Title: AMS02 Thermal Test
1AMS02 Thermal Test
- Marco Molina, Christian Vettore, Massimiliano
Olivier (CGS) - Serena Borsini (UNIPG)
2Test specification
- TVTB Test specification issue 1
- November 2007
- Subdetectors test requirements collected
- TIM, February 2008
- TVTB Test specification issue 2
- Apr 14th 2008
- Comments received and implemented from AMS
- TVTB Test specification issue 2 rev H
- June 29th 2008
- Last comments have been gathered, will be
incorporated before issuing the final one
3Apr 2008- Jul 2008
- Steady state thermal analysis have been done (S.
Borsini , UNI PG) - Maximum and minimum temperature achievable on the
detectors - IR lamps design has been consolidated
- Assessment on gradients on the gondola has been
completed - Power density has been calculated for the lamp to
generate thermal gradients - Transient analysis (cooling down) has been
started
4Thermal test principle
- Thermal test conditions are NOT representative of
the extremes AMS will experience on orbit - Thermal test conditions, in general, are NOT
representative for the entire detector of any
specific on-orbit condition - AMS will be in equilibrium with the impinging
fluxes varying view factors to the ISS deep
space unobstructed view
5T MAX
Thermal requirements for detector A
On orbit
Test
T MIN
6Thermal requirements for detector B
T MAX
Test
On orbit
T MIN
7T MAX, B
Thermal requirements for detector B
Test
On orbit
Thermal requirements for detector A
T MAX, A
On orbit
Test
T MIN, A
T MIN, B
8Isochronous snapshot (same time), on orbit
T MAX, B
Thermal requirements for detector B
Test
On orbit
Thermal requirements for detector A
T MAX, A
On orbit
Test
T MIN, A
T MIN, B
9Isochronous snapshot (same time) Cold case in the
LSS
T MAX, B
Thermal requirements for detector B
Test
On orbit
Thermal requirements for detector A
T MAX, A
On orbit
Test
T MIN, A
T MIN, B
10Isochronous snapshot (same time) Hot case in the
LSS
T MAX, B
Thermal requirements for detector B
Test
On orbit
Thermal requirements for detector A
T MAX, A
On orbit
Test
T MIN, A
T MIN, B
11Isochronous snapshot (same time), Temperature
swing in the LSS
T MAX, B
Thermal requirements for detector B
Test
On orbit
Thermal requirements for detector A
T MAX, A
On orbit
Test
T MIN, A
T MIN, B
12What is it representative the TV test of?
- For each detector, a cold and a hot environment
will be provided for performance evaluation in
vacuum in the two conditions - Transition between hot and cold
- Model correlation
13Model correlation in 2 steps
- Not being possible to reproduce entirely the ISS
environment, an isothermal environment is used
for model parameters identification - The so called validated model (with identified
parameters) is then used for on-orbit predictions
14?
LSS
15Test data
Parameters tuning (identification)
Test data?Model data VALIDATED MODEL
Model data
16On orbit predictions (final)
On-orbit temperature are predicted with higher
reliability
AMS VALIDATED MODEL is integrated with ISS
model
- Overall uncertainty in the temperature prediction
will be reduced - BUT
- Environment-related uncertainty cannot be reduced
by the TVTB test
17Thermal extremes prediction in the LSS
- LSS analysis conditions
- COLD shroud at -90C, see next page for the
other conditions - HOT shroud at -10C, lamps OFF, AMS ON
- Nominal operations (power)
18COLD case analysis
- Transient to -90C for 20 hrs
- Heaters TRD and TRDGB ENABLED
- Heaters RAM set 1 on
- Lamps on Lower USS ON with a power of 500 W per
module (1 module 8 lamps) - AMS02 electronics on
19Temperature ranges during test
- TRD
- side panel from -5 C to 20C
- M-structure (corner bracket) from -14C to 16
C - M structure (center) from 1C to 20C
- Lower TOF from -16C to 14C
- Upper TOF from -6C to 24C
- Ecal from 5C to 38C
- Rich from -16C to 15C
- Tracker
- Hybrids from -18C to -12C
- Silicon tracker from -13C to 5C
- Cryocoolers from -17C to 18C
- TRD temperatures are not stabilized after 20
hours longer transients needs to be run
20Temperature ranges during test
- CAB from -12C to 18C
- TTCB
- Baseplate from -20C to 5C
- Start-up radiator from -17C to -4C
- Star tracker electronics from -4C to 8C
- Acc from -19C to 20C
- Tracker radiator
- Ram side from -54 to 4C
- Wake side from -52C to 3C
21- TRD GB baseplate from -18C to 14C
- XPD from -14C to TBD in the hot case
- Crates from -5C to 33C
- PDS from 12C to 39C
- E-crates from -9C to 8C
- UPS from -30C to 12C
- HV on lower USS from -50C to 5C
- By switching on the lamps, can be raised up
to 30C
22- Hottest temperature is driven by ECAL (38C)
- Coldest temperature is driven by UPS (-30C)
23LAMPS POWER FLUXES ESTIMATION
24LAMPS ON TRACKER WAKE RADIATOR
LAMPS POWER EVALUATION
25LAMPS ON TRACKER WAKE RADIATOR
Lamp power from TD 0,19 x Plamos if Plamps
1000 W ? 300 W/m2 if Plamps 1960 W ? 600
W/m2 if Plamps 2776 W ? 820 W/m2
Number of lamps on the tracker radiator will be
doubled
26LAMPS ON TRD
LAMPS POWER EVALUATION
27LAMPS ON TRD
Lamp power from TD 0,25 x Plamos if Plamps
1000 W ? 600 W/m2 if Plamps 1960 W ? 1100
W/m2 if Plamps 2776 W ? 1600 W/m2
Number of lamps on the TRD will be doubled
28LAMPS ON ECAL
LAMPS POWER EVALUATION
29LAMPS ON ECAL
NODE 90400
Lamp power from TD 0,04 x Plamos if Plamps
1000 W ? 440 W/m2 if Plamps 1960 W ? 870
W/m2 if Plamps 2776 W ? 1200 W/m2
Number of lamps on the ECAL will be incremented
by 50 (for accomodation reasons)
30Total IR lamps
- 92 lamps (30 spares)
- 32 independent controllable power supply (10 A
max) - It is recommended by NASA/Jacobs to have more
power supply units for contingency (to oversupply
the lamps, as needed) - Final number of power supply and feed lines will
be given to ESTEC in September
31Test sequence
32(No Transcript)
33Test sequence
- Functional checkout before vacuum
- Bake out
- Initial cooling down
- Switch on
- CCEB (for monitoring Pt1000 sensors)
- M (for monitoring various temperatures)
- UG (to monitor TRD TEMPERATURE)
- The Upper TOF is switched on for thermal reasons.
- TRD GAS is switched on
- Cryocoolers are switched ON, to follow the
recommendation by the Magnet group of running
them as much as possible - Before Magnet charging everything will be ON with
exception of - TRD
- RICH
- ECAL
- TRACKER
34- Magnet charge
- Cold thermal balance
- Cold start
- PDS
- J-crate
- CCEB (For monitoring)
- M-crate
- UG-crate
-
- TOF
- TRDGB (For operational and thermal)
- Cryocoolers
-
- TRACKER, RICH, ECAL, TRD are switched on with no
priority driven by thermal considerations
35- Cold to hot transition
- Hot thermal balance
- Hot start
- PDS
- J-crate
- CCEB
- M-crate
- UG-crate
- All the other detectors (TOF, TRD GAS BOX,
Cryocoolers , TRACKER, RICH, ECAL, TRD) - Hot to cold transition
- Cold thermal balance number 2
- Hot thermal balance number 2
- Magnet discharge
- Re-pressurization
- Functional checkout at ambient conditions
- End of the test
36Example of transient analysis
37PDS
38RICH
39Conclusions
- TVTB test spec document can be found at
- ftp//ftp.cgspace.it/Projects/AMS/TWG/DOC/SPEC/1-L
SS/TVTB-TEST-SPEC/ - Coming next TVTB workshop in Milano in September
23-24 2008 - Test duration estimate
- Thermal transient calculations from Thermal group
- Time estimate for each detector tests from AMS
subdetectors see next page - Draft step-by-step procedure (S. Lucidi)
- Test procedure to ESTEC Nov 1st 2008
40REQUEST TO SUBDETECTORS
- Functional test duration (including activation of
the subdetector) has been estimated 2 hours. - Subdetectors needing more time should let us
know, as well as any critical parameters to
monitor.
41(No Transcript)
42TV test scope
- Functional performance verification of the entire
detector - Under vacuum conditions
- At the extreme achievable thermal environment
(hot and cold) - Respecting the flight hardware limits (WITHIN
ACCEPTANCE LEVELS) - Driven by the test configuration
- TVT stand
- IR lamps
- SUCCESS CRITERION Proper functioning of sub
detectors and electronics. - REMARK IT IS NOT A (PROTO)-QUALIFICATION TEST
- Equipments and detectors will not necessarily go
to their flight extremes
43MATERIALS COMPATIBILITY with vacuum
- NASA-gtESTEC
- AMS flight hardware DML
- AMS-gt ESTEC
- TVT test stand and all hardware used for the test
outgassing data - AMS-provided cables
- scaffolding
- AMS-provided piping
- valves
-
- ESTEC -gt NASA/AMS
- ESA-provided hardware outgassing data
- Lamps and their rigs
- Test MLI
- Test heaters
- ESTEC provided pipes
44ITEMS TO BE PROVIDED BY ESTEC
- 450 Temperature sensors (thermocouples) (50
spares) - Some of them, according to Tab. 8-1 will be
needed in advance for being pre-installed at CERN - IR lamps with power supply, controllers and
cabling, as specified in 7.2.3 - 106 Lamps 30 spares
- 18 independent power supply and controllers for
the IR lamps - IR Lamps cabling
- IR lamps rigs
- Venting lines
- TRD gas BOX vent line
- Pipe inside and outside the LSS
- Test MLI (0.05 effective emittance) to wrap-up
the pipe - Heaters (2 W / m) underneath the MLI and power
supply - Cryogenic system venting (see paragraph 7.5 )
- Feed-through
- AMS Power, Command and Data (see paragraph 7.3 )
- For Helium lines (see figure Fig. 7-2)
- For TRD vent lines
- Test MLI for the LSS floor (as specified in
paragraph 7.2 )
45Temperature sensors
- 350 thermocouples are foreseen for the test
article. - LSS shroud temperature shall be monitored with
50 sensors to provide information on temperature
uniformity. - 50 sensors shall be used to monitor the TVT
stand temperature
46At the end of the test each subdetector will have
undergone
- Partial functional test
- At ambient before the test
- In a cold environment (twice)
- In a hot environment (twice)
- Transient data (cooling down in case of a power
loss) will be collected - In a cold environment (twice)
- In a hot environment (twice)
- Response of some subdetctors (TRD, TOF) to
environment variation will - AMS02 Activation sequence is tested
- Magnet charge and discharge is tested
- High beta-angle (heat unbalance) is tested for
RICH, ECAL and TRD - RAM-WAKE unbalance is tested for the TTCS
47Overall duration
- Bake out and thermostats check-out (initial
cooling down) 200 hours - Cold thermal balance (5 plateau) 300 hours
- Power outage in a cold case 10 hours
- Hot thermal balance 100 hours
- Power outage in a hot case 10 hours
- Cold TB number 2 80 hours
- Hot TB number 2 80 hours
- Magnet discharge 5 hours
- LSS chamber re-pressurization 30 hours
. - TOTAL 815 hours 34 days
48Lamp group 1 (AMS bottom)
49LAMP GROUP 2 (ECAL/RICH side)
50LAMP GROUP 3 (TRD side)
51LAMP GROUP 4 (Tracker radiator)