Title: MPSC Procedures An update
1MPSC ProceduresAn update
- Alick Macpherson
- Rutgers University/ETH Zurich
2MPSC Procedures Observations
- Purpose
- Procedures are required for systems that can by
their malfunctioning cause significant damage to
LHC equipment - Procedures are required for 3 types of system
- Central system This is the BIS.
- Standard System A system that interfaces only
to the BIS - Complex System
- A system supplies inputs to systems in addition
to the BIS. - A system that reacts to signal from the BIS (ie
BEAM_INFO, SAFE_Machine parameters) - Examples
- Central BIS
- Standard PIC, WIC, FMCM
- Complex Vacuum, BLM, LBDS
- Systems not (yet) included in the MPSC procedures
- Electron stoppers (RF), Access, Movable objects
3MPSC Procedures Status
System 1st Draft Edit Status EDMS Ready MTF Ready
Access ? - - No
BIS Yes Updated Yes No
BLM Not yet - - No
Collimators Not yet - - No
FMCM Yes Minor edits No No
Injection System No - - No
LBDS Yes Edits needed No No
PIC Yes Minor edits No No
Vacuum system Yes Edits needed No No
WIC Yes Minor edits No No
4Timetable for Completion of Procedures
- All out-standing procedures submitted to Jan by
1st October. - Procedures returned to groups after review/cross
check by Jan/Alick - Expect 1 week per procedure for review and
feedback and 2 weeks for corrections. - Target Review 1 procedure per week.
- Review process started with BIS procedure
- From 1st October, start EDMS checking procedures
- Tareget 1 per week.
- Start with BIS procedure
- As EDMS approval finishes, transfer to MTF.
- Allow 1 week for transfer to MTF
- Look to have all procedures in MTF by mid
December - Collimator procedure linked to presentation at
MPSCWG on 3rd Oct
5Procedures More Observations
- Most procedures have had a first revision
- Still awaiting some procedures
- Question is data/state logging considered part
of MPS commissioning? - MPSC Commissioning should (where possible) be
modular - Use hardware commissioning to set entry
conditions for front end systems. - HWC Procedures results (MTF) to be confirmed by
MPSC procedure - Test the interface with the BIS gt complementary
to BIS Commissioning - Set exit conditions that allow the system to
proceed to validations during cold machine cold
checkout or validation with beam. - MPSC validation must insure that there is no
possibility of machine protection risks due to
operator controls - gt procedures to confirm that operators cant
change critical settings? - Dependency on info from BIS and other systems
must be made clear
6Procedures Flag concerns
- BEAM_INFO Flag
- BEAM_INFO is a mirror of the BEAM_PERMIT that is
returned to the systems inputting to the BIC - Questions
- Does the system initiate protective actions based
on feedback from the BIS - Does the system use the BEAM_INFO flag for
critical actions - If BEAM_INFO FALSE is used, what are the
timescales of the actions? - Can systems ensure that the initiation of any
protective action is gt 3 orbits - Assumption need a max of 3 orbits to trigger and
dump beams - Safe Machine Parameters Understand if/how they
are used - Questions
- Is toggling of USER_PERMIT conditional on the
state of the SAFE BEAM flag - If this happens, is the logic integrated into the
CIBU/BIC or the user system - Does any subsystem use SAFE_INJECTION flag as
part of MPSC - Does any subsystem use Movable_devices_allowed
flag as part of MPSC
7Observations Vacuum System
- Vacuum system good example of movable objects
- Interlock Chain includes sector valves, electron
stoppers, Access Safety Block - Need to confirm commissioning of redundant
interlocking mechanisms - ie vacuum access, vacuum RF?
- Need to commission joint system configuration
- RF commissioning mode ie sector valves open,
electron stoppers closed - Need to confirm protection from equipment failure
of movable devices - Access Safety Block
- Vacuum system provides signals directly to
others RF, MKI, MKB, Access - Concerns are dump requests compatible with MPSC
- Initiation of RF dump requests on loss of good
vacuum on P1 cavity. - RF Dump request mechanism depends on intensity
threshold single/multiple cavity loss. - MKI Vacuum signals used to assert injection
inhibit. Can initiate valve closure. - MKB Kicker interlock based on vacuum system can
generate a dump request - Access system Ensure that the control logic and
configuration for the electron stoppers and
Access Safety Block are such that there is
redundancy in the interlocking - Uses BEAM_INFO FALSE as a necessary condition
for closing sector valves - In failure mode, what are the sufficient
conditions (eg leak detection)
8Observations PICs and WICs
- Entry Conditions
- Front end commissioned in HWC
- Need to re-confirm procedures and MTF results
from HWC - Focus on PICBIS and WICBIS validation
- PIC and WIC treats both beams simultaneously
- Dump request applies to both beams simultaneously
- PIC specific features
- PIC does not use USER_PERMIT_A and USER_PERMIT_B
- Uses unmaskable and maskable USER_PERMIT instead
- Timescale Concern
- Is system reaction to fault detection
(BEAM_INFOFALSE) too fast for completion of beam
dump. Essential Circuit fault detection few
?s - SAFE BEAM Flag and Auxiliary circuits
- Need to confirm location of interlock truth table
for Auxiliary circuit faults SAFE_BEAM - WIC specific features
- Timescale concern
- Is system reaction to fault detection
(BEAM_INFOFALSE) too fast for completion of beam
dump. Fault detection for Fast Boolean Processor
of WIC 1 ?s
9Observations BIS
- Procedure almost ready for checking via EDMS.
- Validation of subsystem interface with BIS
requires - Valid USER_PERMITs (or reasonable USER PERMIT
simulator?) - Clear statement of subsystem functionality wrt
BIS - BIS logic
- Clarification that all logic for setting
BEAM_PERMIT to FALSE is within the BIS system - Confirm there is no safe machine parameter
dependence attached to the USER_PERMIT. - USER_PERMIT as received by the BIS Clarify
difference between A AND B FALSE and A OR B
FALSE when setting the BEAM_PERMIT (during
commissioning) - Timing issues
- Validation of worst case time from user system
toggling the USER PERMIT to completion of a beam
dump gt confirm fastest reaction timescale
10Observations FMCM
- Entry conditions established by HWC
- Commissioning in situ and with pilot beam
- Beam time at 450 GeV and 7TeV beam is needed to
set trigger thresholds and trigger time-window - FMCM inputs only into the BIS
- Inputs are maskable
- Special commissioning mode
- FMCM test mode can set USER_PERMIT FALSE on
request - Need to confirm this mode cannot be invoked
during running - Data logging essential
- used to set trigger threshold for USER_PERMIT
- Included in MPSC procedure
11Observations LBDS
- For MPSC, LBDS is a complex system
- Beam dump related Inputs
- BEAM PERMIT loop trigger from BIS
- Direct TCDQ BLM trigger (independent of BIS)
- Direct Access system trigger (independent of BIS)
- Interlock related Outputs
- LBDS USER_PERMIT
- Can LBDS set its USER_PERMIT to FALSE with beam
in the machine? - Injection Inhibits sent to injection kickers and
re-phased RF revolution frequency sent to abort
gap watchdog - Commissioning needs to be cleanly divided into
- Individual User system tests, Hardware
Commissioning, and MPSC tests. - MPSC entry conditions must confirm previous test
sets - Use MPSC tests to validate chain of control prior
to the LBDS Reliability Run - detailed 1st draft but needs more focus on MPSC
for a non-ideal situation. - Address issues and modes of (partial) failure of
component user systems - Implications of lost abort gap synchronisation
from the RF - Partial loss of communication with injection
system
12Summary
- Procedures
- 1st drafts of available procedures have been
reviewed. - Will circulate back to subsystems for corrections
and cross checks. - Need to get all out-standing 1st drafts
- Submit revised procedures for EDMS approval then
to MTF - Start process now and finish by mid December.
- Global picture
- Assess interdependencies between systems in
relation to MPSC - Clarify if any automated actions are based on
feedback from the BIS - If so, ensure timescales are compatible with
integrated system response - Require procedures confirm no operations
influence on critical settings - Address MPSC risks for partial failure modes,
especially in complex systems like the LBDS - Understand/review implications to protection
given different states of the safe machine
parameters ( SAFE_BEAM, SAFE_INJECTION etc) - Ensure that any safe machine parameter dependent
interlock logic is in BIS
13Spare Stuff
14(No Transcript)
15Access Safety Block
- Covered by both Access and Vacuum system
interlocks - Time scale for closure is slow ( 3sec) gt much
slower than beam dump.