Title: Managing Risks for Winnipeg
1Managing Risks forWinnipegsWater Treatment
Program
Presented by Tom R. Pearson, P. Eng, Project
Director
2Agenda
- Background
- Project Profile
- Project Status
- Winnipegs Policy on Risk Management
- Key Issues
- Initial Risk Assessment
- Process
- Outcome
- Ongoing Risk Management
- Management of risks Examples
- Benefits of risk management
- Questions
3Background Councils Decision to Treat
- In 1993 Council
- - Accepted the recommendation to undertake water
treatment within a ten year time frame - - And established a Water Treatment Reserve
- Between 1995 and 1999 a comprehensive program of
monitoring, pilot testing and engineering studies
was undertaken - In 2000, Council adopted a recommendation that
Winnipeg proceed with a water treatment program - This decision was supported by public
consultation, public health officials and the
opinion of an expert panel (low risk high
consequence)
4Background - Specific Objectives
- Reduce the risk of a waterborne disease outbreak
caused by chlorine-resistant microorganisms - Reduce chlorine disinfection by-products
- Meet the Canadian Drinking Water Quality
Guidelines
5Background - Plant Location
6Background - History
7Profile - Our New Treatment Plant
- Located at the Deacon Reservoir Site.
- Design Life projected to be 2040
- Maximum Finished Water Production 400 ML/d
- Average Finished Water Production 254 ML/d
- Minimum Finished Water Production 100 ML/d
- Total cost now projected at 300 Million
8PROFILE - AERIAL VIEW FROM SOUTH WEST
9Profile - The Water Treatment Process
10Project Status
- Detailed Design is underway, concurrent with
construction - Design will wrap up this year
- About 55.3 Million spent
- Overall, we have committed about 192.2 Million
to date - The 300 Million budget projection appears to be
secure
11Risk Management in Winnipeg
- In June, 1999 the City Auditor recommended to
Council pursuant to a review of the Main Norwood
Bridge, that We must ensure a corporately
focused and risk-based approach to managing major
capital projects. - Policies and governance concerning risk are the
responsibility of the Chief Financial Officer - Administered under the auspices of the Corporate
Controller - All large projects (10 Million or more) must
report each quarter to the Committee on Fiscal
Issues, outlining project status, emerging risks
and steps to mitigate - Reports are reviewed by a Major Capital Committee
before submittal to the Committee on Fiscal
Issues - Risk management is identified as a deliverable in
project Terms of Reference
12Key Issues
- Environmental Issues
- Organizational Issues
- Market Conditions
- Schedule
- Finances
13Environmental Effects Assessment
- An Environmental Effects Assessment study of the
effects the water treatment plant identified no
adverse effects. - The study was voluntary not required by
regulators. - The results were shared with stakeholders and
Manitoba Conservation. - Two Public Open Houses were held in Springfield
- All substantive issues were addressed.
- The Environmental Effects Assessment study
reduced project risk, and improved the quality of
the project.
14Organizational Issues
- This is a large complex project with four major
consulting firms working from geographically
diverse locations - Coordination/communication through ERoom
- Construction Management and Fast Tracking lead
to risks and cultural issues for City and
Consultants - Hiring and training of certified operators in
time for commissioning and start-up (2008 by
Council mandate) will be challenging
15Market Conditions
- Many large new projects will be going to market
over the scheduled construction period - A period of high inflation within the
construction industry is forecast (time money) - A shortage of qualified contractors and personnel
is anticipated - We must make this an attractive project for
contractors
16Aggressive Schedule
- April 2005 Finish preliminary design and
environmental effects study - Spring 2005 Started building the
water treatment plant - Fall 2008 Start testing the plant
- End of 2008 Begin operating the plant
17Finances
- The original water treatment program budget was
214 million to build the WTP and 12.75
million/yr to operate - Council has approved an additional 13.3 million
for risk mitigation initiatives and 2.8 million
for shops/staff consolidation (Total budget now
at 230.1 Million) - The current rate model will provide about 117
Million in cash financing - Projected cost is now 300 Million and additional
borrowing will be required - Once the plant is up and operating, revenues from
water sales are sufficient to cover operating and
debt servicing without extraordinary increases to
water rates
18Initial Risk Assessment
- Undertaken after preliminary design, before
starting detailed design - 2-day workshop format
- Pre-workshop preparation
- survey of participants concerns
- orientation concerning risk assessment
methodology and terms - Facilitated by S.M.A. Consulting Ltd.
19Workshop Participants
- 23 in total, in addition to SMA staff
- City 9
- Earth Tech 5
- UMA 5
- EPCOR 3
- TetrEs 1
- Participants were divided into 5 groups that
considered specific types of risks
20Group Assignments
- 1 Identify potential problems with the design.
- 2 Risk analysis focused on design of treatment
processes, and mechanical equipment etc. - 3 Risks analysis focused on operations including
commissioning, resources, operations, responses
to disastrous situations, contingency planning
etc. - 4 Risks associated with project coordination,
project management, schedule, staging,
estimating, cash flow, and external factors. - 5 Risks associated with constructability,
underground work, construction logistics,
staging, tie-ins, and contracting strategies etc.
21Quantifying Risk Factors 4 Steps
- Determination of the likelihood of the factor
being encountered (e.g. probability, or a
subjective descriptor) - Determination of the magnitude of the impact if
the factor is encountered (e.g. dollar value or a
subjective descriptor) - Determination of the overall severity of the
factor by multiplying the likelihood (1) by
magnitude (2). - The factors are then grouped based on the overall
severity score and risk responses are developed
22Step 1 - Determination of Likelihood
23Step 2 Determination of Magnitude
24Step 3 - Determination of Severity
25Step 4 Develop a Risk Response
- Possible actions include
- Reduce uncertainty by obtaining more information.
(This may lead to a re-evaluation of the
likelihood and sometimes the magnitude.) - Eliminate or avoid the risk factor by partial or
complete modifications to proposed ideas, a
different strategy, etc. - Transfer the risk element to other parties.
- Insure against the occurrence of the factor if
possible. - Abort the project if the risk is intolerable and
no other means can be undertaken to mitigate its
damages. - A planned response must be developed for all
risks.
26Outcome
- 120 risk items were identified by workshop
participants - These were synthesized into 44 project issues and
33 design issues by the Risk Consultant. - Some of the risks were Serious to Critical
27Ongoing Risk Management
- The risk management plan defines specific tasks
to be undertaken to mitigate the risk - Responsibility and timelines for the tasks are
assigned - Follow up on the risk factors is undertaken on a
regular basis until the project is complete. - Risks are monitored on an ongoing basis by the
project risk team and reviewed at monthly
meetings
28Risk -Public Involvement
- The public open house (or action by a resident or
RM) could result in additional requirements to
mitigate perceived risks or nuisance or the need
to file an Environmental Impact Statement. Then
the project will be impacted. - Assessment L 10 M 50 S 500
- Recommended Action
- 1- Open House
- 2- Environmental effects assessment
- 3- Continued communication
29Risk Impact of Floodway Operation
- Floodway operation may impact early stages of
Construction particularly bulk excavation. Impact
is increased potential of base heave from till
layer increased pore pressure affecting slope
stability. - Assessment L 20 M 15 S 300
- Recommended Action
- 1- Stop excavation at 50 depth
- 2- Install pump wells
- 3- Pile first / excavate after - cost
30Risk Long Duration Power Outage
- If a power outage occurs then the DBPS pumps will
stop and water supply to the city will be harmed - Assessment L 10 M 50 S 500
- Recommended Action
- Could add backup power for partial UV and
chlorination (chlorine - 2M at deacon, backup
power 3). Come up with boil water strategy and
potential for delay with regulators.
31Outcome Chlorine
- Risk analysis The probability of an accident
resulting in a catastrophic release of chlorine
gas from a rail tank car is very unlikely, but
the consequences are disastrous and may include
injury or death to City personnel and the general
public. - Recommended that this risk be eliminated or
reduced. Additional capital funding of 7.3
million required for on-site sodium hypochlorite
generation, and operating costs will increase by
74,000 per year.
32Outcome Power
- Risk analysis The probability of a long duration
power failure which would cause depletion of
potable water storage and result in the need to
supply untreated water is very unlikely, but the
consequences are severe and include the need to
boil water to ensure health safety during the
power outage. - Recommended that the risk be eliminated.
Additional capital funding of 6.0 million
required for increased standby generation
capacity, and operating costs will increase by
90,000 per year.
33The Benefits of Risk Management
- Quality
- Credibility
- Cost
- Value
34Questions?