Ground Equipment Staging Program (GESP) or USMC Long Term Equipment Storage Program

Description:

NEW GEAR. DRMO. Long Term Benefits. Increased equipment readiness for ... 15 Jan 04 III MEF/LOGCOM SITE SURVEY/VISIT. 30 Jan 04 LOGCOM DEVELOPS COST ESTIMATES ... – PowerPoint PPT presentation

Number of Views:234
Avg rating:3.0/5.0
Slides: 27
Provided by: ltcolw
Category:

less

Transcript and Presenter's Notes

Title: Ground Equipment Staging Program (GESP) or USMC Long Term Equipment Storage Program


1
Ground Equipment Staging Program (GESP)
orUSMC Long Term Equipment Storage Program
MARINE CORPS LOGISTICS COMMAND
  • Presented to
  • MRIPT Conference
  • 24 August 2004

LtCol Ron Wallace Dir, Mat Dist Dept DSN
567-5501
2
Background


THOUGHT PIECE
HQMC directed Redefine T/E Definition Reduce
Unit Maintenance Burden Balance T/E of 100
vs. Personnel and funding Less than 100


LOGCOM Initiative 2002-2004
3
Concept of Operation
Storage
Mvmt to Storage Location
Equipment Withdrawal
Preservation
ID Equip
Maintenance (Care in Stores)
II
III
IV
I
Phase I MARFOR(s) identify equipment for
storagePhase II Movement to storage
locationPhase III Equipment will be preserved,
stored and maintainedPhase IVEquipment will
withdrawn from the facility (contingency or stock
rotation)
4
Administrative Storage
Ground Equip Storage Program (GEPS)
Contractor / LOGCOM
Using Unit
Long Term Storage
Ready to Roll
Example
Unit Rates 10. CO determines unit requires four
(TA). Six go into GESP. Two R/R FOUR into LTS
5
Strategic Pause
  • OIF I
  • MSP Reconstitution
  • OIF II

6
Lessons Learned
  • Force Structure Review Group (FSRG)
  • Provisional Units
  • Strategic Position of Assets (Fwd in Stores)
  • Remain Behind Equipment (RBE) Mgmt
  • NBC Consolidated Storage Facility (CSF)
  • MARFORRES
  • Controlled Humidity Protection (CHP)
  • USMC Base Regionalization

7
Current Status
Contract Support LOGCOM will enlist contract
support in order to move the initiative forward
and bring program management support and emerging
technologies to the table. Funding. Funding is
in place for 12 months of program support.
Statement of Work Request for Proposal (RFP)
Underway.
8
Road Ahead
  • IPT Will reconvene this fall.
  • Three Phased Approach
  • Program requirement development and specification
    determination
  • Implementation
  • Execution
  • LOGCOM Msg to provide Marine Corps with GESP/LTS
    Program Update and Road Ahead

9
Questions?




10
BACK UP SLIDES




11
Integrated Planning
INTEGRATED STAFFS
LOGBASES MATCOM
  • Define Process
  • Ownership
  • Withdrawal
  • Rotation
  • Readiness reporting

I MEF
IPT
III MEF
II MEF
MARFORs
  • Disciplined Approach to Planning
  • Helps to
  • Share Information
  • Satisfy the Customer (warfighter)

Commander
Warfighter
12
Courses of Actions (COAs)

II MEF
  • COA (s) will be tailored for each MEF
  • The key factors that differentiate COAs are
    storage location and program administration
  • All COAs are required to address the access of
    equipment by the MEFs in the event of a non-MPS
    contingency
  • Cost estimates will be developed for each COA

13
I MEF Courses of Actions (COAs)
OPTIONS
  • 1. Local Storage
  • Government Administered
  • 2. Local Storage
  • Contractor Administered
  • 3. Regional Storage
  • Government Administered
  • 4. Regional Storage
  • Contractor Administered
  • Other COAs as Applicable

I MARINE EXPEDITIONARY FORCE
MCLB BARSTOW
29 PALMS
CAMP PENDLETON
MCAS MIRAMAR
MCAS YUMA
14
II MEF Courses of Actions (COAs)
OPTIONS
  • 1. Local Storage
  • Government Administered
  • 2. Local Storage
  • Contractor Administered
  • 3. Regional Storage
  • Government Administered
  • 4. Regional Storage
  • Contractor Administered
  • Other COAs as Applicable

II MARINE EXPEDITIONARY FORCE
MCAS CH. PT
CAMP LEJEUNE MCAS NEW RIVER
MCAS BEAUFORT
MCLB ALBANY
BICmd
15
III MEF Courses of Actions (COAs)
OPTIONS
  • 1. Local Storage
  • Government Administered
  • -Contractor Administered
  • 2. Regional Storage
  • Government Administered
  • Contractor Administered

III MARINE EXPEDITIONARY FORCE
MCAS IWAKUNI
JAPAN
KANEOHE BAY
OKINAWA
HAWAII
16
Equipment Rotation Program
STORAGE
TECOM
NEW GEAR
DRMO

DEPOT
MPS/Norway
FLEET
17
Long Term Benefits
Increased equipment readiness for the
warfighter Warfighters relief from the current
maintenance burden Improves LOGCOMs ability to
manage ground weapon systems/SECREPs Weapon
Systems availability and maintainability is
improved over the life cycle resulting in lower
ownership cost
18
Long Term Benefits
Improve the scheduling and forecasting of depot
level maintenance program (DLMP)
requirements Improve forecasting of parts
requirements to support depot maintenance
production Stabilize the master work
schedule Improve and formalize equipment
rotation over a broader spectrum of weapon
systems
19
OEF OIF I OIF II
COA Development was completed but never staffed.
T/E Initiative took a strategic pause during
Operation Enduring Freedom/Iraqi Freedom.
20
Additional Requirements
In July 2003, the Deputy Commandant for IL
tasked LOGCOM to expand the T/E Policy Initiative
to include the reserves. Additionally, LOGCOM
was directed to establish and administer the
controlled humidity protection (CHP) program to
coincide with the T/E Policy Initiative.
21
July 2003
T/E Initiative Planning commenced with III
MEF Ground Equipment Staging Program
22
MPS Constitution OIF II OEF MMC-8 (MARITIME
MAINT CYCLE) RBE (REMAIN BEHIND EQUIPMENT)
Initiative continued but planning and equipment
storage requirements impacted by the events
listed above.
23
DRAFT POAM
Date Action 30 OCT T/E POLICY IMPLEMENTATION
BRIEF AT MATERIEL DIST CONF, ALBANY, GA 15
Nov LOGCOM Msg to provide Marine Corps with T/E
Initaitive Program Update and Road
Ahead. III MEF msg to MCLAT directing
Revalidation of Supported Unit
TOEs Supported Unit COs must categorize
TA/RTR/LTS MSC MEF aggregate/harvest data
collection MSC CGs must endorse the
TA/RTR/LTS values to MEF MARFORCPAC
concurrence with III MEF data/ products 15 Dec
III MEF EQUIPMENT NOMINATIONS AND DATA TO
LOGCOM
24
DRAFT POAM
Date Action 15 Jan 04 III MEF/LOGCOM SITE
SURVEY/VISIT 30 Jan 04 LOGCOM DEVELOPS COST
ESTIMATES 5 Feb 04 STAFF COST EST AND GESP
PRODUCTS WITH III MEF 28 Feb 04 T/E POLICY
IMPLEMENTATION IPT MEETING 5 Mar 04 PROVIDE
BRIEFS AND COST EST TO III MEF 25 Mar 04 PROVIDE
COA BRIEFS TO DC, I L TBD PROVIDE COA BRIEFS
AND IMPLEMENTATION PLAN TO MROC TBD BEGIN
IMPLEMENTATION OF MROC APPROVED COAs
25
Unresolved Issues
Readiness Reporting Policy. Plans, Policy and
Operations (PPO) will assist in the develop of
readiness reporting policies and
procesures. Funding. The T/E initiative
currently represents an unfunded project. The
analysis effort conducted jointly with the
MARFORs and LOGCOM during course of action (COA)
development will provided data to assist in
financial decisions. Stock/Equipment Rotation
Plan. The key to achieving a return on
investment, though long term in nature, from the
T/E Policy Initiative is through efficiencies
realized by effective equipment rotation.
26
GROUND EQUIPMENT STAGING PROGRAM
  • Definitions of Table of Equipment
  • T/E T/A RTR LTS
  • T/E---- Table of Equipment
  • T/A ----Training Allowance
  • RTR ---Ready to Roll
  • LTS--- Long Term Storage
  • Previous IPT unanimously agreed that MPS should
    not be
  • included in the T/E formula

Action Item III MEF PWG needs to validate this
concept