Goonyella%20Coal%20Chain - PowerPoint PPT Presentation

About This Presentation
Title:

Goonyella%20Coal%20Chain

Description:

The new Integrated Planning process will be undertaken across three planning horizons: ... work planned on a critical asset, as defined in the critical asset ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 35
Provided by: alans80
Category:

less

Transcript and Presenter's Notes

Title: Goonyella%20Coal%20Chain


1
  • Goonyella Coal Chain
  • Integrated Planning Group
  • Mine Update
  • March 2006

2
Presentation Overview
  • GCC Improvement Program Status
  • Key Coal Chain Concepts
  • Integrated Planning Process
  • Changes seen by the Mines
  • Integrated Planning Communication

3
GCC Status
  • Goonyella Coal Chain Improvement Group (GCCIP) is
    transitioning over to
  • the Coal Planning Steering Group (CPSG) with
    stakeholder representation
  • from
  • Babcock Brown Infrastructure
  • QR Network Access
  • QRNational
  • DBCT Pty Ltd
  • DBCT User Representative
  • BMA
  • This group will provide strategic direction for
    the Integrated Planning Group
  • (previously known as the GCCIP project working
    party.)
  • QR Network Access will chair and facilitate this
    group.

4
GCC Status
CPSG top down strategy Providing the strategic
direction for IPG
GCCIP Strategy Feeding information up, focus on
operational level
5
GCC Status
  • The Integrated Planning Group has representation
    from the following stakeholders
  • DBCT Team Lead representative Dan Flynn
  • QRNational Team Lead representative Mario
    Chetcuti
  • QR Network Access Team Lead representative Mark
    Henrich
  • DBCT User Mine representative Greg Stevens
  • BMA is representing their port and mines through
    Jeff Edwards.
  • Industry have agreed that QRNA will facilitate
    the integrated planning function on
  • behalf of the coal chain.

6
GCC Status
Handover at April meeting
First Meeting May
CPSG
IPG
Name change in line with official launch of CPSG
7
Why Integrated Planning?
  • To maximise system throughput by a coordinated,
    transparent approach to
  • identifying and implementing improvements
  • reducing system variability and loss
  • building strategic Infrastructure Plans
  • planning process
  • planned maintenance
  • communications and information flow

8
Why Integrated Planning?
  • In 2009/10 throughout required to be in the order
    of 135 - 140 mtpa
  • If we continue operating under the same
    processes, the variability will still exist and
    cause throughput loss.
  • Opportunity to reduce system loss by
    understanding the system in detail, installing
    rigid planning and operational processes and
    measuring the outcomes
  • Solution capital expenditure on coal chain
    infrastructure AND new operating mode to maximise
    throughput (integrated planning approach)
    including reducing variability

9
Goonyella Coal Chain Defined
Pit Operations
ROM transport, wash plant etc
Mine Stockpile
End Users
Port Stockpiles and Outloading
Mine Train Loadout
Rail Transportation
Port Inloading
Shipping Stem
Mine Loadout to Vessel Hatch
10
Key Concepts
  • The Coal Supply Chain
  • Demand Systems Pull and push
  • Planning Horizons

11
The Coal Supply Chain
12
The Coal Supply Chain
Demand Vessel ETA Tonnage Load Point
Supply Coal Availability Capability
Statements Load Point

Critical Asset Capability Maintenance
Outages Upgrade and commissioning plans


Available System Throughput This and knowledge
of system variability become the basis for
Planning eg when you are getting your trains and
when your ship will be loaded
13
Demand Systems
  • Supply chain management systems fall into three
    categories Push, Pull or a hybrid push/pull
  • While a push system process depends on forecast
    demand, a pull system starts from actual demand -
    the customers order, and uses some types of
    just-in-time processes eg rapid cargo assembly.
  • Generally, push systems require larger volumes of
    inventory as production may not necessarily match
    Demand in the short medium term
  • A pull system operates with minimal inventory and
    requires an order to commence supply
  • Push/pull systems typically have a mix of the
    above options

14
Pull System - DBCT
  • DBCT operates a pull system from the mines
  • DBCT throughput and stockpile capacity together
    with its multi-user status requires a cargo
    assembly, pull system
  • A vessel nomination and associated parcel
    definition (ie tonnes and load point) starts the
    planning process
  • Each vessel cargo is built into discrete
    components at the correct quality
  • Limited stockpile space means high throughput is
    achieved by low stockpile residence time
  • No Vessels No Trains

15
Pull System - DBCT
  • Pull system may have some effect on Mine Product
    stockpiles
  • Faster cargo assembly will increase the mean time
    between stock offtakes.
  • Peak stockpile levels may be higher than historic
  • Impact low if the vessel arrival pattern is smooth

16
??? System - HPS
17
Planning Horizons
  • The new Integrated Planning process will be
    undertaken across three planning horizons
  • Long Term Planning - a rolling monthly plan
    covering months 5 24 from the current day of
    operation
  • Tactical Planning - a rolling weekly plan
    covering weeks 3 17 from the current day of
    operation
  • Operational Planning - a rolling daily plan
    covering 0 14 days from the current day of
    operation which includes a detailed 0 - 48 hour
    schedule component
  • The Tactical and Long Term planning processes
    will focus on highlighting and resolving
    imbalances between demand, mine supply and
    available capacity
  • The Operational planning process will focus on
    reducing the current system variability and
    maximising coal chain throughput by using more
    accurate and timely vessel and mine product
    availability information to drive coal chain
    plans

18
Integrated Planning Timeframe
  • TO BE ADVISED

19
Stabilisation
  • Reducing variability within the coal chain
    requires
  • Information that is accurate, timely and
    transparent
  • Processes are currently being built to allow
    information flow and detail to improve
  • Robust processes
  • For example, if a train is cancelled what process
    is always followed to ensure loss to the system
    is minimised
  • A detailed understanding of each link in the
    chain
  • For example, a load point or port unload system
    needs to have a defined capability that can be
    the basis for scheduling

20
Stabilisation a mine perspective
  • The coal loading plan needs definition
  • A Load Point Capability Statement is to be built
    and will contain the data vital for planning eg
    planned load times, recharge allowance between
    trains, allowances for coal type changes
  • The Load Point Capability Statement will be
    reviewed regularly with the Operator.
  • The more accurate the data, the more likely
    trains will arrive, load, depart and unload at
    the planned time. This means
  • Loss is minimised
  • Process is measurable
  • Opportunities are identifiable

21
Stabilisation a mine perspective
  • Train consists will be standardised to
  • 20 x 9,600 tonne trains
  • 1 x 9,000 tonne train
  • MineTrak is being updated to facilitate
    information flows
  • For example - Advice when parcel will be
    available for railing
  • HPS ?????

22
Long Term / Tactical Planning
  • Highlighting and resolving imbalances between
    demand, supply and available capacity
  • The Long Term/Tactical Forum will be achieve this
    through implementation of
  • Critical Asset Register
  • Critical activity calendar
  • Coordinated Planning
  • Capacity Management
  • Utilising contract, marketing and shipping
    forecasts
  • Simplistic capacity determination
  • Long term planning time amounts months
  • Tactical planning time amounts weeks
  • Business Rules

23
Operational Planning
  • Coordinate information, share information and
    planning on
  • Mine forecasts
  • Critical Asset Calender
  • Shipping arrivals/orders
  • Berthing Plan
  • Yard plan
  • Rail scheduling
  • Operational Planning Time amounts days
  • Business rules

24
Operational Planning Horizon
25
Operational Planning Horizon
HPS Version ???
26
Day of Operations
  • Execution of plan focusing on running ..
  • Loading trains
  • Railing
  • Unloading
  • Stockpiling
  • Shiploading
  • .. And recovering to plan using
  • Business rules
  • Recovery Plan
  • Information transparency
  • Plan will be in the form of a 48 hour schedule

27
Key Changes for Mines
  • Long Term and Tactical Planning Horizons
  • Provision and maintenance of Critical Asset
    Register and Calender information
  • Available system capacity can be defined with
    sufficient notification to enable demand to align
  • Any interruption to capability (coal flow or
    maintenance) of a critical asset MUST go through
    the Integrated Planning Process
  • Provision of Demand information
  • Capacity balancing will be undertaken monthly for
    the 524 month horizon and weekly for the 317
    week horizon Assessment of demand and supply
    together with Maintenance alignment using a
    simple capacity analysis tool

28
Key Changes for Mines
  • Operational Planning Horizon
  • DBCT berthing plans will look out 14 days instead
    of the current 7 days and will drive the planning
    and scheduling of the DBCT stockyard and the rail
    network
  • Hay Point demand will be in the form of inloading
    request by sequence at the pits.
  • Operational plans and schedules will be updated
    and communicated to all stakeholders on a daily
    basis
  • Emergency, essential and opportunity maintenance
    requirements will be communicated to all relevant
    stakeholders
  • Mines will confirm coal is on the ground and
    ready for loading onto trains a minimum of 24 hrs
    prior to any 48 hour schedule in which trains are
    to be run to the mine
  • Minimising coal supply variability
  • Consistent sequencing of trains to align with
    requirements of yard and berthing schedule
  • A detailed berthing, yard and rail schedule will
    be defined by Plan at 48 hours from execution and
    will be made visible to all stakeholders
  • Train configurations will be standardised across
    the system 90 x 106 t 30 x 90t (9600 t)

29
Key Changes for Mines
  • Performance
  • Performance framework currently under
    construction
  • Framework intent to focus on stabilisation then
    improvement measureable KPIs to allow
    systematic improvement
  • Ports, trains, track and mines will be measured
    and reported on
  • Performance
  • Information quality and timeliness

30
Business Rules - Mines
  • Any work planned on a critical asset, as defined
    in the critical asset register, must be
    communicated in line with the integrated planning
    process to eliminate the possibility of unknown
    activities impacting on coal chain performance
  • Planned maintenance will be locked in at 21
    days or more depending on the lead time. No
    further changes may be made to planned durations
    or start dates within this lock down period
  • All significant, planned maintenance, asset
    upgrades and asset commissioning activities will
    be submitted at least 12 months out from the
    current day of operation. Changes to planned
    durations and start dates may occur until the
    greater of the 21 day lock down or planning lead
    time is reached

31
Business Rules - Mines
  • If DBCT does not receive parcel, vessel and mine
    information at specified times or it is altered,
    the vessel will cede berthing priority until
    these requirements are met
  • Parcel assembly plans must be agreed 7 days out
    from vessel ETA
  • 24 hours ahead of any 48 hour rail schedule, all
    mines will need to confirm the availability of
    coal on the ground and the readiness to load all
    trains which will be run in that 48 hour schedule
  • Further business rules will be developed during
    operating plan design across all planning
  • horizons.
  • Recovery Plan is to be developed in conjunction
    with internal operational stakeholders.

32
IP Communications
  • GCC Web Portal
  • Common interface for stakeholders to view
    performance, plans, meeting agenda's, minutes,
    and timetables
  • Web site is secure and open to GCC nominated
    stakeholders only (administered)
  • During IP implementation, regular updates will be
    forwarded to nominated site representatives and
    posted to the web portal
  • Regular forums will enable additional information
    flow
  • Long term/Tactical forum
  • SOMM

Web Portal View ?
33
IP Project Implementation
  • Stabilisation approximately 15 May 2006
    (Operational Planning, DOO, business rules,
    recovery plan)
  • Leading up to the 15th, operating plans, recovery
    plan and business rules will be workshopped.
  • Long Term Tactical planning progressing with
    processes rolling out
  • Training supply chain package under development
  • IT systems (information sharing). GCC web portal
    under development

Slide 18 or here
34
IPG Objective Maximise throughput whilst
maintaining service levels
Write a Comment
User Comments (0)
About PowerShow.com