Title: Goonyella%20Coal%20Chain
1- Goonyella Coal Chain
- Integrated Planning Group
- Mine Update
- March 2006
2Presentation Overview
- GCC Improvement Program Status
- Key Coal Chain Concepts
- Integrated Planning Process
- Changes seen by the Mines
- Integrated Planning Communication
3GCC Status
- Goonyella Coal Chain Improvement Group (GCCIP) is
transitioning over to - the Coal Planning Steering Group (CPSG) with
stakeholder representation - from
- Babcock Brown Infrastructure
- QR Network Access
- QRNational
- DBCT Pty Ltd
- DBCT User Representative
- BMA
- This group will provide strategic direction for
the Integrated Planning Group - (previously known as the GCCIP project working
party.) - QR Network Access will chair and facilitate this
group.
4GCC Status
CPSG top down strategy Providing the strategic
direction for IPG
GCCIP Strategy Feeding information up, focus on
operational level
5GCC Status
- The Integrated Planning Group has representation
from the following stakeholders - DBCT Team Lead representative Dan Flynn
- QRNational Team Lead representative Mario
Chetcuti - QR Network Access Team Lead representative Mark
Henrich - DBCT User Mine representative Greg Stevens
- BMA is representing their port and mines through
Jeff Edwards. - Industry have agreed that QRNA will facilitate
the integrated planning function on - behalf of the coal chain.
6GCC Status
Handover at April meeting
First Meeting May
CPSG
IPG
Name change in line with official launch of CPSG
7Why Integrated Planning?
- To maximise system throughput by a coordinated,
transparent approach to - identifying and implementing improvements
- reducing system variability and loss
- building strategic Infrastructure Plans
- planning process
- planned maintenance
- communications and information flow
8Why Integrated Planning?
- In 2009/10 throughout required to be in the order
of 135 - 140 mtpa - If we continue operating under the same
processes, the variability will still exist and
cause throughput loss. - Opportunity to reduce system loss by
understanding the system in detail, installing
rigid planning and operational processes and
measuring the outcomes - Solution capital expenditure on coal chain
infrastructure AND new operating mode to maximise
throughput (integrated planning approach)
including reducing variability
9Goonyella Coal Chain Defined
Pit Operations
ROM transport, wash plant etc
Mine Stockpile
End Users
Port Stockpiles and Outloading
Mine Train Loadout
Rail Transportation
Port Inloading
Shipping Stem
Mine Loadout to Vessel Hatch
10Key Concepts
- The Coal Supply Chain
- Demand Systems Pull and push
- Planning Horizons
11The Coal Supply Chain
12The Coal Supply Chain
Demand Vessel ETA Tonnage Load Point
Supply Coal Availability Capability
Statements Load Point
Critical Asset Capability Maintenance
Outages Upgrade and commissioning plans
Available System Throughput This and knowledge
of system variability become the basis for
Planning eg when you are getting your trains and
when your ship will be loaded
13Demand Systems
- Supply chain management systems fall into three
categories Push, Pull or a hybrid push/pull - While a push system process depends on forecast
demand, a pull system starts from actual demand -
the customers order, and uses some types of
just-in-time processes eg rapid cargo assembly. - Generally, push systems require larger volumes of
inventory as production may not necessarily match
Demand in the short medium term - A pull system operates with minimal inventory and
requires an order to commence supply - Push/pull systems typically have a mix of the
above options
14Pull System - DBCT
- DBCT operates a pull system from the mines
- DBCT throughput and stockpile capacity together
with its multi-user status requires a cargo
assembly, pull system - A vessel nomination and associated parcel
definition (ie tonnes and load point) starts the
planning process - Each vessel cargo is built into discrete
components at the correct quality - Limited stockpile space means high throughput is
achieved by low stockpile residence time -
- No Vessels No Trains
15Pull System - DBCT
- Pull system may have some effect on Mine Product
stockpiles - Faster cargo assembly will increase the mean time
between stock offtakes. - Peak stockpile levels may be higher than historic
- Impact low if the vessel arrival pattern is smooth
16??? System - HPS
17Planning Horizons
- The new Integrated Planning process will be
undertaken across three planning horizons - Long Term Planning - a rolling monthly plan
covering months 5 24 from the current day of
operation - Tactical Planning - a rolling weekly plan
covering weeks 3 17 from the current day of
operation - Operational Planning - a rolling daily plan
covering 0 14 days from the current day of
operation which includes a detailed 0 - 48 hour
schedule component
- The Tactical and Long Term planning processes
will focus on highlighting and resolving
imbalances between demand, mine supply and
available capacity - The Operational planning process will focus on
reducing the current system variability and
maximising coal chain throughput by using more
accurate and timely vessel and mine product
availability information to drive coal chain
plans
18Integrated Planning Timeframe
19Stabilisation
- Reducing variability within the coal chain
requires - Information that is accurate, timely and
transparent - Processes are currently being built to allow
information flow and detail to improve - Robust processes
- For example, if a train is cancelled what process
is always followed to ensure loss to the system
is minimised - A detailed understanding of each link in the
chain - For example, a load point or port unload system
needs to have a defined capability that can be
the basis for scheduling
20Stabilisation a mine perspective
- The coal loading plan needs definition
- A Load Point Capability Statement is to be built
and will contain the data vital for planning eg
planned load times, recharge allowance between
trains, allowances for coal type changes - The Load Point Capability Statement will be
reviewed regularly with the Operator. - The more accurate the data, the more likely
trains will arrive, load, depart and unload at
the planned time. This means - Loss is minimised
- Process is measurable
- Opportunities are identifiable
21Stabilisation a mine perspective
- Train consists will be standardised to
- 20 x 9,600 tonne trains
- 1 x 9,000 tonne train
- MineTrak is being updated to facilitate
information flows - For example - Advice when parcel will be
available for railing - HPS ?????
22Long Term / Tactical Planning
- Highlighting and resolving imbalances between
demand, supply and available capacity - The Long Term/Tactical Forum will be achieve this
through implementation of - Critical Asset Register
- Critical activity calendar
- Coordinated Planning
- Capacity Management
- Utilising contract, marketing and shipping
forecasts - Simplistic capacity determination
- Long term planning time amounts months
- Tactical planning time amounts weeks
- Business Rules
23Operational Planning
- Coordinate information, share information and
planning on - Mine forecasts
- Critical Asset Calender
- Shipping arrivals/orders
- Berthing Plan
- Yard plan
- Rail scheduling
- Operational Planning Time amounts days
- Business rules
24Operational Planning Horizon
25Operational Planning Horizon
HPS Version ???
26Day of Operations
- Execution of plan focusing on running ..
- Loading trains
- Railing
- Unloading
- Stockpiling
- Shiploading
- .. And recovering to plan using
- Business rules
- Recovery Plan
- Information transparency
- Plan will be in the form of a 48 hour schedule
27Key Changes for Mines
- Long Term and Tactical Planning Horizons
- Provision and maintenance of Critical Asset
Register and Calender information - Available system capacity can be defined with
sufficient notification to enable demand to align - Any interruption to capability (coal flow or
maintenance) of a critical asset MUST go through
the Integrated Planning Process - Provision of Demand information
- Capacity balancing will be undertaken monthly for
the 524 month horizon and weekly for the 317
week horizon Assessment of demand and supply
together with Maintenance alignment using a
simple capacity analysis tool
28Key Changes for Mines
- Operational Planning Horizon
- DBCT berthing plans will look out 14 days instead
of the current 7 days and will drive the planning
and scheduling of the DBCT stockyard and the rail
network - Hay Point demand will be in the form of inloading
request by sequence at the pits. - Operational plans and schedules will be updated
and communicated to all stakeholders on a daily
basis - Emergency, essential and opportunity maintenance
requirements will be communicated to all relevant
stakeholders - Mines will confirm coal is on the ground and
ready for loading onto trains a minimum of 24 hrs
prior to any 48 hour schedule in which trains are
to be run to the mine - Minimising coal supply variability
- Consistent sequencing of trains to align with
requirements of yard and berthing schedule - A detailed berthing, yard and rail schedule will
be defined by Plan at 48 hours from execution and
will be made visible to all stakeholders - Train configurations will be standardised across
the system 90 x 106 t 30 x 90t (9600 t)
29Key Changes for Mines
- Performance
- Performance framework currently under
construction - Framework intent to focus on stabilisation then
improvement measureable KPIs to allow
systematic improvement - Ports, trains, track and mines will be measured
and reported on - Performance
- Information quality and timeliness
30Business Rules - Mines
- Any work planned on a critical asset, as defined
in the critical asset register, must be
communicated in line with the integrated planning
process to eliminate the possibility of unknown
activities impacting on coal chain performance - Planned maintenance will be locked in at 21
days or more depending on the lead time. No
further changes may be made to planned durations
or start dates within this lock down period - All significant, planned maintenance, asset
upgrades and asset commissioning activities will
be submitted at least 12 months out from the
current day of operation. Changes to planned
durations and start dates may occur until the
greater of the 21 day lock down or planning lead
time is reached
31Business Rules - Mines
- If DBCT does not receive parcel, vessel and mine
information at specified times or it is altered,
the vessel will cede berthing priority until
these requirements are met - Parcel assembly plans must be agreed 7 days out
from vessel ETA - 24 hours ahead of any 48 hour rail schedule, all
mines will need to confirm the availability of
coal on the ground and the readiness to load all
trains which will be run in that 48 hour schedule
- Further business rules will be developed during
operating plan design across all planning - horizons.
- Recovery Plan is to be developed in conjunction
with internal operational stakeholders.
32IP Communications
- GCC Web Portal
- Common interface for stakeholders to view
performance, plans, meeting agenda's, minutes,
and timetables - Web site is secure and open to GCC nominated
stakeholders only (administered) - During IP implementation, regular updates will be
forwarded to nominated site representatives and
posted to the web portal - Regular forums will enable additional information
flow - Long term/Tactical forum
- SOMM
Web Portal View ?
33IP Project Implementation
- Stabilisation approximately 15 May 2006
(Operational Planning, DOO, business rules,
recovery plan) - Leading up to the 15th, operating plans, recovery
plan and business rules will be workshopped. - Long Term Tactical planning progressing with
processes rolling out - Training supply chain package under development
- IT systems (information sharing). GCC web portal
under development
Slide 18 or here
34IPG Objective Maximise throughput whilst
maintaining service levels