Transcript and Presenter's Notes

Title: Proton Driver Test Cryostat: Cost Estimation


1
Proton Driver Test Cryostat Cost Estimation
Approval Process
  • Michael White
  • Technical Division E F
  • Fermi National Accelerator Laboratory

2
(No Transcript)
3
(No Transcript)
4
(No Transcript)
5
(No Transcript)
6
Cost Estimates
Category Total Cost
   
Vacuum Vessel 50,000.00
Magnetic Shielding 25,500.00
80 K Shield 9,000.00
He Reservoir 10,000.00
Valves 25,000.00
Heat Exchanger 7,000.00
Instrumentation 6,500.00
Piping 2,000.00
Bayonets 5,000.00
Relief System 4,000.00
   
Total 144,000.00
7
Design Review
  • Before fabrication begins, design should be
    reviewed for
  • Pressure and Vacuum Vessel Codes
  • Relief System
  • Model, Drawings, Specifications, and Flow
    Schematic

8
Design Review People
  • Argonne ( Joel Fuerst or Ken Shepard)
  • AD/Cryo (Jay Thielacker or Arkadiy Klebaner)
  • TD/EF (Tom Nichol or Tom Page)
  • Outsider (Tom Peterson?)

9
Safety Review Committee
  • Before installation, must be reviewed by safety
    committee in charge of Meson Detector Building
  • Bob Sanders is the chairman
  • Also on the committee are Michael Geynisman, Joel
    Misek, and David Pushka

10
Engineering Notes
  • 5031- Pressure Vessel Engineering Note
  • Can be partially completed
  • Will require vendors U stamp before it can be
    completed
  • Only necessary for helium reservoir

11
Engineering Notes
  • 5032- Cryogenic System Review
  • Requires FEMA (Failure Mode and Effect Analysis)
  • Also requires What-If analysis (human error,
    weather, etc.)
  • I need to better understand cryostats connections
    (plumbing and electrical)
  • Meeting with Arkadiy tommorrow

12
Engineering Notes
  • 5033- Vacuum Vessel Engineering Note
  • Can be filled out as soon as I determine proper
    method of sizing relief