Title: FOT ACIS Training
1FOT ACIS Training
- HW and SW Overview
- Flight Operations
- X-Ray CCD Basics
- Radiation Damage and Contamination
- Science Examples with ACIS (pretty pictures)
2Overview of ACIS HW and SW
- ACIS HW, MAIN COMPONENTS
- DEA, Detector Electronics Assembly - analog
electronics to clock the CCDs and process analog
data, contains video boards for the CCDs MIT - DPA, Digital Processing Assembly - contains
Back-End Processors (BEPs) and Front-End
Processors (FEPs), processes digital data from
the from DEA (CCDs) and SW commands MIT - DH, Detector Housing - contains CCD focal plane
(FP), optical blocking filter (OBF), proton
shield, collimator Lockheed-Martin and Lincoln
Laboratories - PSMC, Power Supply and Mechanism Controller -
power supplies, door and valve controllers,
connection to the ISIM RCTU, processes HW
commands - Lockheed-Martin
- Radiators - Warm (connected to DH) and Cold
(connected to FP) radiators Lockheed-Martin
3ACIS Flight SW
- ACIS BEPs controls all science functions which
CCDs are on, which video boards are on, which FEP
is connected to which CCD, ACIS TLM formats, etc. - Normal commanding entails only ACIS SW
commands, in fact we have not sent a HW command
to ACIS since 15 July 2004 (a Warm Boot) ! This
means the weekly Chandra load contains only SW
commands. - ACIS SW commands are of variable length, the
parameter block is the most important, it
contains about 150 commands - Flight SW has been patched several times since
launch, the latest version is loaded by
SOP_ACIS_SW_EVHCC3X3_CATL (4/15/2004)
4ACIS HW Diagram
5ACIS HW Diagram Exploded View
6ACIS Detector Housing
7ACIS Engineering Unit Door Mechanism
8ACIS Focal Plane Support Drawings
9ISIM at Ball with SIs
10(No Transcript)
11ACIS CCDs, FEPs, VB Connections
12ACIS PSMC Interfaces
13ACIS DPA Interfaces
14ACIS Focal Plane
15ACIS Paddle Design
16HW Design and Lifetime Issues
- DEA - 10 video boards (VB), one VB hard-wired to
one CCD, the loss of one VB would result in the
loss of that CCD - DEA - A/D converters may experience long-term
degradation due to radiation exposure - DPA - FEPs multiplexed to the CCDs, any FEP can
process data from any CCDs - DPA - FEP0 anomaly has been of no consequence
since we started assigning FEP0 last - DPA - both side A and side B of the DPA must be
powered on to clock 6 CCDs - Radiators - cooling capacity is less than
pre-launch predictions, have difficulty
maintaining -120 C, more on this later - CTI - CTI of the FI CCDs may increase to the
point at which the CCDs are no longer useful for
scientific observations - Contamination - contamination may increase to
the point at which science observations are more
seriously impacted than now
17ACIS Mass
Weight (lbs)
Detector Assembly 20.8
Venting Subsytem 8.7
Support Assembly 124
Thermal Control and Isolation 5.4
Radiators 10.2
Sun Telescope Shades 16.0
PSMC 32.7
PSMC Cables 9.1
SIM Mounted Cal Source 4.3
Total Weight 254
- total weight from Observatory to SI ICD
(CM07a), email from Bill Mayer - Email from Bill Mayer, all other weights from
May 1997 Monthly Report
18Flight Operations
- OPERATIONAL CONFIGURATIONS
- Only three general ones thankfully, Normal
Science,Thermal Standby, Radiation
Shutdown because there is so much margin in the
spacecraft power budget
Mode DPA A 1DP28AVO 1DPICACU DPA B 1DP28BVO 1DPICBCU DEA A 1DEA28AVO 1DEICACU DA htr B 1DAHBVO 1DAHBCU Total
Normal Science (6 CCDs) 40 W 35 W 57 W 5 W 137 W
Thermal Standby 40 W 35 W 26 W 5 W 106 W
Radiation Shutdown 12.5 W 8 W 26 W 5 W 51.5 W
- DPA A B On DEA A on, DEA B off, DA Htr side B
On, this is normal - DEA A power consumption will vary depending on
the number of active CCDs - DEA current monitor is noisy must integrate to
get an accurate reading - Cold Radiatior (1CRABT) at -127.3 C, Warm
Radiator (1WRABT) at -82.0 C - ACIS Ops web page http//asc.harvard.edu/mta/RT/a
cis/www/acis-mean.html displays realtime data,
average 10 samples, computes power
19Flight Operations
- Radiation Environment
- The pre-launch concern was high energy protons
(Egt10 MeV), hence the heavy proton shield around
ACIS - The unfortunate discovery post-launch was that
low-energy protons (100 keV) reflected off of
the mirror with a small but not negligible
efficiency - The solution was to translate the SIM to the
HRC-S position for every perigee passage - Low energy protons outside of the belts also
produce damage - EPHIN only measures protons from 5 MeV and up,
the spectrum of the protons varies from one solar
event to the next, sometimes the low and high
energy protons both go up dramatically, sometimes
only the low energy protons go up significantly - Use ACE to monitor the 112-187 keV protons on
the way, use GOES P2 channel (4-9 MeV) to better
predict EPHIN P4 GM rates - Use EPHIN P4GM, P41GM, and E1300 as SCS107
triggers P41GM for hard proton events, P4GM for
softer proton events, E1300 as a failsafe
detector out of the belts - HETG is assumed to provide a factor of 5
attenuation for 100 keV protons and the LETG a
factor of 2
THE SIM MUST BE AT HRC-S (-99616) FOR EVERY
PERIGEE PASSAGE !!!!!!
20Flight Operations
- Operational Issues and Concerns
- Perigee passages - the SIM must be at HRC-S and
the video boards powered down - RADMON MUST be enabled if ACIS is in the focal
plane - Unsafe ACIS Response - procedures developed,
SAP_UNSAFE_ACIS_PHASE1 and SOP_UNSAFE_ACIS_PHASE2.
Should we schedule a separate meeting to review
these procedures in detail ? - FP temperature regulation - it has become more
difficult over the course of the mission to
maintain -120 C on the FP. Analysis is under way
to determine if this is caused by earth in the
ACIS radiator FOV or Sun on the ACIS radiator
shades or both. One option it to turn off the
ACIS DH heater, this would require significant
analysis from FOT Thermal for approval. - Multiple Limit Sets - ODB, Greta, SOT MTA, ACIS
Ops, ODB needs to be updated, other three sets
have the latest limits - PSMC gets warm for pitch angles between 45-60,
(1PIN1AT, 1PDEAABT), raised the limits for
these values to the ground qualification limits
in February 2005, need to get the ODB updated - DPA-A shutdown anomaly - occurred twice on
October 26, 2000 and December 19, 2002, most
likely due to a SEU in the ISIM RCTU - Threshold Crossing Plane Latchup - occurred three
times over the life of the mission. Last
occurrence was Nov 5, 2001. We now power-cycle
the FEPs before
21Flight Operations
- Operational Issues and Concerns (continued)
- observations which compute a new bias. This
wont prevent the latchup from occurring but it
will reset the memory chip so that subsequent
observations wont be affected. - Large ACIS commands - ACIS PBs are much larger
than most spacecraft commands. The loads cannot
put another command directly after the ACIS PB
command because the OBC will not complete
processing the PB in time. The risk is that the
load will hang. - THREATS to ACIS
- SIM at the incorrect position
- Spacecraft attitude is incorrect so that the Sun
is on the ACIS radiator or the HRMA - Any future ACIS HW commanding. SW commanding
should be innocuous. - An ACIS bakeout.
- Contamination damages the instrument, perhaps the
OBF - PSMC gets warm enough that a component fails
22ACIS FP Cooling Tests to Date
Date Duration (ks) Min Temp (C)
2005070 43 -121.86
2004201 101 -121.58
2003133 114 -121.96
2003130 54 -121.64
1999354 46 -123.09
23(No Transcript)
24Issues for the FOT SOT in 2005
- PSMC heating, we may have to reduce the duration
of observations at pitch angles between 45 and 60
degrees - BAKEOUT !!!!!
- Analysis of FP heating, we need to understand
what the effect is and if there is anything we
can do to limit the heating - We may have to study the feasibility of turning
off the ACIS DH heater to provide more margin on
the FP
25X-Ray CCD Basics
- An X-ray photon interacts with the CCD by
liberating electrons in one or a few pixels - The electrons are held in the pixel by the
electric fields in the CCD, until it is time to
be read out when the fields are varied to clock
or push the charge out the readout amplifiers - The number of electrons is proportional to the
original energy of the X-ray photon, thus the
position and energy of the photon can be measured - ACIS CCDs were manufactured at MIT Lincoln
Laboratories. They are 1024X1024, 24um pixel,
frame-transfer CCDs, meaning there is a 1024X0124
pixel imaging region and a 1024X1024 pixel
framestore region - ACIS has 8 Frontside-Illuminated CCDs and 2
Backside-Illuminated CCDs - ACIS allows the CCDs to be clocked in a Timed
Exposure mode or a Continuous Clocking mode.
Full frame requires a 3.2s static integration
time. - ACIS also allows subarrays, spatial windows, and
different events filters - ACIS flight SW detects events and reports only
those pixels with charge from X-ray events, other
pixels are not telemetered. Hence, X-ray CCDs
are usually operated in the photon-counting
mode. - ACIS has several different telemetry formats for
reporting information about each event. It also
has a mode specifically designed for FMT 1 when
the HRC is the prime instrument.
26ACIS Timed Exposure Mode Clocking
Image to Framestore Transfer 41us
Framestore Readout 3.2
Integrate for 3.2s
27X-rays in ACIS Full Frames
I3, subassembly O-K (0.525 eV)
I3, subassembly Cu-K (8.09 keV
28Initial Damage of the ACIS CCDs
- ACIS-S was at the launch-lock position,
launch on DOY 204 (1999) - First measurements of internal Fe-55 source were
nominal on DOY 210 - ACIS Door was opened on DOY 220 and Aft
Contamination Cover of the HRMA was opened on DOY
223 - Measurements of calibration sources on Forward
Contamination Cover (FCC) were nominal on DOY 224
(see Elsner et al. SPIE 2000) - FCC opened late on DOY 224, first light with
ACIS, first unprotected perigee passage on DOY
225 - ACIS-S at focus for 5 perigee transits, ACIS-I
for 3 perigee transits, and ACIS-S/HETG for 2
perigee transits - Large increase in CTI discovered on DOY 250, DOY
257 was the last unprotected perigee transit
and DOY 260 was the last ACIS-S/HETG perigee
transit
29Radiation Damage of the ACIS CCDs
- The CTI increase was caused by low-energy (100
keV) protons, which scatter off of the mirror
surfaces to the focal plane. - All 8 FI CCDs exhibit a large increase in CTI,
damage is restricted to the imaging region,
framestore regions are unaffected. - Neither of the BI CCDs shows any damage.
- No increase in the dark current of the FI CCDs.
- Irradiation of flight-like CCDs with 100-150 keV
protons produces similar damage. - Prigozihn et al. (2000) identify 4 types of
traps, two with timescales of tens to hundreds of
ms, one with hundreds of ms, and one on the order
of several seconds - Kolodziecjzak et al. (SPIE 2000) simulated the
scattering of protons off of the HRMA and
transmission to the focal plane, they conclude
that it is plausible but their model
underpredicts the damage by a factor of 3-4 and
preliminary ground measurements indicate the
scattering efficiency is not high enough
30(No Transcript)
31Spectrum of 1E0102-723 No or little degradation
32Spectrum of 1E0102-723 Significant degradation
33Operational Response
- ACIS is always moved out of the focus of the
HRMA before radiation belt transit. - A 10 ks pad has been added on either side of
the radiation belts. - Data from other satellites with sensitivity to
low-energy protons have been incorporated into
the Chandra alert system. - On-board thresholds for safing have been
adjusted.
Mitigation Techniques
- Operate the CCDs as cold as possible, currently
-120 C. - Develop a phenomenological correction for the
effects of CTI, improve the quality of the data - perhaps use new modes in the future which will
report additional information for each event
which could lead to a better correction for CTI
34CTI Correction at Al-Ka (1.5 keV)
35CTI Correction at Mn-Ka (5.9 keV)
36Average ACIS-I CTI
Grant (MIT)
37Average ACIS-S3 CTI
Grant (MIT)
38ACIS Contamination Brief Description of the
Problem
Problem A layer of contamination is building up
on the ACIS Optical Blocking Filter
(OBF). Impact The contamination layer reduces
the transmission of X-ray photons through the
OBF, thereby reducing the number of photons which
reach the CCDs. This decreases the effective
area of the High-Resolution Mirror Assembly
(HRMA) and ACIS system. The effective area
is defined as the combination of the collecting
area of the HRMA, the transmission of the OBF,
and the detection efficiency of the CCDs. The
detection efficiency is defined as the
probabilty of detecting a photon which strikes
the detector. This effect is energy-dependent,
affecting low energies most. The decreased
sensitivity results in
- longer observing times to achieve the same
science objective ( 15) - loss of some science programs because they are
no longer feasible (15)
39Comparison to Level 1 Requirements (Detection
Efficiency)
- Level 1 requirements on the ACIS instrument
detection efficiency are greater than 5 between
0.4 0.7 keV, 20 between 0.7-1.0 keV, and 50
between 1.0-8.0 keV - The decrease is due solely to the additional
absorption of the contamination layer
- At the current rate of increase in the thickness
of the contamination layer, the level 1
requirement will not be met at 0.4 keV around
November 2005
Bandpass Level 1 Req. Launch
Value 6/2004 Value
0.4- 0.7 keV gt 5 gt29 gt7
0.7-1.0 keV gt 20 gt59 gt35
1.0-8.0 keV gt50 gt50 gt50
40Contamination, Bakeouts CTI Increase
- Contamination was expected on ACIS during the
mission since ACIS contains the coldest surfaces
internal to the spacecraft - The pre-launch plan was to bake ACIS out at
regular intervals to minimize the buildup of
contamination
- There have been two ACIS bakeouts to room
temperature in the mission, both early in 1999.
The first bakeout was part of the ACIS door
opening procedure. The CCDs were functioning
nominnally before and after this bakeout. - The CCDs suffered radiation damage from
low-energy protons (100 keV) in August and
September 1999. Further damage has been
minimized by moving ACIS out of the focus of the
HRMA during radiation belt passages. - The second room temperature bakeout was an
attempt to anneal the CCDs (to reverse some
of the effects of the radiation damage).
Unfortunately, the CCD performance got worse
after the second room temperature bakeout (CTI
increased by 30). - This leads to the expectation of increased CTI
for another bakeout.
41Mitigation Options
- Accept degradation, relax the level 1
requirements on detection efficiency - Bakeout to remove the contamination
Proposed Bakeout Scenario
- Heat the ACIS detector housing (DH) from -60 C
to 20 C - Heat the ACIS focal plane (FP) from -120 C to
20 C - DO NOT Heat the Science Instrument Module (SIM)
surfaces surrounding the ACIS aperture from -10 C
to 10 C - Maintain the hot phase of the bakeout for 1
orbit (150,000 s)
42Risks Associated with Bakeout
Definition Risk to the spacecraft or instrument
health safety, and/or to the science mission.
- Thermal cycling results in a HW failure in the
ACIS instrument - Damage to the OBF
- CTI increases by a larger than anticipated amount
- Unexpected change in contamination
- 4a) contamination increases in thickness
- 4b) contamination returns quickly
- 4c) contamination migrates to another
spacecraft system - Thermal cycling has a negative impact on the
spacecraft -
43Risk Assessment
RISK MITIGATION IMPACT PROBABILITY
1. HW failure due to thermal cycling Assessment by ACIS engineering team, HW design, previous bakeouts Moderate Possible degradation Very low
2. OBF Damage Ground tests at NGST on spare flight OBFs Moderate Loss of science Very low
3. Larger than anticipated CTI increase Ground irradiation tests on spare flight CCDs Low Loss of science Very low
4. Undesirable change in contamination Simulations of bakeout, materials testing Moderate Loss of science Low
5. Thermal cycle has adverse effect on spacecraft Assessment by Chandra FOT and NGST Low Possible misalignment Very low
44Benefits of the Bakeout
- Restore the HRMAACIS effective area to close to
launch values and restore the original margin
against the level 1 requirements - Provide an additional 2.8 Million seconds of
observing time per AO, which will be 54
additional Chandra observations per AO - Restore classes of targets with soft spectra
which are not currently feasible (such as
supersoft sources, neutrons stars with soft
spectra)
Costs of the Bakeout
- The bakeout and calibration observations will
take 1 Million seconds. Given that the
contaminant accumulation is slowing in time and
we have gone 5 years without a bakeout, we expect
that we would not desire another bakeout for at
least another 5 years. - The likely CTI increase of the FI CCDs will
impact observations of extended objects on the I
array through degraded spectral resolution - The delay in some analyses until updated
calibration products are available
45External Calibration Source Mn-L complex/Mn-K vs
Time
Grant (MIT) Analysis
Tennant, ODell (MSFC) Functional Form
46E0102 Spectrum vs. Time
47E0102 Count Rate vs. Time
DePasquale (SAO)
48Optical Depth vs. Time based on the Mn-L
complex/Mn-K
Vikhlinin (SAO)
Bottom of S3 CCD
Middle of S3 CCD
Contaminant is thicker along the edges of the I
and S array OBFs, thinnest in the middle.
Contaminant has reached over 80 of its maximum
depth.
49Material Investigation (from Kelly Henderson and
Marty Mach)
- Several materials were tested in an attempt to
identify the contaminant - GCMS was performed to determine the elemental
ratios of the outgassing products for materials
used on Chandra - None of the materials tested had ratios similar
to that of the ACIS contaminant - None of the materials tested indicated
fluorocarbons in the outgassing products, except
Braycote, which evolved a very small amount - It was suggested that radiation could enhance the
outgassing rate of Braycote and other materials - Braycote 601 grease irradiated w/ 27Co60 gamma
radiation was more volatile and the only material
that liberate fluorocarbons per GCMS and VODKA
tests - Most of the materials tested spanned the
retention time (similar boiling point range) of
the Braycote 601 grease. It was therefore chosen
as the model compound
CONCLUSION The contaminant is most likely a
mixture of several materials and not just one
material.
50(No Transcript)
51ACIS Optical Blocking Filter
ACIS-I OBF Al/Polyimide/Al 1200A/2000A/400A ACIS-S
OBF Al/Polyimide/Al 1000A/2000A/300A
52Thermal Models of the ACIS Instrument
Purpose In order to model and understand the
bakeout, one must know the temperatures of all
the surfaces the contaminant might encounter.
Modeling provided by Neil Tice at LMA, ACIS
thermal engineer pre- and post-launch Collimator
primary surface which the contaminant will
interact with on its way out of the instrument
during the bakeout Detector Housing upper
portion probably contains the majority of the
contaminant by mass and the OBFs are installed in
the DH OBFs significant temperature gradient
across the filters In order to model the bakeout,
the temperatures of the relevant surfaces in ACIS
must be known for 1) Normal operations, FP -120
C, DH-60 C 2) Bakeout conditions, FP 20 C,
DH20 C
53Tice (LMA)
54ACIS Filter Temperatures for Standard Conditions
Tice (LMA)
55Geometric model
OBA vent
SIM focus structure
SIM translation table
Optical bench (OBA)
ACIS collimator
Snoot
OBA stove pipe
ACIS camera top
ACIS OBF
TRASYS model by NGST/ H. Tran et al.
56Integrated Science Instrument Module (ISIM)
Translation Table
Focus Assembly
Top Hat Stove Pipe
ACIS Aperture
57Contaminant Path of Travel
ACIS Location
OBA Vent Locations
Contaminate Migration Path
Optical Bench Assembly (OBA)
Integrated Science Instrument Module (ISIM)
5810.DOP de-rated TOBF Mass column
ODell Swartz (MSFC)
1 ACIS OBF 2 Camera top 3 ACIS snoot 4 ACIS
collimator 5 SIM trans table 6 SIM focus
struc 7 OBA stove pipe 8 Optical bench 9 OBA
vent
NOMINAL
DE-RATED
591.0DOP de-rated TOBF Mass column
ODell Swartz (MSFC)
NOMINAL
DE-RATED
1 ACIS OBF 2 Camera top 3 ACIS snoot 4 ACIS
collimator 5 SIM trans table 6 SIM focus
struc 7 OBA stove pipe 8 Optical bench 9 OBA
vent
60Limits on vaporization rates
ODell Swartz (MSFC)
Min to vent 0.2 g in 1 orb5?10-3 mg cm-2 s-1 _at_
Tcoldest
Min to clean OBF in 1 orb2?10-3 mg cm-2 s-1 _at_
TOBF-bake
Upper limit at OBF center1?10-7 mg cm-2 s-1 _at_
TOBF-ops
61Conclusions From New Simulations
- If the contaminant has a volatility of less than
0.1 X DOPs volatility, a one orbit 30 C bakeout
will not move a significant amount of the
contaminant - If the contaminant volatility is within an order
of magnitude of DOPs volatility, a significant
amount of the contaminant will vaporize and
migrate to the cold surfaces at the top of the
ACIS collimator and the SIM. The contaminant
will then migrate very slowly back to the OBF and
it may be years before a significant amount
re-accumulates on the OBF - If the contaminant volatility is an order of
magnitude higher than that of DOP, a significant
amount of the contaminant will vaporize and
migrate to the cold ACIS collimator and SIM
surfaces. The contaminant will then migrate back
to the OBF such that after 1 year, the thickness
will be 1/3 of the original thickness.
62Work Still to be Done (January 2005)
- ACIS team will conduct irradiation tests,
analyze the results, and refine the prediction
for the effect of another room temperature
bakeout on the CTI - The working group will prepare another briefing
for the Chandra project and seek approval for the
bakeout
63Orion Nebula
Orion Nebula, X-ray
64E0102 Chandra and ROSAT Images
Gaetz et al. 2000
Hughes et al. 2001 t 1000 yr
1 arcmin
65CAS-A ACIS S3 50ks
Gotthelf et .al 2001
t 350 yr
4 arcmin
66Cas A
1 Million second true-color Image of Cas-AGreen
ContinuumBlue FeRed SiHwang et al.(2004)
67Cas A
Cas-A The Movie
68- Crab Nebula (Mori et al 2002), compliments of
Hester/Mori/Gaensler - Wisps move outwards at 0.43c (similar
features seen in optical/radio) - Inner ring quasi-stationary
- Knots brighten over 6 months
Crab Nebula (0, 3, 6, 9, 12, 15, 18, 21 weeks)
69SN1987A Chandra and HST
Image Chandra Contours HST Burrows et al. 2000
2 arcsec
70SN 1987A, Montage
SN 1987A Montage
Burrows et al. 2000
ATCA 8 GHz
HST
ACIS 2000 Jan 17
ACIS 1999 Oct 6
71G292.01.8 A SNR Like They Outta Be
Hughes et al. 2001, Park et al. 2002, Camilo et
al. astro-ph/0201384
0.5-2.5 keV
2.5-8.0 keV
8 arcmin
t 1600 yr
72Summary of Advances in SNR Research with Chandra
- Resolve the X-ray emission into smaller and
hopefully, physically meaningful regions - Allow a detailed correlation with high
resolution radio and optical data. - Separate the outer blastwave from the ejecta so
that one can use the outer blastwave for
dynamical studies - Discovery of new compact objects, some
traditional pulsars, others perhaps a new class
of objects Central Compact Objects. - Discovery of new synchrotron nebulae.
- In the future, proper motion studies of
shockfronts and bright knots.
High Angular Resolution is the Key !!!!!
We owe our gratitude to the thousands of
engineers and technicians who built AXAF/Chandra
!!!