Title: BCRA Poster
1Subgrade Soil Support and Stabilization
OHARE Airport Modernization Research Project
Research Progress Presentation June 30, 2005
Co-PIs Erol Tutumluer
Marshall R. Thompson RA
H.S. Brar
2Introduction
- Subgrade performance is a key factor in the
overall pavement performance
National Airport Pavement Test Facility -
Atlantic City, NJ
- This project provides testing and analysis to
establish subgrade support and stabilization
requirements for OHare airport pavements
3Introduction (contd)
- The preliminary concrete pavement design for the
OHare Modernization Program (OMP) - 15 17 inches of PCC Surface
- 6-inch Hot Mix Asphalt Base
- 6-inch Asphalt Treated Permeable Base (!?)
- Stabilized Subgrade Zone (SSZ)
- Prepared Subgrade
- North Runway (9L-27R, 7,500 ft) paving is
scheduled first for the Spring 2006 (!?) - Stockpiles of local soil on runway centerline
(excavated from the Deep Pond nearby) - Primarily fill and cut areas
4Research Objectives
- Consider pavement design inputs for subgrade
support - Modulus of subgrade reaction, k
- Consider subgrade support and stabilization
requirements with respect to - Need for subgrade stabilization
- Stabilization admixture(s) stabilization
- Stabilization depth
- Estimate subgrade support for various
combinations of subgrade stabilization treatments
and prepared subgrade conditions
5Project Tasks
- Task 1
- Establish the Best Demonstrated Available
Technology (BDAT) for subgrade soil evaluation
and stabilization (Ongoing) -
- Reports and publications collected submitted
as Technical Notes on - Subgrade strength/stiffness evaluation techniques
- Subgrade stability requirements IDOT Manual
- Working platform requirements for pavement
construction
6Project Tasks
- Task 2
- Evaluate currently available data for the
subgrade test sections constructed in the Fall of
2003 and the necessity/usefulness of constructing
additional subgrade treatment test sections at
OHare - (Effort completed)
- Plate load tests conducted (8/04) on the test
sections - Plate 1 12-inch stabilization/compaction no
admixture - Plate 2 12-inch quicklime fine (40 lb/yd2) fly
ash (80 lb/yd2) stabilization - Plate 3 12-inch quicklime fine stabilization (40
lb/yd2) ? - Plate 4 12-inch lime kiln dust stabilization (40
lb/yd2) ?
7Plate Load Tests
Modulus of Subgrade Reaction, k
8Project Tasks
- Task 3
- Advise OMP on current and future test section
monitoring and field test evaluation programs - (Effort completed)
- Various field tests may be useful to
characterize the treated subgrade (OMP will
arrange for testing) - Dynamic Cone Penetrometer (8/04)
- Light-Weight Deflectometer (8/04)
- Clegg Hammer
- Geogauge
- Heavy Weight Deflectometer (HWD)
- Ground Penetrating Radar (GPR)
- Seismic Pavement Analyzer, SASW, etc.
9Dynamic Cone Penetrometer
Light-Weight Deflectometer
10Project Tasks
- Task 4
- Evaluate currently available geotechnical/subgrad
e data for the North Runway with emphasis on the
stockpiled Deep Pond soils. Recommend further
soil sampling testing to be conducted (by an
OMP designated testing firm) (Ongoing) - Routine tests to establish representative soils
existing for the runway subgrade - Grain size distribution (including hydrometer)
- Atterberg limits (LL and PL for PI)
- Moisture-density-CBR
- PH value calcareous content
- If needed, organic matter content
11Preliminary Geotechnical Report
Soil sampling testing conducted by Everest
Engineering on OMP Runway 9L-27R - October 2004
Atterberg limits (LL and PL for PI)
Boring Logs
12Preliminary Geotechnical Report
Soil sampling testing conducted by Everest
Engineering on OMP Runway 9L-27R - October 2004
Grain size distribution (including hydrometer)
13Preliminary Geotechnical Report
Soil sampling testing conducted by Everest
Engineering on OMP Runway 9L-27R - October 2004
Moisture-density-CBR
14Preliminary Geotechnical Report
Soil sampling testing conducted by Everest
Engineering on OMP Runway 9L-27R - October 2004
Unconfined Compressive Strength, Qu
15Soil Sampling Dec. 04 Feb. 05
Current scheduled soil sampling testing from
the R9L-27R
- The Drilling Program
- Auger borings, 17 boreholes, MT-1 to MT-17
- 10 to 45 depths through fill cut areas
- All reaching down to elev. 640 in the natural
subgrade - 3 North of runway, 3 North edge of runway, 4
under runway, 2 South edge of runway, 2 between
runway and taxiway, and 3 under taxiway - SPT and soil sampling at 2.5
- Moisture content, LL, PI, grain size distribution
(clay) - Shelby tube samples at each location (638 to
642) - At least 1 bucket for each major soil in each
borehole - Two 5-gallon buckets (60-70 lbs./bucket) for each
representative soil (composite sample) to test at
the University of Illinois
16Project Tasks
- Task 5
- Based on the data and information gathered in
Task 4, select (in consultation with OMP) the
identified representative soils and recommend an
admixture stabilization program (Ongoing) - Tests to be conducted at the UIUC Advanced
Transportation Research and Engineering
Laboratory (ATREL) on both untreated treated
soils - Moisture-Density-CBR
- Unconfined Compressive Strength
- Resilient Modulus
- Permanent Deformation _at_ 6-psi deviator stress
17Project Challenges
- Proper sampling of the R9L-27R stockpiled soils
- Selecting identifying representative soil
samples - Adequately characterizing the representative soil
samples by conducting tests at the UIUC ATREL for
- Moisture-Density-CBR
- Unconfined Compressive Strength
- Resilient Modulus
- Permanent Deformation _at_ 6-psi deviator stress
18University of Illinois Laboratory Testing Program
at ATREL
Advanced Transportation Research Engineering
Laboratory (ATREL)
1962 Buckets of OMP Soils Arrived at ATREL from the
Drilling Program
MARCH 2005
2062 Buckets of OMP Soils Arrived at ATREL from the
Drilling Program- contd
MARCH 2005
21Grouping of Soils at ATREL
Boring No. Bucket No. Depth Soil Description Clay () LL () PI () Silt ()
GROUP 1 GROUP 1 GROUP 1 GROUP 1 GROUP 1 GROUP 1 GROUP 1 GROUP 1
MT 14 20 5'-10' Gray SILTY CLAY with Sand 17.6 22 6 54.8
MT 16 17 1'-5' Brown and Gray SANDY LEAN CLAY 19.2 30 17 35.4
MT 4 43 1'-4' Gray LEAN CLAY with sand 22.1 24 8 52.4
MT 3 54 29'-33' Gray SANDY LEAN CLAY 22.1 30 11 39.7
GROUP 2 GROUP 2 GROUP 2 GROUP 2 GROUP 2 GROUP 2 GROUP 2 GROUP 2
MT 3 52 6'-10' Gray SANDY LEAN CLAY 22.8 25 8 44.5
MT 3 51 2'-6' Gray LEAN CLAY with sand 23.5 27 12 49.9
MT 4 44 8'-12' Gray SANDY LEAN CLAY 23.7 24 8 42.9
MT 5 50 33'-36' Gray SANDY LEAN CLAY 25.3 28 10 41.6
Grouping done primarily according to clay
content!..
22Grouping of Soils at ATREL
Boring No. Bucket No. Depth Soil Description Clay () LL () PI () Silt ()
GROUP 3 GROUP 3 GROUP 3 GROUP 3 GROUP 3 GROUP 3 GROUP 3 GROUP 3
MT 5 47 1'-5' Gray LEAN CLAY with sand 29 33 13 43.2
MT 15 32 1'-5' Gray LEAN CLAY with Sand 29.2 24 9 41.4
MT 10 36 1'-5' Gray LEAN CLAY with Sand 29.4 24 11 39.3
MT 13 3 16'-20' Gray LEAN CLAY with sand 29.7 32 17 50
GROUP 4 GROUP 4 GROUP 4 GROUP 4 GROUP 4 GROUP 4 GROUP 4 GROUP 4
MT 17 24 18'-21' Brown and Gray LEAN CLAY with Sand 39.4 41 24 39.7
MT 8 16 30'-34' Brown and Gray LEAN CLAY with Sand 39.7 38 19 43.3
MT 12 12 30'-35' Brown and Gray LEAN CLAY with Sand 41.9 46 26 42.6
MT 6 27 6'-10' Brown and Gray LEAN CLAY with Sand 43.7 44 18 38
23Admixture Types / Sources
- Carmeuse (potential supplier)
- South Chicago (dolomitic lime)
- Buffington, IN (high calcium lime)
- Lime types
- Lime Kiln Dust (LKD)
- Quicklime fines
- Buffington is the primary source
- (We will work with this confirm with S.
Chicago)
so far used in lime treatment
24Test Specimen Preparation
Air Drying
Pulverizing
Mixing
25Moisture- Density- CBR Results
CBR (ASTM D1883)
Untreated
Proctor Compaction (ASTM D698, D1557)
26Group 1 Results
0 Lime 0 Lime 5 Lime 5 Lime
W () Dry Density ( pcf ) W () Dry Density ( pcf )
10.2 117.89 10.7 110.44
11.9 121.72 13.2 114.30
14.3 118.84 16.3 112.97
16.1 113.27 19.3 107.57
27Group 1 Results
California Bearing Ratio (CBR)
0 Lime 0 Lime 5 Lime 5 Lime
W () CBR W () CBR
10.1 44 10.5 77
11.4 22 13.1 61
13.8 5 15.8 16
15.8 2 19.1 5
28Group 1 Results
29Group 2 Results
0 Lime 0 Lime 5 Lime 5 Lime
W () Dry Density ( pcf ) W () Dry Density ( pcf )
12.4 115.36 14 109.81
14.1 119.06 16 114.98
15.8 114.84 18.9 110.23
18.3 108.74 22.4 102.34
30Group 2 Results
California Bearing Ratio (CBR)
0 Lime 0 Lime 5 Lime 5 Lime
W () CBR W () CBR
11.7 26 13.2 55
13.4 15 15.9 39
15.7 4 18.6 10
17.6 1 22 4
31Group 2 Results
32Group 3 Results
0 Lime 0 Lime 5 Lime 5 Lime
W () Dry Density ( pcf ) W () Dry Density ( pcf )
12.3 112.85 13.6 107.00
14.4 117.61 17.1 107.65
16.4 113.21 19.8 107.53
18.1 108.75 22.7 102.39
33Group 3 Results
California Bearing Ratio (CBR)
0 Lime 0 Lime 5 Lime 5 Lime
W () CBR W () CBR
11.9 27 13.3 55
13.9 13 16.1 35
15.8 4 19.2 13
18 1 22.2 6
34Group 3 Results
35Group 4 Results
0 Lime 0 Lime 5 Lime 5 Lime
W () Dry Density ( pcf ) W () Dry Density ( pcf )
17.2 102.97 16.9 96.91
18.7 105.26 20.0 97.38
21.2 103.77 23.4 98.00
22.9 100.39 26.5 94.30
36Group 4 Results
California Bearing Ratio (CBR)
0 Lime 0 Lime 5 Lime 5 Lime
W () CBR W () CBR
16.0 26 16.7 41
18.7 19 19.6 34
20.6 10 22.4 25
22.3 6 26.3 12
37Group 4 Results
38Unconfined Compressive Strength Test Results
t
sd s1 s3(0)
failure
C (s1f)/2 Qu/2
s1
s1f
s3 0
s
- Cohesive Soils (c, f0)
- (ASTM D2166)
39UCS without Lime
Group No. OMC () Water Content () Dry Density (pcf) UCS (psi)
1 12.1 12.3 122.5 80
2 14.1 14 118.7 44
3 14.4 14.2 118.7 60
4 18.8 19.5 108.2 74
40UCS Without Lime
41UCS with 5 Lime
Group No. OMC () Sample No. Water Content () Dry Density ( pcf ) UCS (psi) Avg. UCS (psi)
1 13.8 1 13.3 106.64 109 119
1 13.8 2 13.7 108.5 120 119
1 13.8 3 13.8 109.49 128 119
2 16 1 15.3 116.82 202 184
2 16 2 15 116.11 177 184
2 16 3 15 115.36 174 184
3 18.8 1 17.5 110.43 129 138
3 18.8 2 17.9 110.48 146 138
3 18.8 3 17.9 110.50 138 138
4 22.8 1 22.1 98.2 197 217
4 22.8 2 22.2 98.4 233 217
4 22.8 3 22.1 97.7 221 217
42Group 1 with 5 Lime
43Group 4 with 5 Lime
44Lime Reactivity
Group No. UCS with Lime Qulime (psi) UCS without Lime Qu (psi) Lime Reactivity (Qulime - Qu) (psi)
1 119 80 39
2 184 44 140
3 138 60 78
4 217 74 143
45Resilient Modulus (MR) Testing
sd
Unconfined s3 0
2-in. in f
MR resilient modulus sd / er sd
Deviator stress er recoverable strain
Conditioning 200 load applications at s3 0,
sd 41 kPa Testing 100 load applications
sd 14, 28, 41, 55, 69, 83, 96, 110 kPa
46MR Tests Soil Samples
Cylindrical specimens, 2 in. f by 4 in. high
Undisturbed soil samples Shelby tube (f 2.8,
4 in.)
47Typical MR Characterization
Greensboro, NC Airport Subgrade Soils
28
24
A-4 soil at OMC
A-4 soil at OMC3
20
Bilinear or Arithmetic Model
16
s
M
- 0.6274
1820
R
d
2
R
0.6617
12
8
4
s
M
- 0.4203
8.351
s
R
d
M
0.0408
4.9412
R
d
2
R
0.8715
2
R
0.8796
0
0
2
4
6
8
10
12
14
16
18
s
APPLIED DEVIATOR STRESS
(psi)
d
48Group 1 MR Test Results
Eri
49Group 2 MR Test Results
50Group 3 MR Test Results
Eri
51Group 3 MR Test Results
52Group 4 MR Test Results
Eri
53Group 4 MR Test Results
Eri
54Summary of Results (1)
- Moisture Density CBR Tests
- Optimum moisture contents of the natural soils
were always lower those of the same soils treated
with 5 lime kiln dust (LKD) - Similarly, maximum dry densities were always
higher for the natural soils without lime
treatment - The unsoaked CBR values obtained from testing the
compacted specimens tend to drop sharply after
the optimum moisture contents for the soils
without lime - The treated soils with 5 lime always gave much
higher unsoaked CBR values than the natural soils
with no lime - In general, the 5 lime treatment was effective
for increasing sufficiently the strength of the
North Runway 9L-37R subgrade soils tested
55Summary of Results (2)
- Unconfined Compressive Strength Tests
- Large increases in unconfined compressive
strengths observed for all groups when 5 lime
was added - Lime reactivity (Qu lime treated - Qu natural) is
greater than 50 psi for all the groups except for
Group 1 - Minimum lime treated Qu 119 psi was recorded
for Group 1 soils with the lowest clay contents
the least reactivity with lime - Resilient Modulus (MR) Tests
- MR decreased with increasing applied deviator
stresses typical stress-softening fine grained
soil behavior - All soil groups tested at the OMC gave high MR
values at 6 psi deviator stress, in the range of
Eri 15-20 ksi
56Conclusion
From the results of all tests performed, Green
Light is given to the 5 lime kiln dust
treatment which seems to be working quite well in
increasing the soil strengths and, therefore, is
suggested as the stabilization choice for the
subgrade soils at the new North Runway 9L-27R of
OHare International Airport
57Project Deliverables
- Technical Notes have been prepared and submitted
to the OMP throughout the project duration to
communicate specific findings and recommendations
to OMP engineers - TN5 K-150 Considerations for RW 9-27
- TN6 Subgrade Strength/Stiffness Evaluation
- TN7 Working Platform Requirements for Pavement
Construction - TN8 Subgrade Stability Manual (IDOT)
- TM13 Moisture Limitations for Lime Stabilization
- TN14 Admixture Stabilization (Lime Treatment of
Subgrades) - Several of the Project Tasks have been pursued
simultaneously and coordinated with OMP - A Report summarizing Laboratory Soil Test Program
has been prepared. More soil-lime testing will be
conducted with different lime sources - A Final Report will be prepared at the end of the
one-year study (September/October 2005) - We will continue to work with OMP on future
subgrade soil support and stabilization needs for
other runways/taxiways