A Project Is Not a Black Box - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

A Project Is Not a Black Box

Description:

Scenario Analysis - Project analysis given a particular ... PV Inflows. PV Outflows. The McGraw-Hill Companies, Inc., 2000. Irwin/McGraw Hill. 10- 10 ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 19
Provided by: matt350
Category:
Tags: black | box | courses | project

less

Transcript and Presenter's Notes

Title: A Project Is Not a Black Box


1
  • A Project Is Not a Black Box

Chapter 10
2
Topics Covered
  • Sensitivity Analysis
  • Break Even Analysis
  • Monte Carlo Simulation
  • Decision Trees

3
How To Handle Uncertainty
  • Sensitivity Analysis - Analysis of the effects of
    changes in sales, costs, etc. on a project.
  • Scenario Analysis - Project analysis given a
    particular combination of assumptions.
  • Simulation Analysis - Estimation of the
    probabilities of different possible outcomes.
  • Break Even Analysis - Analysis of the level of
    sales (or other variable) at which the company
    breaks even.

4
Sensitivity Analysis
  • Example
  • Given the expected cash flow forecasts for
    Otoban Companys Motor Scooter project, listed on
    the next slide, determine the NPV of the project
    given changes in the cash flow components using a
    10 cost of capital. Assume that all variables
    remain constant, except the one you are changing.

5
Sensitivity Analysis
  • Example - continued

NPV 3.43 billion Yen
6
Sensitivity Analysis
  • Example - continued
  • Possible Outcomes

7
Sensitivity Analysis
  • Example - continued
  • NPV Calculations for Pessimistic Market Size
    Scenario

NPV 5.7 bil yen
8
Sensitivity Analysis
  • Example - continued
  • NPV Possibilities (Billions Yen)

9
Break Even Analysis
  • Point at which the NPV0 is the break even point.
  • Otoban Motors has a breakeven point of 8,000
    units sold.

PV Inflows
400 200 19.6
Break even NPV9
PV (Yen) Billions
PV Outflows
Sales, 000s
85 200
10
Monte Carlo Simulation
Modeling Process
  • Step 1 Modeling the Project
  • Step 2 Specifying Probabilities
  • Step 3 Simulate the Cash Flows

11
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
150(.6) 30(.4)
Turboprop
-550 NPV ?
-150
100(.6) 50(.4)
or
0
Piston
-250 NPV ?
12
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
812 456 660 364 148
150(.6) 30(.4)
Turboprop
-550 NPV ?
-150
100(.6) 50(.4)
or
0
Piston
-250 NPV ?
13
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
812 456 660 364 148
150(.6) 30(.4)
Turboprop
-550 NPV ?
-150
100(.6) 50(.4)
or
0
Piston
-250 NPV ?
14
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
812 456 660 364 148
150(.6) 30(.4)
Turboprop
-550 NPV ?
450
-150
or
100(.6) 50(.4)
0
Piston
331
-250 NPV ?
15
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
NPV888.18
812 456 660 364 148
150(.6) 30(.4)
Turboprop
-550 NPV ?
NPV444.55
450
-150
NPV550.00
or
100(.6) 50(.4)
0
Piston
331
-250 NPV ?
NPV184.55
16
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
NPV888.18
812 456 660 364 148
150(.6) 710.73 30(.4)
Turboprop
-550 NPV ?
NPV444.55
450
-150
NPV550.00
100(.6) 403.82 50(.4)
or
0
Piston
331
-250 NPV ?
NPV184.55
17
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
NPV888.18
812 456 660 364 148
150(.6) 710.73 30(.4)
Turboprop
-550 NPV96.12
NPV444.55
450
-150
NPV550.00
100(.6) 403.82 50(.4)
or
0
Piston
331
-250 NPV117.00
NPV184.55
18
Decision Trees
960 (.8) 220(.2) 930(.4) 140(.6) 800(.8) 100(.2) 4
10(.8) 180(.2) 220(.4) 100(.6)
NPV888.18
812 456 660 364 148
150(.6) 710.73 30(.4)
Turboprop
-550 NPV96.12
NPV444.55
450
-150
NPV550.00
100(.6) 403.82 50(.4)
or
0
Piston
331
-250 NPV117.00
NPV184.55
Write a Comment
User Comments (0)
About PowerShow.com