Keck NGAO Proposal: Management Overview - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Keck NGAO Proposal: Management Overview

Description:

NGAO is ready to become a real project: Ready to begin system design phase ... Need to take advantage of expertise & resources at CIT, UC & WMKO in system design ... – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 17
Provided by: cney1
Category:

less

Transcript and Presenter's Notes

Title: Keck NGAO Proposal: Management Overview


1
Keck NGAO ProposalManagement Overview
  • Presenter
  • P. Wizinowich
  • SSC Meeting
  • June 21, 2006

2
Presentation Sequence
  • Development Process
  • NGAO Project
  • Schedule, WBS, Budget
  • System Design Phase
  • Deliverables, Plan, Schedule, Budget
  • Management status next steps

3
WMKO Development Process
We are here Next step
4
NGAO Project Milestones
Year Month Milestone
06 July System design phase starts
07 June 1st major funding secured
07 Sept System Design Review
08 Dec Preliminary Design Review
10 Mar Detailed Design Review
12 Mar AO LGS facility pre-ship reviews
12 Dec NGS 1st light
13 Jun LGS 1st light
13 Dec Shared-risk science begins
  • This is only a first-cut timeline

5
NGAO Project Top-level WBS
PW
6
NGAO Project AO Budget
  • AO Cost Estimate 35M ? 10M
  • Estimation approach 1 Comparison to other
    systems
  • Gemini-S MCAO - 18M in 03 dollars.
  • Add 7M for 2 additional lasers 4 inflation ?
    29M
  • Gemini-S GPI - 19M 6M reserve
  • Add 15M for LGS subtract 5M for instrument ?
    35M
  • TMT NFIRAOS - 25 for AO 24M for LGS
  • Subtract 10M for simpler system ? 39M
  • Estimation approach 2 Bottoms-up cost estimate

Estimation methods agree
7
NGAO Project Instrument Budget
  • Cost Estimate 20M ? 4M for 1st three
    instruments

Instrument ROM Cost Anchor
Near-IR Imager 3M G-S NIR imager 3.5M 1 vs 4 H2-RG
Visible Imager 3M LRIS-R upgrade 1.5M camera/filters 1M SW 0.5M
Deployable NIR IFU 14M TMT IRMOS 42M for 10 IFU AO 1.6M/IFU for 6
Near-IR IFU 7M OSIRIS 5.5M new detector
Visible IFU 4.5M OSIRIS without full cryo, 4x4K deep depletion CCD, slicer
Thermal NIR Imager 3M Similar to NIR, smaller but more expensive detector
8
System Design Objectives
  • Establish design approach that meets the
    scientific user requirements
  • Establish discipline integrated engineering plan
    for the proposed design
  • Understand technical risks, trade-offs,
    performance estimates, cost to completion
  • Key deliverables
  • Systems Requirements Document
  • System Design Manual
  • Systems Engineering Management Plan
  • Systems Design Report

9
System Design Project Schedule
  • Plan based on delivery of 4 key documents
  • Plan includes schedule person-hours

10
System Design Project Schedule
  • System requirements need science team effort
  • Budget includes 3 graduate students 1 postdoc

11
System Design Project Schedule
  • System design will utilize expertise resources
    at CIT, UC WMKO

12
System Design Project Schedule
  • System Engineering Management Plan

13
SD Risk Assessment Management
  • Detailed risk assessment spreadsheet produced
  • 40 items identified during initial point design
    development
  • Severity probability of each item indicated
    along with risk mitigation plan
  • During system design each risk area will be
    further addressed as either part of the planned
    trade studies /or as part of risk assessment
  • Risk management process includes balancing
    scientific technical performance, cost
    schedule

14
System Design Budget
  • Cost Estimate 980k
  • Basis
  • 12400 hrs or 6.4 FTE eng/scientist 120k/yr
    770k
  • 5500 hrs for 3 grad students postdoc 150k
  • 40k for travel 20k for procurements
  • Only 3 of total NGAO budget ? system design
    phase budget may be low
  • Believe we have properly identified path forward
    have a clear idea of how to proceed
  • A more detailed estimate will be prepared as
    individuals identified next level of detail
    added to plan

15
Management Status
  • Observatory Directors plan to define the NGAO
    management structure
  • More detailed NGAO system design phase planning
    awaits management structure resolution
  • NGAO ready to become a real project

16
NGAO Project Next Steps
  • NGAO is ready to become a real project
  • Ready to begin system design phase
  • The project needs the following key personnel
  • Principal Investigator
  • Project Scientist Science Team
  • Project Manager
  • Systems Engineer
  • NGAO Project Scientist science team lead
    development iteration of science requirements
  • Volunteer model unsustainable
  • Need to take advantage of expertise resources
    at CIT, UC WMKO in system design
  • Form NGAO Science Advisory Committee to provide
    high level science guidance