6'12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

6'12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Description:

The cropping season starts in 15th march dominantly they produce sorghum. ... Estimating the frequency, amount and duration of the flood water in un gauged rivers. ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 28
Provided by: john989
Category:

less

Transcript and Presenter's Notes

Title: 6'12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT


1
6.12aDESIGN APPROACH ON BILILO SPATE IRRIGATION
PROJECT
Presented by Eyob Yehayis
2
(No Transcript)
3
1. Project Area Description
  • Bililo spate is located at 42.75 N and 9.233E
  • The average altitude is 1450 m.
  • The annual mean rain fall is 757.15 mm.
  • The annual effective RF579.4mm
  • T max31.6 and T min15.6 oc
  • The Annual mean ETo1902.77mm

4
1. Project Area Description Continued
  • The cropping season starts in 15th march
    dominantly they produce sorghum.
  • The crop water required during the cropping
    season 579.14 mm.
  • The total effective rainfall during the cropping
    season is 338 mm.
  • Irrigation required CWR-ERF 259.69 mm

5
1. Project Area Description Continued
  • The watershed Area is 157 km2 of which above 70
    of it is covered by forest and scattered bushes,
    the rest is farmland.
  • About 25 of the cathment has a slopegt28
  • The Project is almost it is a newly designed
    spate irrigation scheme.

6
2 The basic assumptions used for the project.
  • The system should be easy for farmers to operate
    and not require the large inputs of labor or
    other resources to maintain.
  • The system should prevent large and uncontrolled
    flood flows from damaging canals and field
    systems.
  • The system should Continue to function with high
    rates of sedimentation on the fields and canal
    beds.

7
3 Structural Component of The System
  • 4.1 Weir (Diversion Head work)
  • 4.2 Canal and Canal Structures

8
3.1 Weir (Diversion Head work)
  • The head work is modified to discharge the excess
    flood that is expected to come in 50 year return
    period.
  • Accordingly , the maximum flood for 50 years
    Return period is 110 3/s.
  • Designed to provides the required head to command
    the Farmland.
  • The intake canal sill level is 0.3 m above under
    sluice level.

9
3.2 Canal and Canal Structures
  • 3.2.1 Flood Canal (Main canal)
  • The design canal capacity is determined by the
    following assumptions
  • The recession flood stays for 5 days
  • The farm land is provided with 25 cm flood water
    on one irrigation.
  • Farm land have chance of getting 2 flood water
    irrigation during the growing season.
  • The resulting design capacity is 3 m3/s for 500ha.

10
4.2. Flood Canal conted
  • The canal cross section and bed slope is designed
    on the maximum permissible velocity which satisfy
    60 design flow to avoid the silt deposition on
    canal bed at lower flow.
  • Some of the canal cross section which passes
    porous and cliff formation is lined with masonry.
  • The secondary canal capacity is designed by
    proportioning the hectare it develops and
    multiplying by flood duration day ( 5 days).

11
4.2.1 Flood Canal conted
  • Generally The System has
  • -Earthen canal
  • on main canal 5 km
  • on secondary canal 10.5km, 11 in number
  • -Lined canal
  • on main canal 2.3 km

12
4.2.2 Canal Structures
  • The system is provided with different farm
    structures which satisfies the hydraulic
    performance and structural stability depending on
    the land topography.
  • Accordingly, on the main canal there are
  • 4 vertical drops
  • 32 inclined drops 7 of which on secondary canal
  • 1 flume
  • 5 division box
  • 4 chute 2 of which on SC1
  • 3 Road crossing culverts

13
5 Water Management
  • It is assumed that only 1/5 of the command area
    is irrigated in one day starting from upstream
    toward the down stream. This could be changed
    based on the community interest.

14
6 Problem encountered
  • Estimating the frequency, amount and duration of
    the flood water in un gauged rivers.
  • Estimating the sediment yield with the respective
    runoff.

15
Head Work
16
Downstream face of Weir
17
Downstream of Headwork
18
Flood water entering the canal
19
Rejection spillway
20
Lined canal
21
Canal running along the cliff
22
Flume upstream
23
Division box with drop
24
(No Transcript)
25
Secondary canal under construction
26
Recession flow
27
Canal Silting
Write a Comment
User Comments (0)
About PowerShow.com