Title: Lyme Regis No longer Slip-sliding Away
1Lyme Regis No longer Slip-sliding Away
2Introduction
3Location
- England
- Southwest Coast
- Dorset
- Jurassic Coast World Heritage Site
- Exposed to severe winter storms
4West, 2006
5Stormy Weather
Undated, 1970s storm Source West, 2006
6Calm Weather
7The Geology of Lyme Regis
- Greensand
- Clay
- Shale
- Blue Lias
8Steep slope
9The Beginnings of a Landslip
- Charmouth Road Car Park
- Asphalt is contributing to landslip
- Work underway to improve drainage system
10The Black Venn
- Between Lyme Regis and Charmouth
- Mostly Clay and Shales with Beef
- Prone to landslides
- Rich source of fossils
11The Blue Lias
- West of Lyme Regis at Monmouth Bay
- Greensand
- Clay
- Limestone
12Landslides
- 1962 Langmoor Gardens
- Caused by construction activities
- The area was re-graded and Langmoor gardens were
established
13The Spittles
- East of Lyme Regis
- The whole system was reactivated in 1986
14Long-shore drift interrupted
- Beach buildup
- Monmouth beach
- Increased protection
- Beach depletion
- Shingle supply interrupted
- This results in depletion
15The depleted beach(1960s) and breached seawall
(1974)
16Coastal Defenses - The Cobb
17Coastal Reinforcements
- Beacon Rocks extended by 110 meters
- North wall rockery realigned
- Added rock armor at Cobb Gate
- New jetties at Lister Gardens and Cobb Gate
- Beach replenishments
- Sand and shingle
- Raised beach level by 2 meters
18Beacon Rocks
19- Armor rocks
- 11,000 tonnes core rock, 2 - 5 tonnes each
- 26,500 tonnes armor, 9 - 18 tonnes each
- Source Norwegian granite
- Byproduct of granite counter top industry
- Shingle (pebbles)
- 72,000 tonnes
- Source Isle of Wight
- Sand
- 37,000 tonnes
- Source northern France
- Precast concrete
- Source UK
- Limestone facing
- Source China
20Rock Armor at Cobb Gate Jetty
21Finishing up at Cobb Gate Jetty
22Reinforcements at Cobb Gate
23Lyme Harbor beach restored
24Work continues at Langmoor Gardens
25Slope stabilization
- Began in 2005, scheduled completion 2007
- Major engineering effort involved considerations
for seismic stability - Only small equipment allowed until slope was
sufficiently stabilized - Gradual increase in machinery size based on
monitoring
26- 1,150 auger-cast piling
- Drilled holes thru clay into bedrock
- Filled with concrete and reinforcement
- Act as dowels to hold slope
- Soil nails
- Similar to piling but horizontal
- 2,300 meters drainage
- Counterforts - at base
- Drilled drains -in hill
- French drains - below car park
27Conclusion
- Phase II construction is nearly complete
- Coastal defenses
- Slope stabilization
- Increased security for town
- Increased income due to tourism
- Cost to maintain will be less than the cost of
emergency repairs