Title: Vertical SRF Cavity Test Stand (ILCTA_IB1_VTS)
1Vertical SRF Cavity Test Stand(ILCTA_IB1_VTS)
- C.M. Ginsburg and C. Sylvester
- TD Department Heads Meeting
- March 13, 2006
2Project People
Project Coordination C.M. Ginsburg, C. Sylvester
Civil Construction R. Alber (FESS), C.M. Ginsburg, C. Sylvester
Cryostat and Top Plate Y. Huang, T. Peterson, R. Rabehl, C. Reid, C. Sylvester, M. Wong
Cryo System Modifications Y. Huang, T. Peterson, R. Rabehl, C. Reid, C. Sylvester, M. Wong
Cryo Controls Y. Huang, T. Peterson, R. Rabehl, C. Sylvester, (TD/IC)
Cryo Commissioning Y. Huang, T. Peterson, C. Sylvester, (TD/IC)
Radiation Shielding C. Brown, C.M. Ginsburg, M. Herr, G. Lauten (AD), I. Rakhno (AD)
Safety (PSS) Interlocks C. Worel (AD/ESH/Interlocks group)
RF/LLRF R. Carcagno, C.M. Ginsburg, J. Ozelis, P. Seifrid (AD)
Test Stand Commissioning A. Lounine, C.M. Ginsburg, J. Ozelis, O. Prokofiev
New C. Brown, Y. Huang, G. Lauten, R. Rabehl, I.
Rakhno, P. Seifrid, C. Worel
Arrived J. Ozelis
Not yet A. Lounine
3Project Scope
- Bare 1.3 GHz 9-cell Tesla-style cavities
- Cryo capacity 60 W at 2 K
- Measure Q vs. T and Q vs. Eacc
- 250 W RF power required at maximum gradient
(Q5x109, Eacc35 MV/m) - Maintain Controlled Area status in IB1
- lt 5 mrem/hr immediately outside the shielding
- lt0.25 mrem/hr in normal working areas
4GDE Document
- Contents
- technical information and schedule
- plans for FY 06
- Status
- Draft complete
- Reviewed by group members
- Forwarded to Shekhar today
5Radiation Physics Analysis
DESY data (Moeller and Gall, private
communication)
- Data measured over 12 years, 85 cavities
- X-ray flux measured
- 5 cm off axis
- above 1 SS top plate
- above 50 kg shielding inside cryostat
- 20 cm Pb 5 cm Al
- Maximum x-ray flux 58 R/hr
- Plots and statistical analysis of DESY data by CMG
6DESY-TTF Vertical Facility
Moeller
1m
0.1m
7DESY TTF measured maximum x-ray flux
Maximum x-ray flux 58 R/hr, typically much less
8DESY TTF measured maximum x-ray flux
- The measured x-ray flux above dewar top plate
- lt6 R/hr 90 of the time
- lt30 R/hr 99 of the time
- always lt58 R/hr
9DESY TTF measured maximum x-ray flux
4 different cavities
Requiring Qgt5E9 very effective, but still need
x-ray flux limit
10Eacc at DESY/TTF
- DESY TTF data
- ltEaccgt increasing with time
- Significant spread all years
11Radiation Shielding Design
Rakhno
- For 90 of all tested RF cavities the measured
dose rate 5 Rad/hr. Use 90 level as baseline.
- Thickness of the vertical concrete wall in the
recessed region 2 ft. An option lead bricks. - Shielding layers of Pb and polyethylene
immediately above the RF cavity - 3H production in surface water UPPER LIMIT 2000
pC/ml-yr will check against current design
probably a non-issue
12Rakhno
ILCTA_IB1_VTS Preliminary Design
Igor will re-do with latest geometry
13Civil Construction Status
- Need Radiation Safety Go-Ahead
- Analysis by CMG (DESY data)
- Shielding Design by Igor Rakhno (AD)
- Safety Review by Mike Herr and Gary
Lautenschlager (AD) - Civil construction bottom of the shaft, recessed
area - Chuck Brown (AD) will assist at next meeting
March 23 - (behind) Schedule
- Go out for Bids (Mar. 6th)
- Award Bid (Mar. 31st)
- Begin Work (April 3rd)
- Contractor on-site 3 weeks
- Work Completed (June 20th)
14Cryostat (based on DESY/TTF)
- Added a phase separator to provide better quality
liquid helium - Estimated RF cycle time based on Pd255 W and
cryogenic capacity in IB1 (Huang) - 40 RF duty factor
- One Engr. (Rabehl) added to team to focus on
cryogenic controls - Made progress on the Process and Instrumentation
Diagram
15Status/Schedule (ILCTA_IB1)
16Next Plans
- Get Rad Safety go-ahead for Civil Construction
and go for bids ASAP - Begin RF instrumentation design with ILC HLRF
people in about 3 weeks, meanwhile - Determine location of instrumentation racks
- Create RF instrumentation wish-list
- Finger person to design input coupler (Lounine)
17Backup Location
- West side of IB1, North of the Vertical Magnet
Test Facility (VMTF) - This location allows for the future construction
of a concrete block structure for accommodating a
horizontal test cryostat - Is in close proximity to the existing VMTF
Cryogenic piping may simplify the tie-in to the
cryogenic services
Vert. SRF Cryostat
Cryo Piping
18Backup Location (contd.)
- The long-term plan for IB1 is to have both a
vertical and a horizontal test facility
Radiation Shielding
VMTF
Vertical SRF
IB1 Control Rm.
19Backup
ILCTA_IB1_VTS Preliminary Design
1.52m
Reid
min cavity depth
2.8m
max cavity depth