Opération TCR
  • From 1 of November to the 6 of December
  • Henrik Nissen

2
Week 47 (15-21 Nov.)
  • Wednesday 17 559--925
  • Defaut Bucholz Bat. 861 (Reseau pulse)
  • Trafo disconnected, SPS stopped
  • Reseau pulse supplied from reseau stable
  • Thursday 18 0108-- 0250
  • Alarme fuite vase exp. ED BA2
  • After EJP could not start with UMMI due to alarm
  • Called piquet, SPS startup delayed

3
Week 47 (15-21 Nov.)
  • Friday 19 0113--0228
  • Not possible to start ED BA6 with UMMI
  • SPS startup delayed
  • Piquet could not start pumps, called responsible
    ST/CV
  • Sunday 21 1238--1635
  • Defaut Compensation puissance reactive Bat. 861
  • SPS stopped, Intervention piquet ST/EL