Cost and Software Data Reporting Training - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Cost and Software Data Reporting Training

Description:

C3.4.5 'The DoD PM, in coordination with the CWIPT, shall: ... Tailor the downloaded RDT example to add the correct number of columns ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 13
Provided by: briano86
Category:

less

Transcript and Presenter's Notes

Title: Cost and Software Data Reporting Training


1
Cost and Software Data ReportingTraining
  • Resource Distribution Table (RDT) Module

2
RDT Topics
  • What is an RDT?
  • Types and components of RDTs
  • How to complete an RDT

3
DoD 5000.04-M-1
  • C3. Stakeholder Responsibilities.

C3.4.5 The DoD PM, in coordination with the
CWIPT, shall Prepare the program resource
distribution table (RDT), project applicability
matrix (PAM), if applicable, and technical
characteristics for inclusion in the remarks
section of the program CSDR plan.
4
What is an RDT?
  • A Resource Distribution Table identifies which
    contractors work on each WBS element and the
    dollar value associated with their overall effort
  • This identifies which contractors must
    participate in the CSDR process, i.e., prepare
    CCDRs and SRDRs
  • CSDR Dollar Threshold Review
  • For all efforts associated with an ACAT IC or ID
    program
  • any contract/subcontract whose estimated value is
    greater than 50M or between 7M and 50M and has
    content of high-risk or high-technical-interest,
    CCDRs are required
  • any contract/subcontract whose estimated software
    development value is greater than 25M, SRDRs are
    required

5
Types of RDTs
  • Program RDT
  • Total dollar value reconciles with government
    budget for given acquisition phase (i.e., SDD,
    LRIP or FRP)
  • Utilizes Program Plan WBS
  • Includes contracts for Government-furnished
    equipment (GFE) and effort accomplished by
    government facilities
  • Contract RDT
  • Total dollar value reconciles with contract value
  • Utilizes Prime Contract WBS

Both RDTs must be updated as the WBS and the
program evolves
6
RDT Example Program RDT(Partial Example)
RDT WBS consistent with Program WBS
Note that two organizations outside of the prime
contract will be submitting CCDRs
7
Types of Contractors
  • Prime Contractor, i.e., a company whose
    contractual customer is the Government
  • Subcontractor, i.e., company whose contractual
    customer is another contractor
  • Two types of subcontractors
  • Direct-Reporting Subcontractor
  • Delivers cost reports directly to the DCARC
  • Summary subcontract values are in Prime
    Contractors cost reports
  • Non-Reporting Subcontractor
  • Not required to submit cost reports to DCARC
  • Below dollar-threshold items that are included in
    the Prime Contractors cost reports

8
RDT Example Contract RDT(Partial Example)
Interdivisional transfers are also subject to
CSDR requirements
2nd tier subcontractors may also be required to
report directly to the government
9
Creating an RDT
  • Download the RDT example (http//dcarc.pae.osd.mil
    /)
  • Insert the Program WBS or the Contract WBS
  • Tailor the downloaded RDT example to add the
    correct number of columns
  • Complete the header section
  • Add Xs to signify the work for each
    organization/contractor

10
Questions / Discussion / Review
  • We just covered
  • What is an RDT?
  • Types and components of RDTs
  • How to complete an RDT
  • Questions?

11
  • Module 4 Resource Distribution Table
  • Questions

12
RDT Questions
  • Which activity is responsible for preparing the
    Program RDT?
  • Government Program Manager
  • DCARC Director
  • OSD CAIG Chair
  • Contractor
  • Which WBS should be used when initially
    developing the Program RDT?
  • MIL-HDBK-881A, Appendix A Aircraft Systems
  • MIL-HDBK-881A, Appendix B Electronic/Automated
    Software Systems
  • Program WBS
  • Contract WBS
  • The Program RDT includes
  • Prime Contractors
  • GFE Contractors
  • Subcontractors
  • All of the above
  • Which of the following is not a component of an
    RDT?
Write a Comment
User Comments (0)
About PowerShow.com