Managing Risks for Winnipeg - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Managing Risks for Winnipeg

Description:

Accepted the recommendation to undertake water treatment within a ten year time frame ... Many large new projects will be going to market over the scheduled ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 35
Provided by: apeg
Category:

less

Transcript and Presenter's Notes

Title: Managing Risks for Winnipeg


1
Managing Risks forWinnipegsWater Treatment
Program
Presented by Tom R. Pearson, P. Eng, Project
Director
2
Agenda
  • Background
  • Project Profile
  • Project Status
  • Winnipegs Policy on Risk Management
  • Key Issues
  • Initial Risk Assessment
  • Process
  • Outcome
  • Ongoing Risk Management
  • Management of risks Examples
  • Benefits of risk management
  • Questions

3
Background Councils Decision to Treat
  • In 1993 Council
  • - Accepted the recommendation to undertake water
    treatment within a ten year time frame
  • - And established a Water Treatment Reserve
  • Between 1995 and 1999 a comprehensive program of
    monitoring, pilot testing and engineering studies
    was undertaken
  • In 2000, Council adopted a recommendation that
    Winnipeg proceed with a water treatment program
  • This decision was supported by public
    consultation, public health officials and the
    opinion of an expert panel (low risk high
    consequence)

4
Background - Specific Objectives
  • Reduce the risk of a waterborne disease outbreak
    caused by chlorine-resistant microorganisms
  • Reduce chlorine disinfection by-products
  • Meet the Canadian Drinking Water Quality
    Guidelines

5
Background - Plant Location
6
Background - History
7
Profile - Our New Treatment Plant
  • Located at the Deacon Reservoir Site.
  • Design Life projected to be 2040
  • Maximum Finished Water Production 400 ML/d
  • Average Finished Water Production 254 ML/d
  • Minimum Finished Water Production 100 ML/d
  • Total cost now projected at 300 Million

8
PROFILE - AERIAL VIEW FROM SOUTH WEST
9
Profile - The Water Treatment Process
10
Project Status
  • Detailed Design is underway, concurrent with
    construction
  • Design will wrap up this year
  • About 55.3 Million spent
  • Overall, we have committed about 192.2 Million
    to date
  • The 300 Million budget projection appears to be
    secure

11
Risk Management in Winnipeg
  • In June, 1999 the City Auditor recommended to
    Council pursuant to a review of the Main Norwood
    Bridge, that We must ensure a corporately
    focused and risk-based approach to managing major
    capital projects.
  • Policies and governance concerning risk are the
    responsibility of the Chief Financial Officer
  • Administered under the auspices of the Corporate
    Controller
  • All large projects (10 Million or more) must
    report each quarter to the Committee on Fiscal
    Issues, outlining project status, emerging risks
    and steps to mitigate
  • Reports are reviewed by a Major Capital Committee
    before submittal to the Committee on Fiscal
    Issues
  • Risk management is identified as a deliverable in
    project Terms of Reference

12
Key Issues
  • Environmental Issues
  • Organizational Issues
  • Market Conditions
  • Schedule
  • Finances

13
Environmental Effects Assessment
  • An Environmental Effects Assessment study of the
    effects the water treatment plant identified no
    adverse effects.
  • The study was voluntary not required by
    regulators.
  • The results were shared with stakeholders and
    Manitoba Conservation.
  • Two Public Open Houses were held in Springfield
  • All substantive issues were addressed.
  • The Environmental Effects Assessment study
    reduced project risk, and improved the quality of
    the project.

14
Organizational Issues
  • This is a large complex project with four major
    consulting firms working from geographically
    diverse locations
  • Coordination/communication through ERoom
  • Construction Management and Fast Tracking lead
    to risks and cultural issues for City and
    Consultants
  • Hiring and training of certified operators in
    time for commissioning and start-up (2008 by
    Council mandate) will be challenging

15
Market Conditions
  • Many large new projects will be going to market
    over the scheduled construction period
  • A period of high inflation within the
    construction industry is forecast (time money)
  • A shortage of qualified contractors and personnel
    is anticipated
  • We must make this an attractive project for
    contractors

16
Aggressive Schedule
  • April 2005 Finish preliminary design and
    environmental effects study
  • Spring 2005 Started building the
    water treatment plant
  • Fall 2008 Start testing the plant
  • End of 2008 Begin operating the plant

17
Finances
  • The original water treatment program budget was
    214 million to build the WTP and 12.75
    million/yr to operate
  • Council has approved an additional 13.3 million
    for risk mitigation initiatives and 2.8 million
    for shops/staff consolidation (Total budget now
    at 230.1 Million)
  • The current rate model will provide about 117
    Million in cash financing
  • Projected cost is now 300 Million and additional
    borrowing will be required
  • Once the plant is up and operating, revenues from
    water sales are sufficient to cover operating and
    debt servicing without extraordinary increases to
    water rates

18
Initial Risk Assessment
  • Undertaken after preliminary design, before
    starting detailed design
  • 2-day workshop format
  • Pre-workshop preparation
  • survey of participants concerns
  • orientation concerning risk assessment
    methodology and terms
  • Facilitated by S.M.A. Consulting Ltd.

19
Workshop Participants
  • 23 in total, in addition to SMA staff
  • City 9
  • Earth Tech 5
  • UMA 5
  • EPCOR 3
  • TetrEs 1
  • Participants were divided into 5 groups that
    considered specific types of risks

20
Group Assignments
  • 1 Identify potential problems with the design.
  • 2 Risk analysis focused on design of treatment
    processes, and mechanical equipment etc.
  • 3 Risks analysis focused on operations including
    commissioning, resources, operations, responses
    to disastrous situations, contingency planning
    etc.
  • 4 Risks associated with project coordination,
    project management, schedule, staging,
    estimating, cash flow, and external factors.
  • 5 Risks associated with constructability,
    underground work, construction logistics,
    staging, tie-ins, and contracting strategies etc.

21
Quantifying Risk Factors 4 Steps
  • Determination of the likelihood of the factor
    being encountered (e.g. probability, or a
    subjective descriptor)
  • Determination of the magnitude of the impact if
    the factor is encountered (e.g. dollar value or a
    subjective descriptor)
  • Determination of the overall severity of the
    factor by multiplying the likelihood (1) by
    magnitude (2).
  • The factors are then grouped based on the overall
    severity score and risk responses are developed

22
Step 1 - Determination of Likelihood
23
Step 2 Determination of Magnitude
24
Step 3 - Determination of Severity
25
Step 4 Develop a Risk Response
  • Possible actions include
  • Reduce uncertainty by obtaining more information.
    (This may lead to a re-evaluation of the
    likelihood and sometimes the magnitude.)
  • Eliminate or avoid the risk factor by partial or
    complete modifications to proposed ideas, a
    different strategy, etc.
  • Transfer the risk element to other parties.
  • Insure against the occurrence of the factor if
    possible.
  • Abort the project if the risk is intolerable and
    no other means can be undertaken to mitigate its
    damages.
  • A planned response must be developed for all
    risks.

26
Outcome
  • 120 risk items were identified by workshop
    participants
  • These were synthesized into 44 project issues and
    33 design issues by the Risk Consultant.
  • Some of the risks were Serious to Critical

27
Ongoing Risk Management
  • The risk management plan defines specific tasks
    to be undertaken to mitigate the risk
  • Responsibility and timelines for the tasks are
    assigned
  • Follow up on the risk factors is undertaken on a
    regular basis until the project is complete.
  • Risks are monitored on an ongoing basis by the
    project risk team and reviewed at monthly
    meetings

28
Risk -Public Involvement
  • The public open house (or action by a resident or
    RM) could result in additional requirements to
    mitigate perceived risks or nuisance or the need
    to file an Environmental Impact Statement. Then
    the project will be impacted.
  • Assessment L 10 M 50 S 500
  • Recommended Action
  • 1- Open House
  • 2- Environmental effects assessment
  • 3- Continued communication

29
Risk Impact of Floodway Operation
  • Floodway operation may impact early stages of
    Construction particularly bulk excavation. Impact
    is increased potential of base heave from till
    layer increased pore pressure affecting slope
    stability.
  • Assessment L 20 M 15 S 300
  • Recommended Action
  • 1- Stop excavation at 50 depth
  • 2- Install pump wells
  • 3- Pile first / excavate after - cost

30
Risk Long Duration Power Outage
  • If a power outage occurs then the DBPS pumps will
    stop and water supply to the city will be harmed
  • Assessment L 10 M 50 S 500
  • Recommended Action
  • Could add backup power for partial UV and
    chlorination (chlorine - 2M at deacon, backup
    power 3). Come up with boil water strategy and
    potential for delay with regulators.

31
Outcome Chlorine
  • Risk analysis The probability of an accident
    resulting in a catastrophic release of chlorine
    gas from a rail tank car is very unlikely, but
    the consequences are disastrous and may include
    injury or death to City personnel and the general
    public.
  • Recommended that this risk be eliminated or
    reduced. Additional capital funding of 7.3
    million required for on-site sodium hypochlorite
    generation, and operating costs will increase by
    74,000 per year.

32
Outcome Power
  • Risk analysis The probability of a long duration
    power failure which would cause depletion of
    potable water storage and result in the need to
    supply untreated water is very unlikely, but the
    consequences are severe and include the need to
    boil water to ensure health safety during the
    power outage.
  • Recommended that the risk be eliminated.
    Additional capital funding of 6.0 million
    required for increased standby generation
    capacity, and operating costs will increase by
    90,000 per year.

33
The Benefits of Risk Management
  • Quality
  • Credibility
  • Cost
  • Value

34
Questions?
Write a Comment
User Comments (0)
About PowerShow.com