas Extraction Wells
27Chemistry Changes
- Since install of new wells, diss. iron levels
have stabilized or decreased - Diss. methane has stabilized or decreased
- Diss. methane typically responds first, and
inorganics follow
Dissolved Iron
Dissolved Methane
28Lessons Learned
- Normal leachate indicators may not identify gas
issues - Redox sensitive parameters function well as
landfill gas indicators - Source isnt always obvious think big picture
- If gas is potential source, include dissolved
methane testing VOCs dont always show up - No quick fix issues take time to resolve
29Lessons Learned (cont.)
- Plan for gas extraction before installing
piggyback liners - Passive vs. active
- Tweak dual well design
- Re-evaluate function of piggyback liners
- Some states dont require piggyback liners
- The gas is where the moisture is
- Condensate sump critical to out-of- waste
collectors
30