Title: CPOE Scope Management:
1CPOE Scope Management MEDITECH CIO Forum Chris
Parisi Sr. Project ManagerNewton-Wellesley
Hospital 06/15/06
2Background MBA from Bentley 20 years in info
tech 10 years in health care info tech IDX, SDK
(Now Eclipsys) NMC Homecare, Harte-Hanks, Lycos,
iMarket/DNB Graduate Instructor, University of
Phoenix Online, I.T. Project Management
3And now - Newton-Wellesley Hospital
4Newton-Wellesley Hospital
- Partners Affiliate
- Teaching Facility with Resident Rotations
- Mid-Sized Community Hospital - 250 Beds
- 1 Pediatric Unit 1 Special Care Nursery
- 1 Telemetry, 1 Med Oncology 1 Med/Surg
- Pediatrics Maternal Child Health
- 1 Surgical Unit PACU
- Psych (two divisions)
5CPOE Scope Management
Did your project ask for this
and you ended up building this???
6CPOE Scope Management
Welcome to CPOE Project Scope Management!
7Scope Management Definition
What is Project Scope Management? The complete
understanding and management of exactly what is
and what is not to be delivered within the
project
And involves Initiation, Planning, Definition,
and Verification of the features and
functionality required for completion of the
project.
8Scope Management Definition
- Scope Management is centered around
- Controlling Changes to the defined requirements
of the project - - and managing Scope Creep
9Project Management
- Projects are steered by the business needs of an
organization - and influenced by the Triple Constraint
- Scope
- Time
- Resources
10CPOE Scope Management the HIS Environment
11Some Questions to ask
Lets talk about CPOE for a minute
- Projects are steered by the Business Need
- What is the organizations strategic direction?
- How would the project address this strategy?
- What are the projects benefits?
- How are they greater than another projects which
is looking for the same resources?
12Motivation for CPOE
- Newton-Wellesley Hospitals ongoing commitment to
patient safety - Improve patient care
- JCAHO (ongoing Patient Safety Program)
- Pay-for-performance guidelines (Leapfrog)
13Scope Management Tools
- The Project Charter is one of the most important
documents that you will create, and lets
everybody know - The direction and deliverables of the project
- The people and resources involved
- The approach being taken
14PM Tools Techniques
Note CLINICALLY driven project, not IT
15PM Tools Techniques
16CPOE Scope Management Quantifiable Success
Factors Scope All Inpatient units LIVE on
CPOE Time 75 LIVE by end of 2005 all by end
of 2006 Cost under 1,500,000
Keys to a successful CPOE implementation Scope
Statement Quantifiable Success Factors in terms
of Scope, Time, Cost and Quality
17(No Transcript)
18Scope Management
Two of the three top factors identified by the
Standish Group as scope problems were Lack of
User Input, and Incomplete Requirements and
Specifications
19NWH CPOE Scope Management The Teams
- CPOE Scope Management NWH Project Team
- Project manager
- Consultants (one full-, one part-time)
- Physician lead (part-time)
- Nursing lead (full-time)
- Pharmacy lead (full-time)
- Network/Hardware representation
- Guests from upcoming units
- Project Manager, Physician Nurse Lead and CIO
sat on CPOE Steering Committee
- CPOE Steering Committee
- Senior Staff, Physicians, IT, Nursing, Education
- Pharmacy CPOE Committee
- Pharmacists, Consultants, Nursing
- Nursing Practice CPOE committee
- Physician Advisory Committee
- IS Steering Committee
- Directors, Physicians, Nursing
20CPOE - Scope Management
This does not mean that there will not be Change!
21Scope Management
There will always be change in a project, and
factors that you have no control over. In a
dynamic world, and a dynamic industry Change
is unavoidable.
22Scope Management
Scope Creep is the tendency for the requirements
of a project to grow past the initial scope
statement and verification According to the
Standish Group, it is the third most common
Project Problem!
23NWH HIS Project Management
Scope
The Triple Constraint
Resources
Time
Cant Change One without impacting the other Two
24Scope Management
There is no such thing as a free lunch!
If there are no trade-offs there can be no
successful change
You cannot have a change in scope without some
kind of impact on cost and time
It is much easier to implement a change earlier
in the project life cycle than it is in the later
stages
25NWH HIS Project Management
The later change is introduced, the more costly
to implement
26Scope Management
Time can be the greatest obstacle in project
management, and scope creep hits the time
constraint the hardest.
A recent CHAOS report from the Standish Group
states that the average time overrun on
unsuccessful I.T. projects was 222.
27Scope Management
- When is Scope Change Ok?
- New requirements are justified
- Impact to the project is analyzed and understood
- Trade-offs are approved by the Steering Committee
28Some Scope Change Guidelines
Priority CRITICAL project cannot proceed
because the change is critical for project
success IMPORTANT significant negative impacts
or major opportunities missed if the change is
not made DESIRABLE benefits outweigh costs, but
project can succeed without the change POST-LIVE
- the change should be evaluated for inclusion on
the project evolution plan
29Example 1 of CPOE Change Management
- NWH CPOE Project
- Wireless Network Phase Initial Scope
- Enable all inpatient locations
- Infrastructure to support 802.11a,b,g thru x
- Support Leapfrog authentication
- Scale to 3x existing concurrent user access
30Example 1 of CPOE Change Management
What Changed Requirements did not
change But The network as installed in the pilot
did not perform to spec
31Example 1 of CPOE Change Management
- Implementation based on discovery
- Floor plans relayed optimal placement of wireless
access points (APs) - Standard configuration was a linear
infrastructure
That means that the APs were laid in a straight
line down the middle of the unit!
32Example 1 of CPOE Change Management
- How did Change Evolve?
- Pilot testing showed
- drop-outs in connection lost orders, rekeying
needed, no pattern immediately evident - slow response times
33Example 1 of CPOE Change Management
Why the Changes? Wireless connectivity was
required for project success Pilot did its job
showed whether current project build would work
or not in a production environment
34Example 1 of CPOE Change Management
- What ended up changing?
- Network engineering worked with hospital
engineering staff - Found detailed blueprints and opened up walls
that showed cold water copper plumbing and walls
causing interference
- Changed placements to a Diamond configuration
35Example 1 of CPOE Change Management
- Initial Impact?
- CPOE Pilot extended to verify that wireless
changes addressed problems
36NWH HIS Project Management
Estimated 300 hrs labor during Rollout
Approx 30 hrs labor at Pilot
The later change is introduced, the more costly
to implement
37Example 1 of CPOE Change Management
- And the Tradeoffs?
- Minimal!
- Production rollout start date was NOT changed
slack built into project plan allowed for
adjustments - Minor cost impact discovery made in time to
address before network rolled out to production
floors -
38Example 2 of CPOE Change Management
- NWH CPOE Project
- Original Rollout Plan
- Enable All Med/Surg Units 1st
- Enable PACU admits after Inpatient units stable
39Example 2 of CPOE Change Management
What Changed Requirements did not
change But The plan changed based upon feedback
from Ortho/Neuro Surg Inpatient unit mgrs Desire
was to have all patients go on-line at same time
40Example 2 of CPOE Change Management
- Why the Changes?
- Remember Success Factors - User feedback and
input is crucial theyre our customers! - Project Team listened to the reasons
- Easier for staff to not have to decide which
patients stayed on paper - Less confusion when learning the new system and
process
41Example 2 of CPOE Change Management
- What ended up Changing?
- Project Team juggled the rollout schedule to
allow sufficient Discovery Time for PACU Admit
specifications - CPOE Steering Committee approved schedule
adjustments Justified change
42Example 2 of CPOE Change Management
- Initial Impact?
- CPOE Rollout Delayed several weeks to adjust to
new plan
43Example 2 of CPOE Change Management
- And the Tradeoffs?
- Again - Minimal!
- Production rollout dates shifted but
- No overall rollout impact Project Team shifted
their approach - Time spent in PACU to floor discovery performed
earlier than anticipated - made up time later on
in the project
44What Contributed to our Success?
- Senior Staff support great leadership!
- Mandated use of system
- Communicated well between groups
- Well orchestrated and documented rollout plan
- Learned from each unit and moved forward
immediately - Built a strong team and recognized excellence
- This is the most intense team effort youll ever
encounter -
45Example of CPOE Scope Management
Final Result? CPOE rollout completed ahead of
schedule under budget and
its looking great!!!
46Example of Scope Management
Questions? Contact info Cparisi_at_partners.org 61
7-243-6702