Title: Offshore electricity transmission, GB SQSS review


1
Offshore electricity transmission, GB SQSS review
  • Monday 3rd July Andy Hiorns

2
Introduction
  • Sub-group objectives
  • Assess the relevance of the existing onshore GB
    SQSS for application to offshore transmission
    networks
  • Provide recommendations to OTEG identifying
    feasible options for security standards relating
    to offshore transmission networks.
  • Note Amendments to onshore standards are out of
    scope of this group
  • Timescales
  • Submit recommendations to OTEG late August

3
Proposals
  • Focus on most relevant areas of GB SQSS
  • Generation connection criteria
  • Customer choice variations
  • Voltage Compliance
  • Establish appropriate deterministic level for
    generation connection criteria by cost benefit
    analysis
  • Formulate network models
  • Populate with real system data
  • Carry out cost benefit analysis on these models

4
Methodology for analysis
Issues to consider Cable is assumed unavailable
2 of time Generation is at full
output 30 of the time Losses Revenue /
Electrical Benefit gained by installation of
additional circuit capacity
5
Work in progress
  • Proposed network models for analysis presented in
    paper GB SQSS 1. Paper agreed at 2nd subgroup
    meeting 27th June 2006.
  • Defining exact data requirements before carrying
    out cost benefit analysis.
  • Population of network models in progress.
  • Compiling data and maintaining documents with all
    information received.
  • Regular progress meetings planned to ensure
    agreement of work in progress.
  • All assumptions made during the analysis to be
    noted and accompany sub group recommendations.
  • Meeting notes and discussion papers published on
    DTI and Ofgem websites as produced.

6
Issues noted to date
  • Requirement to assess impact that offshore
    security can have on onshore transmission network
    capability to meet ACS demand.
  • Updates to technical codes will follow the GB
    SQSS review work.
  • Commercial frameworks will follow once optimum
    design solution has been established
  • Use of system charges
  • Access rights
  • Interface concerns with DNO connections between
    onshore and offshore TO.