Title: Project Update / New R


1
Project Update / New RD Proposal
  • M. Hebert

2
Outline
  • The New RD Proposal for FY03
  • Stepping up project formalism in SOWs, cost, and
    schedule tracking
  • Looking into another, possibly more user
    friendly, cost and schedule software system
  • Status of the Muon Beamline subcontract
  • More tweaks to the MECO web site
  • Things that I should have finished by now but
    havent

3
Since The Last Meeting
  • Brad Smith has accepted the position of Solenoid
    SSM and his appointment has been approved of or
    concurred with by all those who must
  • Notified of 610k RD grant which should be in
    hand this week
  • Issued RFP for Industrialization Studies
    details in Bills talk
  • Received six bids in round 1
  • Funding three and reopening the RFP to encourage
    additional bids
  • Poised to commence Interim Base Support for
    William Mary and Houston from that money as
    well
  • Magnet Acquisition Panel meeting next weekend to
    recommend the best procurement strategy to the
    SSO again Bills talk
  • Attempting to arrange a preliminary review of the
    CDR by appropriate safety committees to get
    feedback for the Technical Specifications
  • NSF has encouraged us to apply for additional RD
    funds in FY03, proposal is due by 9/26 effectively

4
Balancing Needs vs. Budget
  • Although NSF cannot know how much they will have
    to work with in FY03, they suggest that we aim
    for a total request similar to our previous one
    year proposal, i.e. 3M
  • The goal in developing the budget remains to
  • Keep the critical path on schedule as much as
    possible, which primarily means keeping the
    magnets on course
  • Keep the existing collaboration together and
    expand it if possible
  • Preferentially investigate items with the
    greatest cost or technical risk
  • Operationally that means maintaining
  • Funding for tasks leading to the tightest
    possible solenoid Technical Specifications and
    RFP package
  • Detector RD efforts needed for collaboration
    building
  • Studies focused upon higher technical risk items

5
Tasks Funded on Existing RD Money
  • Tasks that we have funded or will cover out of
    the new grant include
  • MIT-PSFCs Solenoid Conceptual Design Report
  • Magnet Industrialization Studies at least
    three, perhaps more
  • Part-time Solenoid Subsystem Manager support
  • Tracker RD at Houston and UCI
  • Calorimeter RD at NYU
  • Cosmic Ray Shield RD at William Mary
  • Interim base support for Houston and William
    Mary
  • Water-cooled target studies at UCI
  • Full-time Project Manager support
  • Internal Reviews

6
FY03 Request 1
  • AGS Studies - 158k
  • Bunched Beam Extraction Studies at g 8, assumed
    parasitic to RHIC
  • Beam Instrumentation
  • Proton Beamline - 363k
  • Shielding design
  • Lambertson magnet designs
  • Instrumentation controls design
  • RF Modulated Magnet conceptual design, but no
    prototype
  • Production Target Shield - 85k
  • Further stress analyses of radiation-cooled
    target
  • Heat and Radiation Shield design
  • Target handling and mounting system design
  • Solenoids - 304k
  • Tolerance/robustness studies
  • The remaining half of the Subsystem Manager
    support

7
FY03 Request 2
  • Muon Beamline - 233k
  • Collimator, Beam Stop, Absorber, and Shield
    designs
  • Detector supports and installation procedure
  • Much reduced cost vacuum system design
  • Stopped muon spectra measurements at TRIUMF
  • Straw Tracker - 809k
  • Prototype low mass manifold
  • Reengineering the Elefant chip
  • Mechanical engineering support at UCI
  • Seamless straw development at Osaka
  • Calorimeter - 503k
  • An 8 x 8 prototype crystal array including
    photodetectors, cooling, calibration, and readout
    electronics
  • An electrical engineer for readout electronics
    development and a technician to assist in crystal
    and readout prototype construction
  • Beam testing of the prototype array

8
FY03 Request 3
  • Cosmic Ray Shield - 103k
  • Salary for a technician to assist with module
    extrusion and testing
  • Mechanical design of the passive shield
  • Data Acquisition and Online Computing - 249k
  • Support for BUs Electronics Design Facility
  • Components, prototype boards, test equipment
  • Project Management - 296k
  • AGS Liaison Physicist and Liaison Engineer
    support
  • Cost and Schedule software system, training
  • BNL contracting officer support
  • Internal reviews
  • Total 3.10M

9
Tasks Deferred to Reach 3M
  • AGS Studies
  • Bunch Intensity Studies
  • Proton Beamline
  • Prototype module of RF magnet
  • Beam instrumentation other than the target
    station area
  • Production Target
  • Fabrication testing of W sample pieces for
    rad-cooled target
  • Design of the cooling and monitoring systems for
    the water-cooled option
  • Solenoids
  • Engineering Design of the Solenoids
  • Additional engineering staff support for the SSM
  • Muon Beamline
  • A portion of the detector installation studies
  • Project Management
  • Support for Cost and Schedule Manager

10
Ratcheting Up Project Formalism
  • Moving toward a more systematic approach to
    establishing performance goals and tracking
    progress via three mechanisms
  • Statements of Work from a standard boilerplate
  • A version of this exists now, borrowed from MINOS
    and tweaked
  • It includes clear statements of deliverables,
    roles of responsible persons, estimated costs,
    schedule milestones, and appropriate signatures
  • We have used this for the Muon Beamline work here
    at BNL and the target work at UCI. In the next
    iteration of contracting we will use it for all
    subcontract SOWs
  • Tracking cost and schedule performance on the RD
    money
  • With the increasing level of funding this is
    becoming more awkward to keep track of without a
    standard approach
  • My hope is to use a new form of software to
    handle this, but if that cant be arranged in a
    timely fashion I will put together a simple
    spread sheet to fill in
  • Regular teleconferences

11
Professional Grade Cost Software
  • Given the delay in the project start we have the
    time to look at alternatives to the system that
    US ATLAS generously provided us
  • Whatever system we go with, we want it installed,
    tested, and to have people familiar with it prior
    to the receipt of construction funds
  • Requirements
  • ONE repository of ALL cost information to avoid
    having to merge data at intervals and suffer
    through resolving conflicts later in the game
  • Easy secure access to that repository from
    anywhere
  • Cost and schedule data intimately linked for each
    task
  • A simple, intuitive interface for most users
  • All the bells whistles for a few power users
  • My current favorite is Primavera used by LIGO,
    NIF, NJDOT, and numerous corporations, although
    there are other commercial options

12
Primavera
  • WYSIWYN Role based functionality
  • Primavera Project Planner aka P3E functions
    as a combination of MS Project and the Access
    cost database system we have now
  • Methodology Manager Stores best practices
    info
  • Primavision Web-based team leader tool basic
    WBS editing, cost schedule tracking, and
    reporting
  • Progress Reporter Simple web-based,
    time-card-esque cost and schedule progress
    reporting tool for Pis
  • A tool for automatic document version control is
    included as well
  • Looks promising, but requires a couple of tweaks
  • I am in discussions with a company that
    specializes in installation training of
    Primavera systems
  • Part of the costs for software, training, etc.
    are in the new budget proposal so that we can see
    if this will meet the need

13
Muon Beamline Effort
  • My statement that we could start work in July
    proved false, but the last hurdle has actually
    been cleared and a contract is being prepared for
    signatures now
  • There are a few other prerequisites to kicking
    off work
  • We must determine what window material we will
    likely be using as this is nearly entirely driven
    by the physics, rather than engineering,
    requirements
  • We need to get a subset of the CDR drawing
    package available on the web for BNL use
  • We expect to have an initial, sketch level design
    by early November and the final report by the end
    of that month
  • With a little luck we will obtain additional
    funding to develop designs for other areas of the
    muon beamline to build some momentum here

14
Additional Web Site Updates
  • Sylvia and I have continued to evolve the design
    of the internal web site, primarily in developing
    pages for each of the level 2 WBS which include
  • Links to relevant TDR section Technical Memos
  • Links to presentations about the subsystem
  • Links to drawings, requirements documents, QA
    documents, ESH docs
  • Links to cost and schedule estimates and progress
    tracking
  • Still more to do to make the site as useful as
    possible for the project
  • Establish a repository of approved plots,
    tables, parameter lists
  • Establish a MECO bibliography including
    electronic copies of useful references if possible

15
Still on the To Do List
  • Reference Design I still havent updated this
    to include the Calorimeter, the Tracker, or the
    details of the Cosmic Ray Shield. I believe that
    October is probable
  • Another pass through the Management Plan needs to
    happen and has not yet