Title: RECOVERABLE ITEMS REPORT (WIR)


1
RECOVERABLE ITEMS REPORT (WIR) ON-LINE PROCESS
HANDLER (WOLPH) Reengineering Project Status
Brief for Materiel Readiness Integrated Product
Team 24 August 2006
2
Background
  • WOLPH is to provide Marine units with an online
    method of requesting disposition instructions
    for excess equipment from the Item Managers at
    LOGCOM.
  • WOLPH is used to manage WIRs in a Web based
    application using LOTUS Domino.

3
IPT Members
  • (Chairperson)
  • (C4 Asst Chairperson)
  • (C4 Application Developer)
  • (C4 Functional Analyst)
  • (C4 Application Host)
  • (C4 Application Host)
  • (Functional User)
  • (Program Assistant)

4
Project Plan
Project Title Recoverable Items Report (WIR)
On-Line Process Handler (WOLPH) Re-Engineering
Project Short Title WOLPH Re-Engineering
Project Purpose Re-engineer the WOLPH systems
in an Oracle Relational Database to enable DoD
Information Technology Security Certification and
Accreditation Process (DITSCAP).
5
Project Scope Status
  • Task 1 Project Kickoff (COMPLETED)
  • Form team
  • Define team roles
  • Identify required skills
  • Identify resources
  • Assign roles to resources
  • Team formed
  • Task 2 Envisioning (ONGOING)
  • Risk Management

6
Project Scope (cont)
  • Task 3 Scope (COMPLETED)
  • Draft Charter
  • Sign Charter
  • Develop POAM
  • Present to Upper Management
  • Present to Executive Steering Committee
  • Finalize POAM
  • Task 4 Analysis/Software Requirements
  • Determine Oracle Licenses - COMPLETED
  • Collect Documentation
  • System Source Codes - COMPLETED
  • Data Dictionaries Not available from contractor
  • Tables Not available from contractor

7
Project Scope Status
  • Task 4 Analysis/Software Requirements (contd)
  • Structure of Database Not available from
    contractor
  • Users Manual - Not available from contractor
  • Review Documentation
  • System Source Codes - COMPLETED
  • Data Dictionaries - Not available from contractor
  • Tables - Not available from contractor
  • Structure of Database - Not available from
    contractor
  • Users Manual - Not available from contractor
  • Document Requirements - COMPLETED
  • Decompose Requirements - COMPETED
  • Review Lotus Notes Software - COMPLETED

8
Project Scope Status
  • Task 5 Design (COMPLETED)
  • Define Hardware Requirements
  • Determine storage requirements
  • Locate web server
  • Locate Oracle database server for development,
    testing, and production
  • Task 6 Security (ONGOING)
  • Develop IA documentation
  • Task 7 Development (In Process)
  • Convert Lotus Code to Oracle

9
Project Scope Status
  • Task 8 Testing
  • Develop Test Plan (In Process)
  • Perform Technical Testing (Not Started)
  • Analyze Test Results and Debug - (Not Started)
  • Perform Functional Testing - (Not Started)
  • Analyze Test Results and Debug - (Not Started)
  • Task 9 Training
  • Develop Training Manual - (In Process)
  • Train Users - (Not Started)

10
Project Scope Status
  • Task 10 Implementation - (Not Started)
  • Run Parallel Production Systems
  • Turn Off Parallel System
  • Deployment Production System
  • Re-engineering Complete