Natural Gas Procurement Process
  • Ohio Hospital Association
  • In Conjunction With
  • MC2 Consultants

2
Where It All Begins
  • The process begins with a committee of
    participants that sets the agenda and oversees
    the process
  • Without the committee oversight, the end product
    will fall short of expectations

3
Doing a Committed Bid
  • Having participants commit to the process makes
    the bid much stronger
  • Precommitment is a demonstration to suppliers
    that substantial quantities are involved
  • Fishing expeditions dont generate the same
    results

4
Contract Review
  • Starting with the old contract, a quick contract
    review of current terms and potential options
    will bring everyone up to speed
  • Decisions will be discussed and made to determine
    the terms of the new contract

5
Vendor List
  • Starting with the list provided, the committee
    will be asked for input regarding the list or
    other to be added to the list.
  • The supplier list will then be finalized and
    distributed to participants.

6
Finalize RFP Document
  • Taking all of the input given by the oversight
    committee the RFP document is finalized and
    distributed for final approval
  • Once finalized, distribute to approved vendors.

7
Evaluation
  • After 3 to 4 weeks, fielding questions and making
    clarifications, receive proposals.
  • Summarize results of bid
  • Present summaries to oversight committee for
    selection of new supplier

8
Finalize Contract
  • Get all signatures and approvals necessary to
    finalize contract
  • OHA and MC2 will work with new supplier to get
    new contracts out to members and signed up

9
Finalize Contract
  • Get all signatures and approvals necessary to
    finalize contract
  • OHA and MC2 will work with new supplier to get
    new contracts out to members and signed up

10
Calendar of Events
  • Mar. 24 - Kickoff meeting
  • Mar. 31 - Finalize RFP document.
  • Apr. 7 - Distribute to approved suppliers
  • May 7 - Receive proposals Summarize
  • May 14 - Supplier Presentations/selection
  • May 17 - 28 Finalize contract
  • June 1-30 Sign up with new vendor