Renton Nickel - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Renton Nickel

Description:

Could add a 4' buffer between HOV and GP lanes. Why? Record of Decision ' ... Staged construction. Will be fully constructed with a later project ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 19
Provided by: billj77
Category:

less

Transcript and Presenter's Notes

Title: Renton Nickel


1
Renton Nickel
  • Its your nickel, watch it work!

2
A Little Background
  • National Environmental Policy Act (NEPA)
  • P stands for Policy
  • Signed into law by President Nixon
  • NEPA documentation started out simply enough
  • Quickly proceeded to get very complicated
  • Documentation now driven by litigation

3
I-405 Corridor
  • Started in 1965, completed in 1971
  • Two lanes in each direction from Tukwila to
    Lynnwood (I-5 to I-5) right at 30 miles
  • High occupancy vehicle (HOV) lanes added in the
    1990s.
  • Made three lanes in each direction

4
I-405 Corridor Master Plan 2002
  • Developed a corridor master plan
  • Used a Tiered NEPA approach
  • First step
  • Environmental Impact Statement (FEIS)
  • Second step
  • Record of Decision
  • Third step
  • How to fund it?
  • Fourth Step
  • Additional NEPA documentation and Permitting

5
FEIS Recommendations
  • Add two additional lanes in each direction
  • Improve interchanges
  • Add up to two lanes each direction along SR 167
  • Bus rapid transit throughout corridor including
    east west connections (not fixed guide way)
  • HOV direct access
  • Anybody seen the Totem Lake HOV direct access?
  • Could add a 4 buffer between HOV and GP lanes
  • Why?

6
Record of Decision
  • The FTA in coordination with FHWA, WSDOT, KCDOT,
    and Sound Transit concurs that the Selected
    Alternative meets the Purpose and Need of the
    I-405 Corridor Program, finds that the Draft and
    Final Environmental Impact Statement represent
    detailed statements required by NEPA and by 42
    U.S.C. Section 4332 on
  • the environmental impacts of the proposed action
  • the adverse environmental effects which can not
    be avoided should the proposed action be
    implemented
  • alternatives to the proposed action
  • And mitigation measures required to minimize the
    harm of irreversible and irretrievable impacts on
    the environment should the proposed action be
    implemented
  • and finds that, on a corridor level, the
    requirements of NEPA and of 49 U.S.C. Section
    5324(b) have been satisfied or met.

7
How do we fund it?
  • Nickel gas tax of 2003
  • Funded 4 billion in Washington state projects
  • 485 million on I-405
  • Added 5 cents a gallon of gasoline and diesel
  • Transportation Partnership Account (TPA)
  • Funded an addition 7 billion
  • 972 million for I-405
  • 9.5 cents more per gallon in fuel taxes

8
Nickel projects along I-405
  • Kirkland Nickel (partly constructed)
  • 164 million
  • Would add a lane in each direction (520 to 522)
  • Staged construction
  • Will be fully constructed with a later project
  • Bellevue Nickel (mostly constructed)
  • 186 million
  • Would add a lane each direction (NE 4th to I-90)
  • Staged construction
  • Removed the Wilburton tunnel
  • Renton Nickel
  • 136 million
  • What was proposed to be funded is not exactly
    whats being constructed
  • Staged construction

9
Remember the Master Plan?
  • Based on two lanes in each direction?
  • BRT (Bus rapid transit)
  • SR 167 improvements
  • Other elements

10
Renton Nickel is now Renton Stage I
  • Renton Stage I
  • Combination of Nickel Funds and TPA funds
  • Allowed for one lane in each direction from I-5
    to SR 167
  • Allowed for one additional south bound lane on SR
    167
  • 91.5 million construction cost

11
Renton Nickel EA
  • Environmental Assessment was one of the first
    supported by the corridor ROD
  • EA and permitting from early 2005 through late
    2006
  • FONSI early 2007
  • Two year environmental process
  • Design-Build Contract awarded in June 2007
  • Construction is a portion of what was covered by
    the EA

12
Renton Nickel Wetland Impacts
  • There were 19.4 acres of total wetlands within
    the EA limits
  • Permanently fill 1.66 acres
  • Temporarily disturb 0.64 acres
  • Mitigation
  • Accomplished at the Springbrook Mitigation site

13
Typical Wetlands
14
Renton Nickel Stream Impacts
  • 0.07 acres of stream impacts
  • Some associated with new bridge over Springbrook
    creek
  • Box culvert removal
  • Side channel reconstruction
  • Some associated with SR 167 changes
  • About 2 lengthening of a non-fish bearing
    culvert

15
Tribal Resources
  • Court cases have determined that the tribe has
    rights to fish and shell fish resources
  • The Muckleshoot Indian Tribe (MIT) have usual
    and accustom fishing areas in Renton and most
    other I-405 areas
  • The Tribe has generally weighed in during Corps
    404 permitting

16
So, What does Environmental Do?
  • Determine resources
  • IDT field visits
  • Determine impacts with preliminary design
  • Make reconditions for modified designs
  • Pursue permitting and mitigation
  • Monitor construction and make permit
    modifications as construction proceeds

17
Todays site visit
  • We will see the stream mitigation site
  • Adding a main channel by-pass
  • Removing the main channel box culvert
  • Re-watering the main channel
  • Enhancing the side channel
  • Will all need to be completed in this years fish
    window
  • June 15 September 1st

18
Safety
  • Active construction site
  • Likely not live today
  • Slips, trips, and falls are most common
  • Watch for traffic
  • Stay together
  • Others?
Write a Comment
User Comments (0)
About PowerShow.com