Uninterruptible Power Source UPS Status October 2004 - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Uninterruptible Power Source UPS Status October 2004

Description:

Finalize Bracket design August 1, 2004. UPS CDR at CSIST mid-October, 2004. EU Battery Box fabrication complete mid-February, 2005. Cell/BMS delivery mid ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 19
Provided by: Lockheed7
Category:

less

Transcript and Presenter's Notes

Title: Uninterruptible Power Source UPS Status October 2004


1
Uninterruptible Power Source (UPS)
StatusOctober 2004
  • P. Nemeth/LM

2
CSP Functional Block Diagram
3
Responsibilities
  • Cells, Bricks, and BMS
  • Yardney/Lithion R. Gitzendanner
  • Battery Casing, Electrical/Mechanical Integration
  • CSIST Dr. Ching-Kai Ho
  • Battery Charger
  • CRISA A. Posada
  • Customer/Subcontract Management
  • MIT F. Eppling and S. Ting
  • Technical Management M. Capell/MIT and G.
    Viertel/ETH
  • Subcontract Technical Monitor P. Nemeth/LM

4
Cell Dimensions
5
Brick Layout
Mass estimate for brick 9kg Total weight budget
for UPS 212.5kg Additional weight savings from
Cutout on side panel Decrease flange width
6
Battery Requirements
  • Battery will provide control power to CSP in
    event of loss of ISS power or communication
  • Watch-dog timer/control circuit
  • Normal Ramp down function
  • Quench monitoring
  • Initiation of quench, 45A pulse
  • Minimum battery voltage 20.3V during pulse
  • Derived from minimum voltage at quench heaters of
    12V
  • Must operate in thermal environment similar to
    USS-02 Upper Trunnion Bridge

7
Battery Specifications
  • Consists of eight cells, Yardney NCP25-3
  • Nominal Voltage 8 X 3.6 V 28.8 V
  • Capacity 28 Ah
  • Operational Temperature Range -30 degC to 50
    degC
  • Capable of supplying 45A pulse at required
    voltage throughout mission profile

8
Electronics Envelope
9
UPS Interior Geometry
BMS
Batteries
10
Revised UPS Mounting
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
Latest UPS Mechanical Design (by CSIST)
16
Cell/BMS Milestone Schedule
  • March 1, 2004 Yardney completes cell
    manufacturing
  • June 14, 2004 Yardney completes internal
    Acceptance test
  • June 21, 2004 - UPS SOW Rev A released
  • Revision required to update testing requirements
    from NASA Safety
  • Allows Yardney to proceed with cell acceptance
    and qualification testing
  • July 15, 2004- Yardney baselines Electronics
    (BMS) physical layout /CSIST to proceed with
    Battery case design
  • August October 2004 Qual and Acceptance Test
    procedures development
  • October 27 - Approve procedures/begin tests
  • January 16 BMS build and test complete
  • March 28, 2005 - BMS and Bricks ship to CSIST

17
UPS Milestone Schedule
  • PDR for Battery Casing _at_ CSIST December 2003
  • Pre-CDR issue closeout telecon October 26 at LM
  • CDR for Battery Casing _at_ CSIST December 2004
  • EDU required for support of Cryomagnet Avionics
    Box (CAB) functional testing
  • Testing scheduled March thru June 2005
  • EU Battery Box fabrication complete mid-March,
    2005
  • Cell/BMS delivery late March, 2005
  • UPS integration and test March - April, 2005
  • EU to CRISA in May to support CAB testing (March
    through June 2005) prior to turnover

18
UPS Target Schedule
  • Baseline BMS footprint July 16, 2004
  • Finalize Bracket design August 1, 2004
  • UPS CDR at CSIST mid-October, 2004
  • EU Battery Box fabrication complete mid-February,
    2005
  • Cell/BMS delivery mid-February, 2005
  • UPS integration and test February early April,
    2005
  • EU to CRISA mid-April to support CAB testing
    (March through June 2005) prior to turnover