Title: Introduction to Central Services Branch
1DCS PORTFOLIO COMMITTEE PRESENTATION NEW
CORRECTIONAL CENTRES
Introduction to Central Services Branch Building
a caring correctional system that truly belongs
to all
Date19 February 2008
2CONTENTS
- General background on building New Facilities
- 8 New Facilities
- Confirming information shared with Portfolio
Committee - Value for Money
- Risks transfer
- Managing Risks and Integrity
- Current status and Project Phases
- Status of Kimberley Correctional Centre.
3GENERAL BACKGROUND ON BUILDING NEW FACILITIES
- Department identified the need for building new
facilities in 2002 - Building was to be undertaken in two phases
subjected to the Prototype Design (completed in
2004) - First phase following 4 sites identified
- Leeuwkop (Sandton).
- Nigel.
- Klerksdorp.
- Kimberley.
- Second phase following 4 sites
- Polokwane.
- Paarl (Allandale).
- Port Shepstone.
- East London.
4CONFIRMING INFORMATION SHARED WITH PORTFOLIO
COMMITTEE
- Leeuwkop Correctional Centre was stopped due to
Environmental Impact Assessment recommendations.
The project has been suspended till the outcome
of the viability study undertaken by Department
of Public Works is available. - Polokwane site identified, could not be acquired
at a reasonable market value, which considerably
delayed the project and was excluded
provisionally from the rest of the projects. - Continue..
5CONFIRMING INFORMATION SHARED WITH PORTFOLIO
COMMITTEE (Continue1)
- A feasibility study report was presented to the
Portfolio Committee on 6 November 2007 - Report provided for Nigel and Klerksdorp
Correctional Centres that were added to the
remaining three which resulted in feasibility
studies for five centres
6VALUE FOR MONEY
- The Transaction Advisor recommended in the
feasibility study that the PPP procurement option
is best value for money. This was determined
based on the Regulation 16 process that was
followed - Feasibility and Options Analysis performed on a
specified and pre-agreed output specification
indicated that - PPP is best option in terms of
- Value for Money
- Risk Transfer and
- Affordability.
7RISKS TRANSFER
- Construction risks transferred to private party.
- (Management of delays and cost overruns by
private party) - Facilities management (maintenance of facilities
and return after 25 years of operation in good
condition by private party). - Management of operations
- Security risks
- Health risks
- Provision of programmes risks (education,
corrections, social skills, etc)
8MANAGING RISKS AND INTEGRITY
- Every participant in the government signs
Confidentiality Contract, Code of Conduct and
Declaration of Interests including Transaction
Advisor. - Vetting process of all evaluation members.
- Continuous auditing both by internal and external
auditors. - Separation of responsibilities of evaluation
between three tiers of evaluation committees.
9CURRENT STATUS AND PROJECT PHASES
- Scope
- Each Centre providing 3000 beds.
- Category Medium and Maximum offenders.
- Contract Term 2 Year construction 25 years
opera- tions. - Compliance with Broad Based Black Economic
Em-powerment (BBBEE). - Request For Qualification (RFQ) bids closed on 10
December 2007 for five new PPP Correctional
Centres. - Responses received five bidders for each of the
project. - No late submissions for RFQ received.
- Bid Evaluation is in progress.
10CURRENT STATUS AND PROJECT PHASES
- RFQ Evaluations to be completed by end April
2008. - Request for Proposal (RFP) documents to be issued
shortly after RFQ evaluations complete and
short-list announced. - RFP submissions expected back September 2008.
- Whole process in terms of PPP regulations,
Regulation 38 of PFMA and DCS Supply Chain
Management. - Process to be verified continuously by DCS
Internal Audit.
11STATUS OF KIMBERLEY CORRECTIONAL CENTRE
- Aerial photo of the construction of New
Kimberley Generation Correctional Centre.
12STATUS OF KIMBERLEY CORRECTIONAL CENTRE (Continue
1)
- Background
- Kimberley is the first of the original eight (8)
to be built with
a capacity of 3000 offenders. - Construction information.
- Tender from Grinaker-LTA/Keren Kula R662 343
119 - Site Hand over date 14 Nov. 2006
- Contract period 24 months
- Original completion date 14 Nov.
2008 - Extended completion date Feb. 2009
- Percentage work completed 35.00
- (As on the 31 January 2008)
13STATUS OF KIMBERLEY CORRECTIONAL CENTRE (Continue
2)
14STATUS OF KIMBERLEY CORRECTIONAL CENTRE (Continue
3)
- Labour force.
- Total workforce 1172
- Present Local Labour workforce component
1099 - Present ex-offender workforce
137 - National Youth Service 90
- Present female workforce component
91 - Present HDI workforce (14 contractors)
- Contract Participation Goal of total contract
29.79
15STATUS OF KIMBERLEY CORRECTIONAL CENTRE (Continue
4)
- Detail on cost of project.
- Contract price excluding VAT R 581
million - Contract Price Adjustment Provision
- (escalation) R 100
million - VAT R 96 million
- Budget allowed for project R 810 million
- (includes 5 allowance for unforeseen costs)
16 QUESTIONS? THANK YOU Renewing our Pledge A
National Partnership to Correct, Rehabilitate and
Reintegrate Offenders for a safer and secure
South Africa