Title: Zachary Department of Civil Engineering
1Regional Workshop on Public-Private Partnership
in Highways
UNCERTAINTY AND OPTIONS IN PPP PROJECTS
Ivan Damnjanovic, Ph.D. Assistant Professor
- Zachary Department of Civil Engineering
- Texas AM University
Belgrade, June 7, 2006
2BENEFITS OF PPP PROJECTS
- GOVERNMENT
- Foreign Direct Investment, Increased Mobility,
Fostered Development, - CONCESSIONAIRE
- Profit
- CONTRACTOR
- Profit
3HOW ARE DECISIONS MADE?
- WHY WE NEED TO KNOW THIS?
- To provide incentives for investment
- To identify and understand the risk
- To evaluate benefits
- RISK and OPPORTUNITY
- UNCERTAINTY
- Traffic
- Performance
- Financial
- Political
4UNCERTAINTY
TRAFFIC PREDICTION
PAVEMENT PERFORMANCE PREDICTION
5IMPACT OF UNCERTAINTY ON CASH FLOW
X
95 CI
6DECISIONS TO INVEST IN PPP PROJECTS
- IRREVERSIBLE INVESTMENTS
- invest NOW
- wait-and-see
- OPPORTUNITY COST!
HIGH UNCERTAINTY HIGH OPPORTUNITY COST
wait-and-see POSITION
TO ENCOURAGE INVESTMENT - ALLOW FLEXIBILITY
7RISK MITIGATION OPTIONS - FLEXIBILITY
- TRAFFIC UNCERTAINTY
- Option to Disinvest
- Stage-based Construction
- Option to Expand
- PERFORMANCE UNCERTAINTY
- Performance-based Warranties
8OPTION TO DISINVEST
- OBJECTIVE To provide an option for investor to
sell the facility to government (at the end of
period T for a discount price) in case of
unfavorable realization of traffic demand - EFFECT Reduces irreversible sink cost of the
investment - EUROPEAN PUT OPTION
9STAGE-BASED CONSTRUCTION
- OBJECTIVE To provide an option for investor to
engage in a multistage construction of the
facility as traffic demand realizes - EFFECT Reduces initial sink cost of the
investment and allows for expansion in case of
favorable realization of traffic demand (reduces
opportunity cost)
10OPTION TO EXPAND
- OBJECTIVE To provide an option for investor to
expand the facility (add lanes or add additional
sections) in order to capitalize on opportunity
when there is a favorable realization of traffic
demand - EFFECT Reduces of the opportunity costs
11PERFORMANCE-BASED WARRANTIES
- OBJECTIVE To provide an option for the investor
to mitigate performance-related risks of the
constructed facility to contractors - EFFECT Reduces of the opportunity costs
- WARRANTY SERVICING COST
- (RISK COST)
12TYPE OF WARRANTIES
- Short-term Warranties
- Long-term Warranties
- Maintenance Warranties
13SYSTEM CHARATERIZATION
14PERFORMANCE UNCERTAINTY
DESIGN
CONSTRUCTION
MANAGEMENT
Design Equations
Material Properties Construction
Processes Construction Blunders
Utilization Natural Hazards Maintenance
Effects Rehabilitation Effects
15RiskPave QUANTIFICATION OF RISK COST
16SUMMARY
- To attract investment allow flexibility but
understand risks. - Adverse effects of high traffic uncertainty can
managed using contract options. - Adverse effects of high performance uncertainty
can be managed using performance-based
warranties.
17Thank you for your attention.