Title: Status of the Dimuon Arm Tracking System
1Status of the Dimuon ArmTracking System
2OUTLINE
- Status of the detectors
- Station 1 status
- Station 2 status
- Stations 3,4 and 5 status
- FEE electronics
- MANAS
- MARC
- MANUs
- Read-Out (CROCUS)
- Services
- Integration
- Summary
3Station 1 status
- Concerns in 2003
- - gas tightness
- - low gain
- - gain inhomogeneity
- Extensive tests performed
- in-lab on quadrant 0
- Modifications of quadrant 0
- - use of a central spacer
- - improvement of the
- closure procedure
- Validation with radioactive source and with
in-beam tests at PS in November 03
4Station 1 status
QUADRANT 0
Test on CH0 Chamber after 2nd Mounting
Before (241Am source)
5Station 1 status
- QUADRANT 0
- In-beam tests at PS
- (November 2003)
- - Gain increased by 1.5
- HV limit 75V higher
- Maximum gain 4 times
- higher
6Station 1 status
- New design for the
- stiffness reinforcement
- - Central spacer
- Foam thickness
- increased by 2x5 mm
- Frame thicknesses
- increased by 18 mm
- Technology modified
- for the vias
- - Construction of the
- quadrant 1 from July 03
- till the end of October
7Station 1 status
- Quadrant 1 performances
- The detector tested by means of a radioactive
source gt gain dispersion in 13.5 (peak to
peak) - Gas leakage less than 9 ml/h
- Mass production
- Green light for construction of all the quadrants
- Most of the components ordered in December 03
- Construction of 4 quadrants/year gt end 2005
- Installation will start in the beginning 2006
8Station 2 status
- Quadrant 0 was constructed
- PRR took place at Kolkata in June 03
- In-lab tests
- Excellent gas tightness (leak rate lt 15 ml/h)
- No leakage current (a few nA)
- Total accuracy on 1120 mm PCB lt100 µm
- Planarity in 85 µm
- Good gain homogeneity ( 15 ) (measured with a
241Am source)
9Station 2 status
10Station 2 status
- In-beam tests at PS on November 03
- Quadrant 0 results
- Good gain
- Residual problems (now fixed)
- Gluing of the anode wires
- Leakage current on a few decoupling capacitors
- Some short circuits in the exit boards
11Station 2 status
- Mass production is started
- All cathode and anode PCBs ready in April
- All kaptons with connectors soldered and tested
by end of April - Assembly of 4 quadrants in 2004
- Completion of the construction by fall 2005
- Installation in the cavern will start in the
beginning 2006
12Stations 3, 4 and 5 status
- All the 4 construction sites are now identically
equipped for the mass production of the slats - All the components for starting the mass
production sent in the labs - Start of production in 3 labs done (Gatchina
delayed till mid-March for practical reasons
person availability, administrative procedures) - 4 slats already constructed per lab. with small
mounting process adjustments
13Stations 3, 4 and 5 status
- Mass production planning
- End of slat production
- Station 4 Nov. 2004
- Station 5 July 2005
- Station 3 Nov. 2005
- Spares Feb. 2006
- Frames
- First two frames for station 3 March-April 2004
- End of all the frame construction Nov. 2004
- Chamber assembly at CERN during 2005
- Installation in the cavern will start in the
beginning 2006
14FEE MANAS
- Issue in 2003 MANAS never tested
- - 120 MANUs produced with MANAS and MARC3
- - in-beam tests with
- - slats at SPS in June
- - with quadrants of stations 1
- and 2 at PS in November
- Noise similar to GASSIPLEX when mounted on
MANU boards and plugged on the detectors 1000
electrons in realistic experimental conditions
15FEE MANAS
- Too large pedestal dispersion in the first
delivered batch Request for a smaller window
acceptation for the mass production (20 to 140
mV)
- Too large gain dispersion (s13) -
Request for a smaller spread (5 peak to
peak) - Absolute necessity for
calibration of all the channels with 1
level accuracy
16MANAS performances
With gain correction
Without gain correction
s 170µm
s 75 µm
Results obtained at PS with quadrant 0 of station
1
17Station 1 results
Resolution obtained with an upper cutoff on the
measured charges
Efficiency in 1 mm without cutoff on the charges
18Station 1 results
Number of small pads hit versus the HV value
19Manas non-linear correction
Tests performed at SPS with slats - very few
multiple scattering - higher sensitivity for
studying fine effects like non linear responses
Calibration non-linear s 50 mm
Conclusion Gain calibration and linearity
measurements are mandatory
20MANAS Calibration
- Calibration issue
- Calibration measurements on board irrelevant due
to the internal capacitance dispersion - Proposed strategy
- - to measure the internal injection capacitances
of all the channels - - to calibrate the response function of all the
channels - How to do?
- - injection of a pulse via well known external
capacitors - - injection of a corresponding pulse via the
internal capacitors - - ratio gives the internal capacitance values
21MANAS Calibration
Construction of a test bench - careful
implementation to minimize parasitic
capacitances - calibrated capacitors at
2 level accuracy (attempt to find calibrated
capacitances at 1 level) - charge
injected between 0 and 500 fC -
possibility to test MANU12 and MANU 345
22MANAS Calibration
Internal capacitance measurements
on MANU12 MANU345
23FEE MANAS
- Calibration issue
- MANAS calibration should be achievable with an
accuracy of 2. - The parameters of this calibration (1 200 000
channels) will be determined and - stored by the factory in charge of the mounting
of the MANU boards - Conclusion
- - MANAS will be usable with some severe
constraints - - Chips have to fulfill acceptation criteria
(pedestals, gains) - - The calibration of all the channels has to be
performed (if possible) - - The knowledge of the mapping for the whole
tracking system is mandatory (the location of all
the MANUs on the different chambers has to be
known) -
24FEE
- MANAS production
- MANAS production launched (delivery of 70 000
chips from September 04 till beginning 2005) - Functionality tests will be done at the factory
- MARC production
- New iteration (MARC4) completed and tested
- 1500 chips produced
- Mass production (20 000 chips for diµ arm) was
launched and the chips should be delivered in
October 2004 - Tests of the chips will be done at the factory
25FEE MANUs
Electronics PRR held at CERN on 22 October
(MANAS) and at Orsay on 27 November
- A preproduction of 250 MANUs is being done after
some minor corrections - Tendering for mass production is starting
- Mass production between fall 2004- mid 2005
(8000 MANU12 and 11000 - MANU345)
- Tests and calibrations performed by the factory
(test bench provided by the collaboration)
26READ-OUT (CROCUS)
J T A G
J T A G
J T A G
J T A G
J T A G
J T A G
J T A G
J T A G
J T A G
J T A G
Front board
Front board
Front board
Front board
Front board
Dsp Analog Device 21160 BGA 400 Pins at 80Mhz
J T A G
J T A G
EEPROM
Concentrator board
FPGA SIU Interface
SIU INTERFACE BOARD
Debug
TO TCI
FPGA TRIGGER
Trigger config
DDL to RORC
27READ-OUT (CROCUS)
- All the components of a prototype are ready
- - Crate and back panel
- - Concentrator board
- - Frontal board
- All the components already tested
- (with SIU)
- Final software is being implemented
- CROCUS should be validated in
- realistic experimental conditions
- in July and September at SPS
- Iteration at fall 2004, then
- mass production
28SERVICES
- TRIGGER DISPATCHING
- Role to decode the signal from the CTP and
dispatch it on all the Front End cards - Decoding card with TTCRx chips will be bought at
CERN - Prototype of dispatching cards are designed and
are currently being fabricated - LV power supplies
- A Wiener LV Power supply prototype was tested
with very good results - New design studied by Wiener with CERN but new
concern with the magnetic field (200 G) - Purchase on wait for the CERN final choice
- HV power supplies
- CAEN 1527 have been chosen (same concern with the
field) - HV distribution device for increasing the
granularity is launched
29INTEGRATION
- STATIONS 1 AND 2
- Support and services designs for the stations 1
and 2 will be completed end 2004 - Construction beginning 2005
- Preliminary mounting in lab mid 2005
- Mounting in cavern beginning 2006
30INTEGRATION
- STATIONS 3, 4 AND 5
- Rails, toolings
- - Design of rails and toolings for chamber
assembly and
installation completed and sent to
industry for final drawings - - Installation of the first part of rails
cooling higher part for - ST3 foreseen in Aug 04.
- - Install. last part rails and cooling ST3
Apr. 05 - - Install. rails ST4 and 5 on superstructure
cooling Sept. 05 - - Start install. chambers Dec. 05- Jan. 06
- Services (LV, HV, R/O, gas...) integration
- - Design is well advanced will be
completed during 2004 - - Connecting boxes (between cables from
supplies and cables from detectors) are not yet
designed.
31Rails of Station 3
General view
SuperStructure
Dipole
1.Fixed part
Muon Filter
3.Removable part
2.Curved part
Absorber
32Summary of installation scenario in cavern
12/Introduction in Dipole
33SUMMARY
- All the PRRs were held before the end of the year
2003 - Main concerns are now fixed
- Mass production for the detectors is starting
- Mass production for components launched.
- FEE production will start after tendering
- Integration is on track