Interconnection Update Jay Zimmerman Manager, Transmission Policy - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Interconnection Update Jay Zimmerman Manager, Transmission Policy

Description:

... issued a Notice of Extension of Time on October 7, 2003, granting requests to ... Credits are required only for transmission delivery service taken with respect ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 11
Provided by: brian568
Category:

less

Transcript and Presenter's Notes

Title: Interconnection Update Jay Zimmerman Manager, Transmission Policy


1
Interconnection UpdateJay Zimmerman Manager,
Transmission Policy
  • Entergy Transmission Planning Summit
  • New Orleans, LA
  • July 8, 2004

2
Interconnection Update
  • Total of 187 requests for Interconnection Studies
    including cancelled studies and duplicate studies
    for the same project
  • Currently 0 requests in Queue

3
Interconnection Operating Agreements (IOA)
  • Entergy has filed over 60 IOAs with FERC for
    new/existing generating facilities representing
    approximately 36,000 MW
  • 19 IOAs representing approximately 7,600 MW have
    been cancelled (some were for existing generation
    and others were proposed)
  • 3 new generation projects representing
    approximately 1,760 MW have either suspended
    construction before completion or suspended
    operation after completion
  • Approximately 25,000 MW of new/existing
    generation is operating/capable of being operated

4
FERC Interconnection Final Rule Order Nos. 2003
and 2003-A
  • Order No. 2003 Standardization of Generator
    Interconnection Agreements and Procedures issued
    July 24, 2003
  • FERC issued a Notice of Extension of Time on
    October 7, 2003, granting requests to extend the
    effective date of the Final Rule and the date on
    which compliance filings were due to January 20,
    2004

5
Order No 2003 Compliance Filings
  • For all non-independent Transmission Providers
    (TP), FERCs Order No. 2003 deemed their OATTs to
    be revised to include the pro forma Large
    Generator Interconnection Agreement and
    Procedures on January 20, 2004
  • Non-independent TPs were directed to make
    ministerial filings reflecting those revisions to
    their OATT in their next filings with the
    Commission
  • Any non-independent TPs seeking a variation from
    the pro forma LGIP and LGIA based on existing
    regional reliability standards must inform FERC
    on or before January 20, 2004
  • After January 20, 2004, any non-independent TP
    may separately file proposed changes to its LGIP
    and LGIA under FPA Section 205 using the
    consistent with or superior to standard

6
Large Generator Interconnection Order on
Rehearing Order No. 2003-AMarch 5, 2004
  • Higher Of Ratemaking Policy
  • Where rolling in the costs of network upgrades
    incurred for an interconnection would have the
    effect of raising the average embedded cost rate
    paid by existing customers, the Transmission
    Provider may elect to charge an incremental cost
    rate to the interconnection customer and thereby
    fully insulate existing customers from the costs
    of any necessary system upgrades. However, under
    no circumstances may a non-independent
    Transmission Provider charge an Interconnection
    Customer both an incremental cost rate and an
    embedded cost rate associated with existing
    network transmission facilities.

7
Order on Rehearing Addresses Pricing Concerns
Raised on Rehearing
  • Clarify that the TP continues to have the option
    to charge the higher of an average embedded
    cost rate or an incremental cost rate for Network
    Upgrades
  • Clarify that up-front funding and crediting are
    only to facilitate financing of the Network
    Upgrades
  • Modify two features of the crediting policy
  • Credits are required only for transmission
    delivery service taken with respect to the
    interconnecting Generating Facility
  • TP has option after 5 years to return outstanding
    balance or continue to provide credits based on
    actual transmission delivery service taken from
    Generating Facility

8
Types of Interconnection Service
  • Energy Resources Interconnection Service (ERIS)
  • Provides as-available access to transmission
    service at Point of Interconnection
  • Network Resource Interconnection Service (NRIS)
  • Allows Generating Facility to be a Network
    Resource, subject to congestion provides a more
    flexible and comprehensive interconnection service

9
Types of Interconnection Service(Continued)
  • Neither ERIS or NRIS convey any right to the
    delivery component of transmission service
  • NRIS does not ensure delivery to specific loads
    or locations
  • TP is able to perform additional studies and
    require construction of upgrades necessary to
    fulfill a subsequent request for delivery service
  • TP may propose NRIS procedures that are
    compatible with regional practices under the
    consistent with or superior to standard
  • NRIS (an interconnection service) is not a
    replacement for NITS (a delivery service)

10
Entergy Regional Reliability Compliance Filing
Pursuant to Order No. 2003-A
  • Consistent with SERC Planning Standards, ERIS
    studies will include the requirement that Entergy
    perform a regional transfer capability analysis
  • Consistent with SERC Planning Standards, requests
    for ERIS require that the interconnection
    customer perform a reactive power analysis and
    provide results to Entergy
  • Consistent with NRC regulations, as part of the
    Interconnection System Impact Study process a
    nuclear plant off-site power analysis is
    required, if applicable
Write a Comment
User Comments (0)
About PowerShow.com