Title: FPU Structure, Baffle and Straylight
1FPU Structure, Baffle and Straylight
- R. Graue, D. Kampf
- Kayser-Threde
2Primary Structure
Chopper Cover
3FPU STM
4Bolometer Integration
5Straylight Analyses Top Optic Model
- ASAP Model of Top Optics
- Derived from optical ZEMAX Model
- Black Coated Walls (gt0.4 mm)
6Straylight Analyses Results and Status
- High straylight suppression
- Neglible straylight impacts in consequent
boxes - Inputs considered for Baffle Design
- Straylight suppression 1e-10 to focal plane
- Modell delivered to ASTRIUM
72K - Feed Through
- Cryo STM Vibration Tested
- Manufactured and Delivered
Outside sleeve Cold finger D/E Retainer ring
1/2 F Muff G Ring
8FPU Suspension Design Status and Material
- Status
- Design completed
- Documentation Completed
- Material
- Fibre T300
- Resin Ciba Geigy
- Araldit LY-3505
- Hardener XP 3403
9FPU Suspension Cryo Qualification Test Matrix
- Status
- Static load tests completed
- (Cold) material characterisation completed
- Cryovibration tests complete
(CRYO STM FPU)
10MGSE and CVSE Status
- MGSE design, procurement and functional test
completed - Vibration test adapter
- Lifting device
- Integration Tools
- FW Test Box
- CVSE design, procurement (cryostat) and
functional test completed
KT Cryostat Test Faciliy for Stability Tests
11Mass Budget
IR Black Paint, Internal Harness, Screws
Contingency not needed
12Performed FPFPU Analyses Program
13PACS Thermal Model
PACS-Thermal Model (Input-Status May 2003) -
PACS thermal model used as submodel of the H-EPLM
reduced thermal model - PACS submodel consists of
154 thermal nodes PACS-TMM includes - All
mechanisms, all harness, radiative environment -
Possibility of transient analysis (cool-down and
operational time-line)
14Thermal Analyses - Status - Completed Tasks
- Thermal Analyses
- Quasisteady state and transient thermal analyses
- Calibration of thermal model (cooling down
curves) after Cryo STM tests - Analyses of thermal links (2 K) wrt conductivity
- Documentation released
15PACS Cool-Down Behaviour
16PACS Thermal Analyses - Open Tasks
- - Update of the cryostat-TMM (Sept. 2003) not yet
included - - Dissipation values of the grating and the
calibration sources are no measured values - Impact of Electrical insulation between
spectrometers and cooling-straps not yet defined
- - Results of the discussion of the
cooling-strap-IFs not yet included - - Contact resistances at the cooling-strap-I/Fs
only assumed, but not measured
17Structural Analyses - Status - Completed
Tasks(see H/O wrt. STM warm/cold vibration)
- Structural Analyses
- Evaluation of ambient and cold vibration tests
- FEM calibration
- Load analyses with calibrated model
(cryo-vibration test) - Strength analyses for FPU metallic and CFRP
components - Cryogenic material properties analyses
- CoG, MoI analyses
- Displacement, distortion, deformation analyses
- Documentation released
18FPU Structure Status External Interfaces
- Design envelope frozen
- Optical beam stay out frozen
- OB envelope frozen
- ? DCNs of Assembly and IF Drawing version 27 to
be approved
19Documents Status
- ICDs
- Chopper, FW, Calibration Source, Filters/
- Dichroics, GaGa Detector, Grating approved
- Bolometer, Distribution Boards approved
- Cryogenic harness and connectors approved
- Procurement specifications (structures,
- mirror, coating, screws/helicoils, Si -lens,
- emitter for CS , etc.) approved
- AIV and functional/environmental test
plan updated - Filled in verification matrix latest status
(10.2003)
20Configuration Control Documents
Document Description Doc.-No. Configuration Control
FPU Interface and Assembly Drawing Version 27 Yes
FPU Design Specification PACS-KT-SP-002 Yes
Ge detector ICD PACS-KT-ID-002 Yes
Bolometer ICD PACS-KT-ID-005 Yes
CS ICD PACS-KT-ID-007 Yes
FW ICD PACS-KT-ID-006 Yes
Distribution Board ICD PACS-KT-ID-004 Yes
21Approved Engineering Documents
Document Description
FPU Alignment Plan
FPU Thermal Analyses
FPU Structural Analysis
FPU Load Analysis
FPU AIV Plan
FPU Environmental and Functional Test Verification Plan
FW Environmental and Functional Test Verification Plan
22PA Activities (KT)
- Approved Documents
- PMP (Update)
- CIDL (Update)
- CIL (Issue1)
- PA Plan (Update)
- MIP/KIP plan (Update)
- Inputs to FMECA (Update)
- Approved procurement/manufacturing
documentation/drawings - Configuration Control
23MIP / KIP List
- Inspection
- FW assembly (CQM/PFM) after functional and
environmental testing - Calibration source (CQM/PFM) after environmental
and functional testing - Coated mirrors (CQM/PFM)
- FPU after vibration tests (CQM/PFM)
- Distribution boards and harness after
manufacturing and functional testing (CQM/PFM)
- Fit check inspection after manufacturing and
coating of aluminium structure (STM/CQM/PFM)
- Functional performance verification after FPU
alignment (CQM/PFM)
24MAIV Status of Structural Items -Completed Tasks
- CQM
- Mechanical items design and manufacturing
drawings completed and released - STM/ CQM metallic items manufactured and IR black
coated - Mechanical Fit check/Preintegration of all
mechanical items (on boxes and FPU level) - STM/ CQM CFRP items manufactured and static load
tested - Cooling straps manufactured
- PFM
- Structural items design and manufacturing
drawings completed and released - CFRP items manufactured and static load tested
25MAIV Status of Structural Items - OpenTasks
- CQM
- Thermal Contact Soldering and GeGa detector
attachment (sapphire embedding) of CQM cooling
straps in progress (until end of Nov. 2003) - Development of GeGa Detector electrical
isolation (thick layer coating) under progress
(until end of Nov. 2003) - PFM
- Substructures and metallic components
manufacturing in progress until April 2004 - Preassembly/fit check until June 2004
- Finish and black Coating until July 2004
26FPFPU Cryo Vibration Qualification Breakdown
?See dedicated chapters
27PACS FPU Verification
- Similarity
- CQM and STM were manufactured parallel with the
same drawingsout of the same lot - Qualification Tests
- STM vibration tests
Tests completed
Conclusion FPFPU Housing is structurally
qualified
28CQM SCHEDULE
- Manufacturing
- CQM primary/secondary structures thermal
treatment /manufacturing /IR coating sequentially
completed - CQMoptical components delivered
- CQM CFRP struts and 2 K feed through material
test program and manufacturing completed - AIV (Final assembly and alignment)
- CQM from 7/03 to 1/04 (tbc)
29PFM SCHEDULE
- Manufacturing
- PFM primary/secondary structures thermal
treatment /manufacturing /IR coating to be
completed until 6.2004 - PFM optical components delivered
- PFM CFRP struts and 2 K feed through material
test program and manufacturing completed - AIV (Final assembly and alignment)
- PFM from 7/04 to 11/04