What will be the total cost for the project of a person with 20 person-month of ... 15.C / The subcontracted task cannot be performed by the contractor, and is ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 25
Provided by: abo101
Category:

less

Transcript and Presenter's Notes

Title: FP7 Financial basics Quizz


1
FP7 Financial basicsQuizz
  • Koos DE KORTE
  • Belgrade, January 2008

2
Definitions
  • EC European Commission
  • FP Framework Programme
  • SME Small- Medium-sized Enterprise

3
Question 1
  • In a project, an SME has real indirect costs of
    71.
  • What will be the total cost for the project of a
    person with 20 person-month of research planned
    for that project if the hourly rate is 30 and a
    month 148 hours?
  • 1.A / 88 800
  • 1.B / 151 848
  • 1.C / 113 886

4
Question 2
  • The following can be funded at 100
  • 2.A / The filing of a patent application
  • 2.B / A study on the societal impact of a
    technology created by a project
  • 2.C / The testing of the prototype of a
    technology created by a project
  • 2.D / The organization costs for a networking
    seminar.

5
Question 3
  • What is the meaning of the non-profit principle?
  • 3.A / The EC grant that reimburses project costs
    cannot exceed 100 of the total project costs
  • 3.B / The contractors are not allowed to make
    profit by exploiting the results of the project.
  • 3.C / The EC grant that reimburses project costs
    cannot be used for other purposes than those of
    the project.
  • 3.D / None of the above.

6
Question 4
  • If the project will have receipts to take into
    account in its financial statement.
  • 4.A / If it organizes a workshop and charges
    entrance fees.
  • 4.B / If One partner funds part of the activities
    of another project partner
  • 4.C / If It generates income the sale of a
    technology produced by the project
  • 4.D / If a project partner receives a financial
    contribution from a third party. 

7
Question 5
  • In the case of an EC grant that reimburses costs,
    which costs are reimbursed?
  • 5.A / All the costs
  • 5.B / Only the so-called eligible costs
  • 5.C / All the costs except the subcontracting
    costs
  • 5.D / None of the above

8
Question 6
  • When is the income generated in using the
    knowledge resulting from the project considered
    as a receipt to the project?
  • 6.A / Always
  • 6.B / Only when the project is successful.
  • 6.C / Never
  • 6.D / None of the above

9
Question 7
  • Which are the type(s) of activities that are
    always 100 reimbursed by the EC?
  • 7.A / Research Management activities
  • 7.B / Management activities only
  • 7.C / Management training activities
  • 7.D / None of the above

10
Question 8
  • When choosing the lump sum financing option,
    partners from the following countries are
    considered as coming from lower middle income
    countries.
  • 8.A / Albania, Bosnia and Herzegovina, Paraguay
  • 8.B / Lebanon, FYROM, Argentina
  • 8.C / Algeria, Chile, Egypt
  • 8.D / Jordan, Mexico, Russian Federation.

11
Question 9
  • Is VAT (Value Added Tax) an eligible cost?
  • 9.A / Yes
  • 9.B / No
  • 9.C / Sometimes
  • 9.D / None of the above

12
Question 10
  • How must the contractors record the project
    costs?
  • 10.A / The project costs must be recorded in the
    contractors accounts following the contractors
    usual accounting principles.
  • 10.B / The project costs must be recorded in the
    contractors accounts according to specific FP6
    rules defined by the EC.
  • 10.C / The project costs must be recorded in
    separate accounts according to the contractors
    usual accounting principles.
  • 10.D / None of the above

13
Question 11
  • Are the preparation costs incurred before the
    official starting date of the project eligible?
  • 11.A / Yes
  • 11.B / Yes but only if the project is selected by
    the EC
  • 11.C / No
  • 11.D / None of the above

14
Question 12
  • What is the general mathematical relationship
    between direct and indirect costs?
  • 12.A / Indirect costs equal 20 of direct costs
  • 12.B / Indirect costs equal 7 of direct costs
  • 12.C / Indirect costs equal a percentage of
    direct costs
  • 12.D / None of the above

15
Question 13
  • On which costs are calculated the overheads?
  • 13.A / On all costs
  • 13.B / Only on eligible direct costs
  • 13.C / On all eligible direct costs except
    subcontracting
  • 13.D / None of the above

16
Question 14
  • The costs related to building rental and
    maintenance are considered as
  • 14.A / Subcontracting
  • 14.B / Direct costs (management)
  • 14.C / Overheads/Indirect costs
  • 14.D / None of the above

17
Question 15
  • Under which condition(s) are subcontracting costs
    considered as eligible costs?
  • 15.A / The subcontracted task cannot be performed
    by the contractor and is necessary to the
    project.
  • 15.B / The subcontracted task cannot be performed
    by the contractor, and is not a core element of
    the project.
  • 15.C / The subcontracted task cannot be performed
    by the contractor, and is necessary to the
    project, and is not a core element of the project.

18
Question 16
  • Is it allowed to subcontract the management of a
    project?
  • 16.A / No
  • 16.B / Yes, but only if the coordinator is
    deficient.
  • 16.C / Yes, but only if the EC has approved it.
  • 16.D / None of the above

19
Question 17
  • How does the EC pay the grant?
  • 17.A / Each partner receives periodic advances
    from the EC
  • 17.B / Each partner is paid by the EC at the
    beginning of the project
  • 17.C / The coordinator receives periodic advances
    from EC and redistributes them to each partner
  • 17.D / None of the above

20
Question 18
  • What is the management report?
  • 18.A / The financial report
  • 18.B / The coordinators report
  • 18.C / The managers report
  • 18.D / None of the above

21
Question 19
Which currency must be used in the financial
reports? 19.A / Contractors local
currency 19.B / Euro 19.C / Belgian
currency 19.D / None of the above
22
Question 20
What is the EC funding rate for an audit
certificate? 20.A / 50 funding 20.B / 75
funding 20.C / 100 funding 20.D / None of the
above  
23
Question 21
If an SME project partner uses the transitional
60 flat-rate for its indirect costs. If it grows
ceases to be an SME on Jan. 1st, what
happens? 21.A / it should keep on using the 60
rate until the end of the project. 21.B / it
must change and use the 20 flat-rate for its
indirect costs. 21.C / it must revise indirect
costs statements made since the projects start
21.D / none of the above.
24
  • Thank you for your participation!
  • Koos de Korte
  • SenterNovem
  • The Hague, Netherlands
  • Phone 31 70 373 5250
  • Email k.dekorte_at_egl.nl