City of Port Angeles Combined Sewer Overflow CSO Program - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

City of Port Angeles Combined Sewer Overflow CSO Program

Description:

City of Port Angeles Combined Sewer Overflow CSO Program – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 13
Provided by: ssp60
Category:

less

Transcript and Presenter's Notes

Title: City of Port Angeles Combined Sewer Overflow CSO Program


1
City of Port Angeles Combined Sewer Overflow
(CSO) Program
  • For Rayonier Inc
  • January 15, 2009

2
CSO Program Update
  • Location and magnitude of problem
  • Regulatory Background
  • Projects (Phases 1 2)
  • Current Issues
  • Moving Forward

3
(No Transcript)
4
Over Flow Locations aerial
5
Combined Sewer Overflows
  • Total of 30-100 events per year at the four
    remaining CSO outfalls
  • Each event can be 10 gallons to 12 million
    gallons
  • Duration of an event can be 5 minutes to multiple
    overflows in 1½ days

6
Combined Sewer Overflows
  • Public Education and Notification
  • Public Notices at each location
  • Notify LEKT, DOH, DOE, Arthur D. Feiro Marine
    Life Center, City staff, County at beginning, end
    of each event
  • Annual notification to utility customers

7
Regulatory Background
  • CSOs are regulated under the WWTPs NPDES Permit
    since 1991
  • Updated CSO Plan Sept.06
  • 2 phases of projects total 32 to 42M
  • Agreed Order Oct.06, amended July 07
  • Annual CSO Reports to DOE

8
Two Options to Deal With CSOs
  • Disconnect sources of stormwater inflows into
    the sewer system
  • Increase capacity of sewer collection system
    convey to WWTP and/or CSO outfalls

9
Objective
  • Increase capacity of sewer collection system
    convey to Citys Waste Water Treatment Plant

10
Option 1 - Disconnect Sources of Stormwater
  • Disconnection Pilot Project 2001-03
  • Estimated to cost 35-50M, not including addl
    cost for necessary Stormwater infrastructure
    improvements
  • Work phased over many years

11
Option 2 - Increase Capacity of Collection System
  • Review of this option included need for storage
    upstream of WWTP
  • Estimated to cost 35-42M
  • Complete by 2015
  • Minimal Stormwater improvements necessary
  • Preferred alternative

12
Two Phases
  • Estimated cost 35M to 42M
  • Complete by 2015

13
Phase 1 Projects
  • Projects, w/estimated Construction costs
  • Force Mains, Oak St. to WWTP - 5.1M
  • Francis St. Park diversion - 2.9M
  • Storage Tank modifications - 2.4M
  • Flow diversion facility, pump
  • station WWTP modifications - 5.0M
  • Bridge over Ennis Creek - 1.5M
  • Total 16.9M

14
Phase 1 Projects
  • Insert map here

15
Phase 2 Projects
  • Downtown Gravity Sewer Mains
  • New Pump Station 4
  • Additional WWTP Improvements
  • Total Estimated Phase 2 Cost 22M

16
Phase 1 Design Stalled
  • Design on hold since June 2008
  • Need to complete permitting, which requires
    additional onsite investigations
  • Rayonier has not authorized permanent use, nor
    onsite access
  • Meeting with DOE Oct 2008

17
Project Milestones
  • Access to Rayonier property
  • 10-12 months to complete design
  • Design/permitting work to restart NLT April 1
  • Oct 2010 DOE SRF Loan application deadline
  • SRF funds available Summer 2011

18
Delay Issues
  • Design on hold
  • Not meeting terms of Agreed Order
  • Unable to obtain addl loan funding

19
  • More Background

20
Key Relationships
  • LEKT
  • DOE
  • Harbor Works PDA
  • Rayonier

21
Lower Elwha Klallam Tribe
  • Design must respect cultural aspects and Tribal
    interests on site including
  • Site history
  • Avoid ground disturbance
  • Restoration of Ennis Creek
  • Future LEKT sewer connections

22
Department of Ecology
  • Enforce Agreed Order (Water Quality Program)
  • Support of Rayonier Clean Up and Redevelopment
    (Toxics Cleanup Program)

23
Harbor WorksPublic Development Authority (PDA)
  • Set up with 3 parallel, but separate, goals
  • CSO Project Tank on Rayonier Site
  • Harbor Planning
  • Assist in Remediation and Re-development of
    Rayonier Mill Site

24
How Did We Plan ToAcquire the Tank
  • Buy it, along with south half of property.
  • OR
  • Acquire it as part of Larger Plan
  • Trade For Citys Assistance In Cleanup And
    Redevelopment
  • OR
  • Acquire only tank and easements for associated
    pipelines and CSO facilities

25
  • How are we moving forward?

26
Next Steps
  • Step 1
  • Present plan to Rayonier, show that CSO efforts
    are not detrimental to property redevelopment
    may actually enhance site and speed up
    redevelopment efforts
  • Step 2
  • Enter into purchase agreement with Rayonier
  • Step 3
  • Amend Agreed Order to extend Phase 1 deadline

27
Questions ?
Write a Comment
User Comments (0)
About PowerShow.com