Title: VadeMecum to set up a programme on European subsidies
1Vade-Mecum to set up a programme on European
subsidies
Philippe Le Guen (leguen_at_racine.fr)
2PART ONE
3Preparatory stage
- The Preparation Phase is of special importance
and serves four purposes - It defines the strategy and the activities that
will be undertaken, estimates their cost and
allocates it between all stakeholders or
partners - It forms basis for resolving potential problems
- It provides a contractual basis on which the
Authorities can approve these activities during
implementation of the work plan. - You are advised to use an effective planning
tool. For example the Logical Framework Approach
or Project Cycle Management could be useful. - This system is based on an approach where
activities are shaped by filling in the grid from
top to bottom, moving from top-left to
bottom-right. In order to check the
appropriateness and viability of the activities
you have set out you verify the connections
between steps, moving in the opposite direction.
4The logical framework for planning a European
project Overview
Intervention
Intervention
Sources of
Sources of
Assumptions
Assumptions
Logic
Logic
Verification
Verification
How to measure
How to measure
How to collect the
How to collect the
The contribution of
The contribution of
Overall
Overall
the objective,
the objective,
information, by
information, by
the project to
the project to
including Quantity,
Objectives
including Quantity,
Objectives
when and by whom
when and by whom
broader objectives
broader objectives
Quality, Time
Quality, Time
How to measure
How to measure
If the Purpose is
If the Purpose is
Direct benefits to
How to collect the
How to collect the
Project
Project
the objective,
the objective,
achieved, what
achieved, what
information, by
information, by
the target group(s)
including Quantity,
assumption must hold
including Quantity,
assumption must hold
Purpose
Purpose
when and by whom
when and by whom
Quality, Time
true to achieve the OO
true to achieve the OO
Quality, Time
How to measure
If Results are achieved,
Better products/ services or processes or
capabilities
How to collect the
Results
Results
the objective,
what assumption must
How to measure
If Results are achieved,
How to collect the
information, by
hold true to achieve the
including Quantity,
the objective,
what assumption must
when and by whom
information, by
when and by whom
Purpose
Quality, Time
including Quantity,
Quality, Time
hold true to achieve the
Tasks to be undertaken to produce results
If Activities are com
-
Tasks to be
undertaken to
Means
Cost
Means
Cost
Activities
Activities
pleted
, what
assump
-
If Activities are com
-
undertaken to
produce the results
tions
must hold true to
pleted
, what
assump
-
produce the results
deliver the results
deliver the results
tions
must hold true to
Conditions that
"Purpose" Describes the expected improvement
concerning the specific problem for which the
project wants to provide innovative solutions
Pre
-
conditions
must be met
before starting
5Establishing the work plan
Resource Scheduling What resources are required?
How much? When?
Work plan What must be done? When? Who is
responsible?
6Points to consider before starting the project
- You must state the start date of the project in
the application form. This must fall within the
funding period. - Bidding rounds are sometimes delayed due to late
approval for the release of funds at Member State
and EU levels. So project approvals may be
delayed.Moreover, you need to consider how the
project may be funded from other sources if the
European application fails. - You should also consider the effect on your
project if it starts late. For example, will you
still be able to deliver it as described in the
application? If not, you should tell the
authorities about any significant changes as soon
as possible. - Risk analysis and risk management of the ESF
project - As well as the rewards, there are risks to
operating European projects.
7Major risks
- Failure to deliver numbers (including target
groups) and outcomes described in the
application.If the actual delivery shows that
numbers and outcomes are significantly reduced,
the whole basis on which the project was approved
may be questioned and could lead to the European
grant being withdrawn and influence the success
of future applications. - Be realistic with your target setting, look at
the performance of similar projects, consult
local partners, use local market information and
other knowledge to assess the feasibility of the
project in your area. - Lack of financial planning, including
organisational risks. Failure to adequately plan
for the flow of cash may lead to liquidity
problems (a lack of cash to run the business and
could lead to its closing down). - It is important to consider the organisations
cash resources as well as the individual
cashflows associated with a particular project.
You should draw together a cash forecast as
accurately as you are able, building in the
outgoings and receipts, as they are likely to
arise. You should then identify when you will
need to meet any particular cash shortages.
8- Risks of incurring significant additional costs
which are not covered by funding if the financial
projections in the application are not accurate.
The programme will not fund more than the
approved costs declared in the application, so if
the project overspends it is at your risk. This
will be particularly important if elements of the
project are to be delivered by partners or
subcontractors. - You should get clear estimates of costs from them
at the application stage and contracts put in
place once the project is approved should make
sure that responsibility for overspending is
clearly defined and understood by all parties. - Failure to share knowledge with your
organisations strategic decision makers. At a
very early stage senior management should have
considered the aims of the project and its links
to the organisations goals and objectives. It is
important that they are informed of the risks as
well as the rewards of operating European
projects. - The senior management team and anyone else who
should be involved should be informed as early as
possible of the project and the risks. This
briefing should also make clear the
responsibilities of you and your partners to find
the balance of funds, maintain detailed records
and to meet the requirements of the contract. - It is essential that you regularly report on the
performance of projects to the senior management
so they can assess how well the project is
meeting the organisations objectives and how it
is performing against the original profile. They
can then identify where action may be needed to
put things right and assess the general
performance of the activity.
9- Failure to project partners
- The vast majority of projects are now delivered
in partnership with other partners or
subcontractors. All the risks also relate to the
delivery of elements of the project by third
parties. However, you are responsible for the
correct operation of the European project
regardless of who is delivering it, where the
records are held or where errors have been found.
So it is your responsibility to repay sums due as
a result of any errors. - It is recommended that you draw up a contract
with significant partners and subcontractors.
This should set out the exact nature of the
relationship, how the project will be funded, the
record keeping requirements, the reporting
requirements, the expenditure eligibility. - Signing a contract alone does not provide you
with absolute peace of mind that the third
parties are keeping appropriate records and are
following the relevant rules. You should monitor
them to make sure that they are keeping to the
requirements of the contract at least once during
the life of the project.
10PART TWO
11Types of procedures
- According to the different European programmes or
funds, several type of procedures may apply, such
as - Procedures involving publication international
open tender (supplies/works), and restricted
tender (services) are published on the EuropeAid
Co-operation Office website http//www.europa.eu.i
nt/comm/europeaid/index_en.htmthe EU Official
Journal and the appropriate media in the
candidate country. Local open tender
(supplies/works) are published only in the
recipient country. - Procedures not involving publication simplified
procedure (direct consultations of companies with
receipt and evaluation of at least three valid
offers), Framework Contracts for services (rapid
consultation of three potential already
pre-selected contractors) and negotiated
procedure (no competition possible only under
strict conditions). - Open procedure open invitation to take part in
competitive tendering. - Restricted tender not all applicants qualify to
submit a tender dossier. The first procedure is
to invite interested companies to express their
interest. The Contracting Authority draws up a
shortlist and only short-listed applicants are
given the opportunity to submit a tender dossier.
12(No Transcript)
13Other important issues
- Co-financing
- Additional funding are often required from the
following entities the beneficiary countrys own
resources, an individual Member States bilateral
assistance programme, international organisations
such as UN agencies, the World Bank, the European
Investment Bank (EIB) and the European Bank for
Reconstruction and Development (EBRD). - Key documents Terms of Reference (for service
contracts) and Technical Specifications (for
supply and work contracts) provide instructions
and guidance to contractors at the tendering
stage about the nature of the activity (services,
works, supplies) tendered for. - These documents are key to the success of a
project, and must be followed thoroughly, to
ensure that the project has been properly
conceived, that the work will be carried out on
schedule and that resources will not be wasted.
14Contract award procedures
- The basic principal governing the award of
contracts is competitive tenderingThis is aimed
at ensuring transparency and the desired quality
of services, supplies and works at the best
possible price. - The best technical offer within the available
budget will be selected. - Feedback to applicants
- You will receive written feedback on your
application. This will allow you to identify the
strengths and weaknesses of your application. If
your application has not reached the minimum
level in a question, you will be told. -
- If your application is not successful, you will
be able to appeal. You can base your appeal only
on the information you originally provided in the
application no new information is allowed.
15Examples of questions for applicants
- Please provide details of the objectives of your
Project, making it clear how they fit with the
Programme theme you have chosen. Eight marks are
allocated to this question. you must reach the
minimum level of 5 out of 8 in this section to be
eligible for selection. - Full answer (8 marks) Your project has clear
objectives that fit wholly with the priorities of
your chosen theme and the leading principles of
the European programme. - Less-full answer (5 marks) There is the type of
evidence listed above, but it is general rather
than sharply focused or is incomplete (or both). - Part answer (fewer than 5 marks) There is little
evidence that your projects objectives fit well
with the priorities of the programme (so your
proposal does not justify support).
16- Please provide an overview of the nature of
activities you will be delivering and indicate
the main outputs you expect (500 words). Four
marks are allocated to this question. - Full answer (4 marks) You have identified some
clearly-focussed and appropriate activities that
fit well with the priorities of the programme. - Less-full answer (3 marks) The response outlines
the type of activities listed in the terms of
reference, but the activities you have identified
are less well focused and less appropriate to
your project. - Part answer (2 marks) There is little evidence
that the activities you have identified fit well
with the priorities of your project. - No answer (0 marks) There is no evidence that
the activities fit well with the priorities of
your project.
17PART THREE
18Recording and keeping evidence of the outputs and
outcomes of the project
- It is important to remember that every project
totally or part-financed by European funds must
deliver outputs, such as qualifications, jobs,
business creation You must keep records to prove
that these outputs have been achieved. - The project application form will specify the
outputs of the project. However, you need to
check your contract and any relevant guidance
notes to make sure that you are aware of any
extra outputs needed to get the grant. - To help track the performance of the project it
may be beneficial to profile the forecast outputs
on a monthly or quarterly basis. These profiles
can then be compared with actual results and you
can then take action if they are not on track. If
you forecast the outputs are going to vary by
more than 15 you must report this to the
Authorities as a significant change and ask for
their approval. - Examples of appropriate evidence are
- Copies of reports or publications
- All financial records such as copy of invoices,
as well as proof of payment - Minutes of meetings or other relevant
correspondence.
19Evaluating the effectiveness a European project
ex. Improving the situation of disadvantaged
target groups
Did it work?
Did we do what we planned?
Disadvantaged people situation
Is the situation of the disadvantaged improved?
PROJ. PURPOSE
Purpose achieved?
Process/product perspective
Have we improved our offering?
Has it enabled better products and services?
Internal process perspective
Have our activities been changed or added to?
Has it enabled better processes?
PROJ. RESULTS
Capabilities perspective
Have we changed or added to our tangible and
intangible capital?
Effectiveness evaluation provides information and
evidence concerning "have better capabilities
really helped to improve the processes and have
the improved processes really helped deliver
better products/services and thus more satisfied
clients?"