Title: End User Presentation
1- End User Presentation
- On behalf of
- Geoffrey Osborne Limited
- Peter Russell Contracts Manager
- Steve Crook Project Manager
- Andy Lam Technical Manager
2- This presentation provides you, the end user,
with an overview of the forthcoming construction
activities at the Cavendish Street Campus. - The presentation will last around fifteen minutes
and will - Provide an overview on what we are building
- Introduce you to key members of the Osborne team
- Discuss key construction activities and
interfaces with the campus - Talk about any potentially disruptive works
- If you have questions, feel free to ask them at
any time
3- Project Overview
- Geoffrey Osborne have been appointed to construct
a new building at the heart of the Cavendish
Street Campus - The Hub Development will provide
- New offices and teaching facilities
- Circulation routes to the adjacent buildings
- A modern kitchen with dining over two levels
-
- The building will utilise Sedum grass roofing
and copper cladding to achieve a contemporary look
4Architects Model
Sedum roofing
Copper cladding
Reglit glazing
5Key members of the Osborne team
- Steve is responsible for leading the site team
and will be your principal Osborne contact - He has a wealth of experience in building
complex, logistically challenging projects - He has recently completed the redevelopment of
Brixton London Underground Station
Steve Crook Project Manager
- Peter was a key member of the initial bidding
team - He is very experienced in demolition and inner
London working - He will provide office based support to Steve
Peter Russell Contracts Manager
6Programme dates
Proposed start on site 30th May 2005 Soft strip
demolition June 2005 August 2005 Erect steel
frame August 2005 October 2005 Start envelope
works October 2005 Substantially
weathertight January 2006 Internal
fit-out January 2006 August 2006 Proposed
completion date 18th September 2006
7Interfaces with the public
- We have agreed a scheme with the University to
define our work areas by using full height timber
hoardings - These hoardings will segregate campus users from
our work activities - The hoardings will also minimise the effects of
noise, dust and pollution
8Hoarding arrangement lower ground floor
9Hoarding arrangement ground floor
10Hoarding arrangement 1st floor
11Principal construction activities
- Demolition of existing lantern structure
- Erection of steelwork frame
- Cladding and roofing works
- Internal wet trades plastering, screed
- Mechanical and electrical installations
- Fit-out works
- Commissioning and end user familiarisation
Courtesy of Queen Mary and Westfield College
12Site craneage
Crane radius
Proposed crane a luffer
13Demolition proposed methodology
- The soft-strip and demolition works starts in
June for a period of 11 weeks - Where possible, we have planned to utilise
non-percussive methods to minimise the disruption
to the University
Bobcat skid steer for loading arisings waste
materials
Brokk incorporating a concrete crunching
attachment
Track mounted diamond saw
Pedestal mounted diamond drill
14Demolition protection works
This photo shows the top of the lantern structure
in relation to 1st floor level. The majority of
the demolition works will occur below 1st floor
level
Flame retardant translucent plastic sheeting,
2.4m high, will be fastened to the ground floor
windows to obscure and provide protection from
the demolition work We shall lay a temporary
bitumen protective layer over the ground floor
slab. This will prevent the ingress of water
into the lower ground floor during the
construction works
15Osbornes Core Values
Integrity
Always be honest and treat others as you would
like to be treated
Quality
Be professional and do a job for which everyone
can be proud
Caring
Encourage, support, understand and respect each
other
Openness
Be open with each other and be prepared to
listen
Progressive
Continually improving and adapting to be the
best