Title: Chris Fears


1
UK Link Technology Refresh
  • Chris Fears
  • December 2007

2
Progress Since Last Update
  • OAT 2 phases Jun-Oct 07 Oct-Jan 08
  • OAT1 machine build confirmation Completed
  • OAT2 performance testing, operational
    schedules, support processes, fall back and
    recovery etc. Started
  • Internal penetration testing conducted, 3rd party
    penetration testing planned
  • UAT Nov end Jan Started
  • Shipper trials Completed
  • 3rd Full scale trial migration added
  • Detailed implementation planning under way

3
Shipper Trial Update
  • Tests have successfully concluded
  • File transfer connectivity between the Shipper
    locations and new UK Link Data Centres has been
    proven
  • NOM files were successfully received, loaded
    processed
  • NMR, COS and MDR files were issued to
    participants who confirmed the file formats and
    content was as expected
  • Participants confirmed successful loading and
    processing of all files issued
  • 1 file was sent to a wrong directory due to a
    configuration error in IX
  • Lesson - Check file location configurations prior
    to implementation
  • Lesson - Tightened up the file exchange approval
    mechanism
  • Delivery receipts successfully received for all
    files issued from the new system

4
Testing Updates
  • OAT is 80 complete
  • Completed back up and fail over tests
  • Scheduler testing planned for 19/12
  • UAT is 88 complete
  • Performance testing ongoing looking good

5
Cut-over and Implementation
  • Outage still planned at 4 days
  • Detailed implementation planning activities
    ongoing
  • Looking at cut-over activities and catch-up
    processing
  • Back-out plans also being drawn up
  • MOD proposal 184 drafted to include
  • 2 partial non-business days for SPA processing
    and queries (25th 26th Feb)
  • 4 days relief from data logger liabilities
    (24th-27th Feb)

6
Cutover Approach
  • Data cutover
  • Will start 3 weeks in advance of main cutover,
    then will require delta data updates
  • This will have no effect upon the operational
    service
  • Final cutover starts 22nd/23rd February 2008
  • REC invoice to be issued early on Friday 22nd
    due dates will be unchanged
  • Other production runs on 22nd will be unchanged
  • Outage start time
  • Start after Datalogger issue on Saturday 23rd
    confirmed as optimal approach

7
Major Milestones
8
Go/No-Go Decision Points
9
System Impacts
10
Implementation Concerns Mitigations (1)
  • Data Corruption
  • IBM conducting a health check on the migration
    and validation processes
  • Replaced manual checks with scripted , repeatable
    checks
  • System performance
  • No adverse performance observed during testing
  • All testing done on production sized environments
  • Back Outs
  • As part of the Dress Rehearsal we will practise
    the back out steps
  • Once we have propagated the data to the systems
    of others we will be in a fix forwards
    situation

11
Implementation Concerns Mitigations (2)
  • Checkpoints
  • The implementation will have a series of go/no-go
    points identified
  • Expanded the number of health checkpoints during
    implementation
  • Both time and event driven
  • Will hold files and validate before release
  • Communications
  • Will be using the xoserve web site for general
    updates
  • Specific updates around the implementation will
    go to the standard distribution lists (UKLC and
    Operations)
  • Will use the existing xoserve teams for
    communications

12
Next Steps
  • IBM to complete assurance of testing and data
    migration approach
  • Completion of OAT Phase 2
  • Includes completion of 3rd party penetration
    testing
  • Progress UAT to completion
  • Finalise Implementation Planning
  • Plan detailed activities for Dress Rehearsal
  • Define and refine back out processes
  • Enhance the go/no go and escalation criteria
  • Finalise catch-up and return to normal operation
    plan