CO2 capture ready options for coalfired power plants - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

CO2 capture ready options for coalfired power plants

Description:

Basis: Draft Study on CO2 capture ready plants' commissioned by the IEA GHG ... Plan for retrofit should be based on state-of-the-art technology and account for ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 12
Provided by: Kay7193
Category:

less

Transcript and Presenter's Notes

Title: CO2 capture ready options for coalfired power plants


1
CO2 capture ready options for coal-fired power
plants

Kay Damen
2
Rationale
  • Basis Draft Study on CO2 capture ready plants
    commissioned by the IEA GHG
  • Application of environmental permits for various
    coal-fired power plants
  • No investments in CO2 capture are to be expected
    in the absence of economic incentives or
    legislation
  • How can we assure that plants can be retrofitted
    with CO2 capture in a later stage?

3
Capture ready interpretations
  • Considerations, measures and investments (mostly
    spatial and technical by nature) that enable a
    power plant to be retrofitted with CO2 capture
    (and storage) in a later stage and still be
    economical to operate
  • As a minimum, a capture-ready plant should have
    eliminated all the factors that would prevent a
    retrofit taking place

4
General issues (1)
  • Access to CO2 storage reservoir
  • Plan for CO2 transport
  • Space should be available for addition of plant
    items (CO2 capture, compressors, piping), access
    to existing plant items, storage of equipment
    during construction
  • Auxiliary plant should be sized to meet ultimate
    demand (with capture) or be developed with a
    costed strategy to expand initial installation
  • Possibilities for integration

5
General issues (2)
  • The design should either minimise significant
    change in major items of equipment when capture
    is fitted or have a clearly identified and costed
    strategy identified by which necessary changes
    could be implemented, accounting for downtime
  • Utilisation of any near-zero cost options for
    increasing the flexibility for subsequent plant
    upgrades

6
Dilemma of technological progress
  • Further improvements in CO2 capture technologies
    are to be expected
  • Hence investments incurred now may appear
    obsolete at the time the plant is retrofitted (or
    are not economically justified)
  • Plan for retrofit should be based on
    state-of-the-art technology and account for
    impacts of future developments

7
Capture ready issues PC post-combustion capture
(1)
  • Boiler. Minimising impact of CO2 capture by
    selecting high-efficiency boiler (ultra
    supercritical conditions).
  • FGD. SO2 concentration limits in the flue gas of
    10 mg/Nm3 for amines. Solutions
  • Install highly-efficient FGD right away
  • The initial FGD may have to be capable of being
    upgraded
  • Add additional polishing unit
  • Other considerations SO2 concentration pipeline
    and storage (EOR)

8
Capture ready issues PC post-combustion capture
(2)
  • Steam cycle. Extraction of low-pressure steam
    from the IP turbine exhaust (IP to LP crossover
    pipe). Solutions
  • Remove 1 LP turbine () lowest energy penalty
  • (-) requires accurate prediction of steam demand
  • Throttled LP turbine (valve to keep crossover
    pressure constant) () flexible in steam
    extraction (-) throttling losses
  • Select turbines that operates well under
    different conditions than nominal specifications
    are can be adapted (flexibility, intermediate
    energy loss)
  • Add back-pressure turbine (no capture ready
    option)

9
Capture ready issues IGCC pre-combustion
capture (1)
  • Combustion. H2 has other combustion properties
    than syngas, modification of GT burners (fuel
    nozzles). To avoid NOx emissions increase due to
    higher flame T, N2 or steam must be injected. N2
    from ASU (additional compressor)
  • De-rating. LHV fuel is reduced when shifting to
    H2. Over dimension coal logistics, ASU, fuel
    pipes to GT. Add additional gasifier.
  • Steam cycle. Less steam available for expansion,
    select turbines that operate well under
    non-nominal conditions. HRSG performance will
    also change due to change in radiative properties
    of the combustion products

10
Discussion
  • Apart from space requirements etc, the issue of
    capture ready is mainly study obligation?
  • Capture ready issues should be restricted to
    capture and not transport and storage?
  • What is a credible sink? To what extent should
    the suitability and availability of storage
    reservoir be studied/accounted for?
  • Additional impacts, energy requirements and costs
    IGCC are lower than for PC. Does that make IGCC
    more capture ready than PC?

11
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com