MPSC Procedures An update - PowerPoint PPT Presentation

About This Presentation
Title:

MPSC Procedures An update

Description:

... Macpherson. Rutgers University/ETH Zurich. A. Macpherson: MPSCWG ... A. Macpherson: MPSCWG - Procedures. 4. 12/22/09. Timetable for Completion of Procedures ... – PowerPoint PPT presentation

Number of Views:551
Avg rating:3.0/5.0
Slides: 16
Provided by: MacP151
Category:

less

Transcript and Presenter's Notes

Title: MPSC Procedures An update


1
MPSC ProceduresAn update
  • Alick Macpherson
  • Rutgers University/ETH Zurich

2
MPSC Procedures Observations
  • Purpose
  • Procedures are required for systems that can by
    their malfunctioning cause significant damage to
    LHC equipment
  • Procedures are required for 3 types of system
  • Central system This is the BIS.
  • Standard System A system that interfaces only
    to the BIS
  • Complex System
  • A system supplies inputs to systems in addition
    to the BIS.
  • A system that reacts to signal from the BIS (ie
    BEAM_INFO, SAFE_Machine parameters)
  • Examples
  • Central BIS
  • Standard PIC, WIC, FMCM
  • Complex Vacuum, BLM, LBDS
  • Systems not (yet) included in the MPSC procedures
  • Electron stoppers (RF), Access, Movable objects

3
MPSC Procedures Status
System 1st Draft Edit Status EDMS Ready MTF Ready
Access ? - - No
BIS Yes Updated Yes No
BLM Not yet - - No
Collimators Not yet - - No
FMCM Yes Minor edits No No
Injection System No - - No
LBDS Yes Edits needed No No
PIC Yes Minor edits No No
Vacuum system Yes Edits needed No No
WIC Yes Minor edits No No
4
Timetable for Completion of Procedures
  • All out-standing procedures submitted to Jan by
    1st October.
  • Procedures returned to groups after review/cross
    check by Jan/Alick
  • Expect 1 week per procedure for review and
    feedback and 2 weeks for corrections.
  • Target Review 1 procedure per week.
  • Review process started with BIS procedure
  • From 1st October, start EDMS checking procedures
  • Tareget 1 per week.
  • Start with BIS procedure
  • As EDMS approval finishes, transfer to MTF.
  • Allow 1 week for transfer to MTF
  • Look to have all procedures in MTF by mid
    December
  • Collimator procedure linked to presentation at
    MPSCWG on 3rd Oct

5
Procedures More Observations
  • Most procedures have had a first revision
  • Still awaiting some procedures
  • Question is data/state logging considered part
    of MPS commissioning?
  • MPSC Commissioning should (where possible) be
    modular
  • Use hardware commissioning to set entry
    conditions for front end systems.
  • HWC Procedures results (MTF) to be confirmed by
    MPSC procedure
  • Test the interface with the BIS gt complementary
    to BIS Commissioning
  • Set exit conditions that allow the system to
    proceed to validations during cold machine cold
    checkout or validation with beam.
  • MPSC validation must insure that there is no
    possibility of machine protection risks due to
    operator controls
  • gt procedures to confirm that operators cant
    change critical settings?
  • Dependency on info from BIS and other systems
    must be made clear

6
Procedures Flag concerns
  • BEAM_INFO Flag
  • BEAM_INFO is a mirror of the BEAM_PERMIT that is
    returned to the systems inputting to the BIC
  • Questions
  • Does the system initiate protective actions based
    on feedback from the BIS
  • Does the system use the BEAM_INFO flag for
    critical actions
  • If BEAM_INFO FALSE is used, what are the
    timescales of the actions?
  • Can systems ensure that the initiation of any
    protective action is gt 3 orbits
  • Assumption need a max of 3 orbits to trigger and
    dump beams
  • Safe Machine Parameters Understand if/how they
    are used
  • Questions
  • Is toggling of USER_PERMIT conditional on the
    state of the SAFE BEAM flag
  • If this happens, is the logic integrated into the
    CIBU/BIC or the user system
  • Does any subsystem use SAFE_INJECTION flag as
    part of MPSC
  • Does any subsystem use Movable_devices_allowed
    flag as part of MPSC

7
Observations Vacuum System
  • Vacuum system good example of movable objects
  • Interlock Chain includes sector valves, electron
    stoppers, Access Safety Block
  • Need to confirm commissioning of redundant
    interlocking mechanisms
  • ie vacuum access, vacuum RF?
  • Need to commission joint system configuration
  • RF commissioning mode ie sector valves open,
    electron stoppers closed
  • Need to confirm protection from equipment failure
    of movable devices
  • Access Safety Block
  • Vacuum system provides signals directly to
    others RF, MKI, MKB, Access
  • Concerns are dump requests compatible with MPSC
  • Initiation of RF dump requests on loss of good
    vacuum on P1 cavity.
  • RF Dump request mechanism depends on intensity
    threshold single/multiple cavity loss.
  • MKI Vacuum signals used to assert injection
    inhibit. Can initiate valve closure.
  • MKB Kicker interlock based on vacuum system can
    generate a dump request
  • Access system Ensure that the control logic and
    configuration for the electron stoppers and
    Access Safety Block are such that there is
    redundancy in the interlocking
  • Uses BEAM_INFO FALSE as a necessary condition
    for closing sector valves
  • In failure mode, what are the sufficient
    conditions (eg leak detection)

8
Observations PICs and WICs
  • Entry Conditions
  • Front end commissioned in HWC
  • Need to re-confirm procedures and MTF results
    from HWC
  • Focus on PICBIS and WICBIS validation
  • PIC and WIC treats both beams simultaneously
  • Dump request applies to both beams simultaneously
  • PIC specific features
  • PIC does not use USER_PERMIT_A and USER_PERMIT_B
  • Uses unmaskable and maskable USER_PERMIT instead
  • Timescale Concern
  • Is system reaction to fault detection
    (BEAM_INFOFALSE) too fast for completion of beam
    dump. Essential Circuit fault detection few
    ?s
  • SAFE BEAM Flag and Auxiliary circuits
  • Need to confirm location of interlock truth table
    for Auxiliary circuit faults SAFE_BEAM
  • WIC specific features
  • Timescale concern
  • Is system reaction to fault detection
    (BEAM_INFOFALSE) too fast for completion of beam
    dump. Fault detection for Fast Boolean Processor
    of WIC 1 ?s

9
Observations BIS
  • Procedure almost ready for checking via EDMS.
  • Validation of subsystem interface with BIS
    requires
  • Valid USER_PERMITs (or reasonable USER PERMIT
    simulator?)
  • Clear statement of subsystem functionality wrt
    BIS
  • BIS logic
  • Clarification that all logic for setting
    BEAM_PERMIT to FALSE is within the BIS system
  • Confirm there is no safe machine parameter
    dependence attached to the USER_PERMIT.
  • USER_PERMIT as received by the BIS Clarify
    difference between A AND B FALSE and A OR B
    FALSE when setting the BEAM_PERMIT (during
    commissioning)
  • Timing issues
  • Validation of worst case time from user system
    toggling the USER PERMIT to completion of a beam
    dump gt confirm fastest reaction timescale

10
Observations FMCM
  • Entry conditions established by HWC
  • Commissioning in situ and with pilot beam
  • Beam time at 450 GeV and 7TeV beam is needed to
    set trigger thresholds and trigger time-window
  • FMCM inputs only into the BIS
  • Inputs are maskable
  • Special commissioning mode
  • FMCM test mode can set USER_PERMIT FALSE on
    request
  • Need to confirm this mode cannot be invoked
    during running
  • Data logging essential
  • used to set trigger threshold for USER_PERMIT
  • Included in MPSC procedure

11
Observations LBDS
  • For MPSC, LBDS is a complex system
  • Beam dump related Inputs
  • BEAM PERMIT loop trigger from BIS
  • Direct TCDQ BLM trigger (independent of BIS)
  • Direct Access system trigger (independent of BIS)
  • Interlock related Outputs
  • LBDS USER_PERMIT
  • Can LBDS set its USER_PERMIT to FALSE with beam
    in the machine?
  • Injection Inhibits sent to injection kickers and
    re-phased RF revolution frequency sent to abort
    gap watchdog
  • Commissioning needs to be cleanly divided into
  • Individual User system tests, Hardware
    Commissioning, and MPSC tests.
  • MPSC entry conditions must confirm previous test
    sets
  • Use MPSC tests to validate chain of control prior
    to the LBDS Reliability Run
  • detailed 1st draft but needs more focus on MPSC
    for a non-ideal situation.
  • Address issues and modes of (partial) failure of
    component user systems
  • Implications of lost abort gap synchronisation
    from the RF
  • Partial loss of communication with injection
    system

12
Summary
  • Procedures
  • 1st drafts of available procedures have been
    reviewed.
  • Will circulate back to subsystems for corrections
    and cross checks.
  • Need to get all out-standing 1st drafts
  • Submit revised procedures for EDMS approval then
    to MTF
  • Start process now and finish by mid December.
  • Global picture
  • Assess interdependencies between systems in
    relation to MPSC
  • Clarify if any automated actions are based on
    feedback from the BIS
  • If so, ensure timescales are compatible with
    integrated system response
  • Require procedures confirm no operations
    influence on critical settings
  • Address MPSC risks for partial failure modes,
    especially in complex systems like the LBDS
  • Understand/review implications to protection
    given different states of the safe machine
    parameters ( SAFE_BEAM, SAFE_INJECTION etc)
  • Ensure that any safe machine parameter dependent
    interlock logic is in BIS

13
Spare Stuff
14
(No Transcript)
15
Access Safety Block
  • Covered by both Access and Vacuum system
    interlocks
  • Time scale for closure is slow ( 3sec) gt much
    slower than beam dump.
Write a Comment
User Comments (0)
About PowerShow.com