Title: Cryomagnetic Avionics Box
1Cryomagnetic Avionics Box
Short Overview and Status
Gert Viertel (ETH-Zurich) January 2004
2(No Transcript)
3CAB Responsibilities
CAN Bus Connection
4Cryomagnet Avionics Box (CAB)
5(No Transcript)
6AMS-02 STS Power Distribution Block Diagram
7Functionality
- CAB is the main interface between the AMS control
and power distribution system on one side and the
AMS cryomagnet on the other side. Its main
functions are - Charging and discharging the magnet
- Protection of the AMS cryomagnet under any
unwanted conditions, including a magnet
quench - Supervision of the cryogenics system
- Providing an interface to the AMS slow control
system - Providing 5.5 kV interface protection between
the cryomagnet and ISS
- The functionality is split between three
subsystems - Cryomagnet Current Source (CCS)
- Cryomagnet Self Protection (CSP)
- Cryomagnet Controller and Signal Conditioner
(CCSC)
8Cryomagnet Current Source (CCS)
- Magnet ramping mode (AMS-02 powered down to its
minimum) - Convert the ISS high voltage (107 V 127 V) to
a low voltage between - 1.0 V and 3.3 V at up to 455 A for
cryomagnet charging - With increasing current the output voltage drops
in order to keep the - power consumption below 1875 W.
- Experiment mode (CCS is powered down)
- CCS semi-conductor switch is OPEN in order to
- prevent current circulation through the CCS
which would cause an excessive power consumption
of the CAB - prevent a magnet discharge from taking several
hours
9Cryomagnet Current Source CCS and Magnet Load
10Cryomagnet Self Protection (CSP)
- The CSP is maintained operational also in case of
an external power loss by means of an UPS in
order to provide the following functionality - Quench detection and quench heaters activation
- Auto ramp-down in case of communication and/or
external power loss - Permitting OCP (Operations Command Posts)
control of all CAB - functions
- Identifies the coil section initiating a quench
- Permit an autonomous operation of all important
CAB functions - quench heaters
- current lead dis-connectors
- current lead valves
- vapour cooled shield vent valves
- cool down circuit vent valves
- current lead TMP (Thermo-Mechanical Pump) heater
- cool-down TMP heater and persistent switch
heater
11CSP Functional Block Diagram
12Cryomagnet Dump Diodes (CDD)
- In the event that the magnet must be powered
down, the persistent switch will be opened to
allow the current in the magnet to be dumped to a
bank of 18 rectifiers (six sets in series of
three rectifiers in parallel) - These rectifiers will be protected by a cover to
prevent incidental contact - The rectifiers will be mounted on the two
wake-side sill trunnion joints (large thermal
mass) - Worst case thermal analysis reveals that with a
continuous load rectifiers will maintain junction
temps well below ratings even if one of a
parallel series of three fail. - Dump time is estimated at 80 minutes
13Cryomagnet Dump Diodes
14Cryomagnet Dump Diode Mounting Locations
15Cryomagnet Controller and Signal Conditioner
(CCSC)
- CAB interface to the AMS-wide redundant CAN-BUS
providing - Control of the CCS
- Telemetry of the magnet cryogenics including
temperatures and pressures - and of the CAB Status.
- Control of the power switches
- Control and monitoring for the Direct Liquid
Content Measurement - Control of charging of the Uninterruptible Power
Source (UPS) and - relaying of telemetry from the UPS
16Uninterruptible Power Source (UPS)
- The UPS will consist of a redundant set of
Lithium-Ion batteries - Battery will provide control power during loss of
ISS power or communication to payload for mission
success - Watch-dog timer/control circuit
- Normal Ramp down function
- Quench monitoring
- Initiation of quench, 45A pulse
- Battery is designed to meet NSTS 1700.7B, "Safety
Policy and Requirements For Payloads Using the
Space Transportation System", NSTS 1700.7B ISS
Addendum, "Safety Policy and Requirements For
Payloads Using the International Space Station",
and JSC 20793, "Manned Space Vehicle Battery
Safety Handbook and will be sized for a minimum
of 8 hours of operation, plus ramp-down time
17Battery Cell Characteristics
- Manufactured by Yardney/Lithion
- Prismatic cell
- Dimensions 95mm (3.74) X 27.84mm (1.096) X
139.7mm (5.500) - Weight 900g (1.982 lbs)
- Operational Temperature Range -30 degC to 50
degC
18Interfaces
- Input power interface
- main power input to the Cryomagnet Current
Source (CCS) 107 lt-gt 127 VDC - 28 VDC supply (PDS) for relays and heaters and
conversion within the CAB to other - internally required voltages
- Control interface
- AMS redundant CAN-Bus for interface and control
- Cryomagnetic sensors
- Temperature sensors, current lead voltage taps,
control valve positions, thermo mechanical - pump currents and voltages, power consumption,
vacuum case vacuum sensors, - helium pressure sensors
- Cryomagnet control
- Cryogenic and warm valves, quench heaters,
persistent switches, helium tank heaters, - current lead dis-connectors, thermo-mechanical
pump heaters
19(No Transcript)
20(No Transcript)
21Weight, Dimensions, Power, Temperature Limits
Total weight 43640 g 10 contingency ? 48000 g
- Power consumption
- CCS is not charging the magnet lt 45 W
- CCS is charging the magnet lt 2000 W
- Temperature limits
- Storage -40 oC to 70 oC
- Operating -40 oC to 60 oC
22Up-dated Electrical Specifications from B.
Anderson (SCL)
23AMS-02 CAB Progress Report 15 July 2003
- Electrical
- Software
- Mechanical
- Thermal
- Programmatic
- Managerial
24ELECTRICAL
- Cryomagnet Current Source Subsystem (CCS)
- DC/DC Power Converters (CCS_CS module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout in progress
- Control TM/TC (CCS_CTRL TMTC module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout in progress
25Electrical
ELECTRICAL
- Cryo Controller Signal Conditioner Subsystem
(CCSC) - Standard Telemetry (CCSC_STM module)
- Standard Telemetry Function
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- CPU Function
- Electrical Design Pending to include the last
modifications - Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- DC/DC Converter
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout not yet started waiting for the
"Valves Status Monitoring" definition. It affects
to STM function
26ELECTRICAL
- Power Switches Subsystem (PS module)
- PS TM/TC Power Drivers Function
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PS DC/DC Converter Function
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout not yet started waiting for the "Warm
Valves" choice and the "Valves Status" monitoring
definition.
27ELECTRICAL
- 28V_ISO module
- Detailed Electrical Design in progress
- Worst Case Analysisin progress
- Parts Stress Analysis in progress (on the
critical EEE parts gt100mW) - Failure analysis DONE
28ELECTRICAL
- Cryomagnet Self Protection Subsystem (CSP)
- CSP Power Drivers (CSP_PWR_DRV module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout PCB layout not yet started waiting
for the "Warm Valves" choice. - CSP TM/TC /CSP_TMTC module)
- Electrical Design Very poor advance. Still
waiting for the "Valves Status" monitoring
definition and for the closure of the definition
of Autonomous quench recovery sequence regarding
to the small flight vent valves DV08A to DV08D
and DV15A to DV15D - Failure analysis in progress, at block level
29ELECTRICAL
- Cryomagnet Self Protection Subsystem (CSP)
- Current Lead Detectors (CSP_CL_DET module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout not yet started. Analysis of the
layout to keep the 2KV Isolation in progress - Magnet Detectors (CSP_MAG_DET module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout not yet started. Analysis of the
layout to keep the 2KV Isolation in progress
30ELECTRICAL
- Cryomagnet Self Protection Subsystem (CSP)
- Detectors DC/DC Converter (CSP_DET_CV module)
- Electrical Design DONE
- Worst Case AnalysisDONE
- Parts Stress Analysis DONE (on the critical EEE
parts gt100mW) - Failure analysis DONE
- PCB layout not yet started. Analysis of the
layout to keep the 2KV Isolation in progress
31SOFTWARE
- The SW development has started and the following
documents have been produced - CAB HW/SW ICD. Delivered for comments
- Software Requirements Document (SRD), in internal
signatures cycling. To be issued before end of
July 2003. - Software Interface Control Document (SICD), in
internal signatures cycling . To be issued before
end of July 2003. - Next
- Architectural and Design Document
- Coding phase
32MECHANICAL
33MECHANICAL
34MECHANICAL
35MECHANICAL
36MECHANICAL
37MECHANICAL
38MECHANICAL
- FIRST NATURAL FREQUENCY ON Y AXIS IN THE PLOT AT
126 HZ
39THERMAL
- This information was provided during the TIM at
CERN on April 2003 - CAB Power Budget
- Conditions
- Both nominal and redundant 28V busses turned on,
in hot redundancy - No external heater or valve activated and the CCS
current source turned off - Only CAB internal consumption has been considered
- (All the CAB nominal and redundant modules are
being supplied) - Typical power consumption of the CAB unit in
standby mode 67 Watts - Maximum power consumption of the CAB unit in WCA
80 Watts - (CAB unit in operating mode including temperature
effects) - In Cold Redundancy (only nominal 28V Primary bus
ON) - Maximum power consumption of the CAB unit in WCA
50 Watts - (CAB unit in operating mode including temperature
effects) - Additionally 280W max full load (final period of
ramp-up process) of the CCS current Source and
42W max of the current shunt
40THERMAL
- AMS CAB THERMAL DESIGN
- Box fixed onto a AMS USS Beams (Dec.2002)
- thermally connected
- conductively to USS
- AMS CAB POWER INPUT
- CCS TRANSIENT RAMP UP
- CONTROL STEADY STATE
- AMS SURROUNDINGOUTER SPACE (NOMINAL COLD
HOT) - AMS CAB BOUNDARIES (CGS e-mail February 26th
2003) - HEAT LOADS FROM AMS AND OUTER SPACE (NOMINAL
COLD HOT) - RADIATION INHIBIT BY BETHA COLTH
- CONDUCTION TO UPPER TRUNNION MAIN PATH
- CONDUCTION TO LOWER TRUNNION NEGLECTED (SPRING)
- CASES STUDIED
- CONDUCTANCE FROM CAB TO UPPER TRUNION 1W/ºC
- TWO SCREWS SIMULATING POOR COUPLING
- CONDUCTANCE FROM CAB TO UPPER TRUNION 3W/ºC
- SIX SCREWS SIMULATING GOOD COUPLING
41THERMAL
- RESULTS COMPARISON
- Three environmental conditions studied with two
conductive couplings. - NOMINAL
- REACHED STEADY STATE CONDITION WITH 6 SCREWS
- HOT
- NOT REACHED STEADY STATE CONDITIONS WITH 6 SCREWS
- COLD
- REACHED STEADY STATE CONDITIONS WITH 6 SCREWS
- NONE OF CASES WITH 2 SCREWS CAN WITHSTAND
PERMANENT OPERATION. - CONCLUSIONS
- It is necessary a good coupling (equal or better
than 8 screws) with the AMS upper trunnion in
order to provide enough heat sinking capabilities
to drain the total heat loads in steady state
condition (around 100w).
42THERMAL
- Results of Thermal Analysis RadiativeConductive
Exchange
43THERMAL
44Status Summary January 2004
- Up-dated specifications for CAB from SCL
- Mounting Design for the CAB on USS
- CRISA CGS Iterations of the thermal model in
progress - Data on some components still missing to finalise
the CAB design - New Version of the Final Technical Proposal
submitted by CRISA - Deliverables EM FM (Both fully functional)