Title: 16:00 Meeting
11600 Meeting
- Schedule
- External scintillator trigger w/ lead shielding
is new baseline data taking configuration
TKR_TACK30 and CAL_TACK90 - TKR efficiency measured with ext. trigger data by
requiring muon in EM CAL - Get the lead out on Tuesday
- Van Der Graaff setup starting Wednesday, Oct. 7
at 8am and ending Thursday Oct. 8 at 3pm - Get the lead back in at 3pm Thursday, Oct 9
- TEM/TEM-PS test on Friday, October 10
Mon. Sept.29 Tues. Sept.30 Wed. Oct. 1 Thurs. Oct. 2 Fri. Oct.3 Sat. Oct.4 Sun. Oct.5
8a-4p Berrie 8a-4p Berrie 8a-4p Larry 8a-4p Larry 8a-4p Jim 8a-4p Xin 8a-4p Mizuno
4p-8p Ric 4p-8p Gary 4p-8p Elliott 4p-8p Elliott 4p-8p Eduardo 4p-8p Mizuno 4p-8p Tune
8p-12a Hiro 8p-12a Hiro 8p-12a Marcus 8p-12a 8p-12a Mizuno 8p-12a Selim 8p-12a
12a-8a Hiro 12a-8a Hiro 12a-8a Hiro
CAL LO data CAL LO data CAL LO data High energy data High energy data High energy data High energy data
Mon. Oct. 6 Tues. Oct. 7 Wed. Oct. 8 Thurs. Oct. 9 Fri. Oct.10 Sat. Oct.11 Sun. Oct.12
8a-4p Brian 8a-4p Larry 8a-4p Larry 8a-4p Gary 8a-4p Brian 8a-4p Marcus 8a-4p Gary
4p-8p Tune 4p-8p Tune 4p-8p Ric 4p-8p Ric 4p-8p Eduardo 4p-8p 4p-8p Eduardo
8p-12a 8p-12a 8p-12a 8p-12a Mizuno 8p-12a 8p-12a 8p-12a
12a-8a Hiro 12a-8a Hiro 12a-8a Hiro 12a-8a Hiro 12a-8a Hiro 12a-8a Hiro
High energy data High energy data VDG data VDG data / HE data TEM-PS test High energy data High energy data
Mon. Oct. 13 Tues. Oct. 14 Wed. Oct. 15 Thurs. Oct. 16 Fri. Oct.17 Sat. Oct.18 Sun. Oct.19
8a-4p 8a-4p 8a-4p
4p-8p 4p-8p
8p-12a
LCB test? EM CAL de-integrated EM CAL shipped to NRL EM CAL arrives at NRL