Title: PROBLEM 13-34


1
PROBLEM 13-34
  • Sager Products has been in the business of
    manufacturing and marketing toys for toddlers for
    the past two decades. Jim Sager, president of
    the firm, is considering the development of a new
    manufacturing line to allow it to produce
    high-quality plastic toys at reasonable prices.
    The development process is long and complex. Jim
    estimates that there are five phases involved and
    multiple activities for each phase.

2
  • Determine the expected completion time for the
    entire process. Also determine those activities
    along the critical path. Jim hopes that the
    total project will take less than 40 weeks. Is
    this likely to occur?

3
(No Transcript)
4
  • The expected completion time for the entire
    process is 38.33 weeks.
  • The activities along the critical path are C, F,
    H, L, N, R, S, V W.