VadeMecum to set up a programme on European subsidies - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

VadeMecum to set up a programme on European subsidies

Description:

... responsibility for overspending is clearly defined and understood by all parties. ... making it clear how they fit with the Programme theme you have chosen' ... – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 20
Provided by: philipp67
Category:

less

Transcript and Presenter's Notes

Title: VadeMecum to set up a programme on European subsidies


1
Vade-Mecum to set up a programme on European
subsidies
Philippe Le Guen (leguen_at_racine.fr)
  • Ankara October 20, 2004

2
PART ONE
  • getting started

3
Preparatory stage
  • The Preparation Phase is of special importance
    and serves four purposes
  • It defines the strategy and the activities that
    will be undertaken, estimates their cost and
    allocates it between all stakeholders or
    partners
  • It forms basis for resolving potential problems
  • It provides a contractual basis on which the
    Authorities can approve these activities during
    implementation of the work plan.
  • You are advised to use an effective planning
    tool. For example the Logical Framework Approach
    or Project Cycle Management could be useful.
  • This system is based on an approach where
    activities are shaped by filling in the grid from
    top to bottom, moving from top-left to
    bottom-right. In order to check the
    appropriateness and viability of the activities
    you have set out you verify the connections
    between steps, moving in the opposite direction.

4
The logical framework for planning a European
project Overview
Intervention
Intervention
Sources of
Sources of
Assumptions
Assumptions
Logic
Logic
Verification
Verification
How to measure
How to measure
How to collect the
How to collect the
The contribution of
The contribution of
Overall
Overall
the objective,
the objective,
information, by
information, by
the project to
the project to
including Quantity,
Objectives
including Quantity,
Objectives
when and by whom
when and by whom
broader objectives
broader objectives
Quality, Time
Quality, Time
How to measure
How to measure
If the Purpose is
If the Purpose is
Direct benefits to
How to collect the
How to collect the
Project
Project
the objective,
the objective,
achieved, what
achieved, what
information, by
information, by
the target group(s)
including Quantity,
assumption must hold
including Quantity,
assumption must hold
Purpose
Purpose
when and by whom
when and by whom
Quality, Time
true to achieve the OO
true to achieve the OO
Quality, Time
How to measure
If Results are achieved,
Better products/ services or processes or
capabilities
How to collect the
Results
Results
the objective,
what assumption must
How to measure
If Results are achieved,
How to collect the
information, by
hold true to achieve the
including Quantity,
the objective,
what assumption must
when and by whom
information, by
when and by whom
Purpose
Quality, Time
including Quantity,
Quality, Time
hold true to achieve the
Tasks to be undertaken to produce results
If Activities are com
-
Tasks to be
undertaken to
Means
Cost
Means
Cost
Activities
Activities
pleted
, what
assump
-
If Activities are com
-
undertaken to
produce the results
tions
must hold true to
pleted
, what
assump
-
produce the results
deliver the results
deliver the results
tions
must hold true to
Conditions that
"Purpose" Describes the expected improvement
concerning the specific problem for which the
project wants to provide innovative solutions
Pre
-
conditions
must be met
before starting
5
Establishing the work plan
Resource Scheduling What resources are required?
How much? When?
Work plan What must be done? When? Who is
responsible?
6
Points to consider before starting the project
  • You must state the start date of the project in
    the application form. This must fall within the
    funding period.
  • Bidding rounds are sometimes delayed due to late
    approval for the release of funds at Member State
    and EU levels. So project approvals may be
    delayed.Moreover, you need to consider how the
    project may be funded from other sources if the
    European application fails.
  • You should also consider the effect on your
    project if it starts late. For example, will you
    still be able to deliver it as described in the
    application? If not, you should tell the
    authorities about any significant changes as soon
    as possible.
  • Risk analysis and risk management of the ESF
    project
  • As well as the rewards, there are risks to
    operating European projects.

7
Major risks
  • Failure to deliver numbers (including target
    groups) and outcomes described in the
    application.If the actual delivery shows that
    numbers and outcomes are significantly reduced,
    the whole basis on which the project was approved
    may be questioned and could lead to the European
    grant being withdrawn and influence the success
    of future applications.
  • Be realistic with your target setting, look at
    the performance of similar projects, consult
    local partners, use local market information and
    other knowledge to assess the feasibility of the
    project in your area.
  • Lack of financial planning, including
    organisational risks. Failure to adequately plan
    for the flow of cash may lead to liquidity
    problems (a lack of cash to run the business and
    could lead to its closing down).
  • It is important to consider the organisations
    cash resources as well as the individual
    cashflows associated with a particular project.
    You should draw together a cash forecast as
    accurately as you are able, building in the
    outgoings and receipts, as they are likely to
    arise. You should then identify when you will
    need to meet any particular cash shortages.

8
  • Risks of incurring significant additional costs
    which are not covered by funding if the financial
    projections in the application are not accurate.
    The programme will not fund more than the
    approved costs declared in the application, so if
    the project overspends it is at your risk. This
    will be particularly important if elements of the
    project are to be delivered by partners or
    subcontractors.
  • You should get clear estimates of costs from them
    at the application stage and contracts put in
    place once the project is approved should make
    sure that responsibility for overspending is
    clearly defined and understood by all parties.
  • Failure to share knowledge with your
    organisations strategic decision makers. At a
    very early stage senior management should have
    considered the aims of the project and its links
    to the organisations goals and objectives. It is
    important that they are informed of the risks as
    well as the rewards of operating European
    projects.
  • The senior management team and anyone else who
    should be involved should be informed as early as
    possible of the project and the risks. This
    briefing should also make clear the
    responsibilities of you and your partners to find
    the balance of funds, maintain detailed records
    and to meet the requirements of the contract.
  • It is essential that you regularly report on the
    performance of projects to the senior management
    so they can assess how well the project is
    meeting the organisations objectives and how it
    is performing against the original profile. They
    can then identify where action may be needed to
    put things right and assess the general
    performance of the activity.

9
  • Failure to project partners
  • The vast majority of projects are now delivered
    in partnership with other partners or
    subcontractors. All the risks also relate to the
    delivery of elements of the project by third
    parties. However, you are responsible for the
    correct operation of the European project
    regardless of who is delivering it, where the
    records are held or where errors have been found.
    So it is your responsibility to repay sums due as
    a result of any errors.
  • It is recommended that you draw up a contract
    with significant partners and subcontractors.
    This should set out the exact nature of the
    relationship, how the project will be funded, the
    record keeping requirements, the reporting
    requirements, the expenditure eligibility.
  • Signing a contract alone does not provide you
    with absolute peace of mind that the third
    parties are keeping appropriate records and are
    following the relevant rules. You should monitor
    them to make sure that they are keeping to the
    requirements of the contract at least once during
    the life of the project.

10
PART TWO
  • Contracting

11
Types of procedures
  • According to the different European programmes or
    funds, several type of procedures may apply, such
    as
  • Procedures involving publication international
    open tender (supplies/works), and restricted
    tender (services) are published on the EuropeAid
    Co-operation Office website http//www.europa.eu.i
    nt/comm/europeaid/index_en.htmthe EU Official
    Journal and the appropriate media in the
    candidate country. Local open tender
    (supplies/works) are published only in the
    recipient country.
  • Procedures not involving publication simplified
    procedure (direct consultations of companies with
    receipt and evaluation of at least three valid
    offers), Framework Contracts for services (rapid
    consultation of three potential already
    pre-selected contractors) and negotiated
    procedure (no competition possible only under
    strict conditions).
  • Open procedure open invitation to take part in
    competitive tendering.
  • Restricted tender not all applicants qualify to
    submit a tender dossier. The first procedure is
    to invite interested companies to express their
    interest. The Contracting Authority draws up a
    shortlist and only short-listed applicants are
    given the opportunity to submit a tender dossier.

12
(No Transcript)
13
Other important issues
  • Co-financing
  • Additional funding are often required from the
    following entities the beneficiary countrys own
    resources, an individual Member States bilateral
    assistance programme, international organisations
    such as UN agencies, the World Bank, the European
    Investment Bank (EIB) and the European Bank for
    Reconstruction and Development (EBRD).
  • Key documents Terms of Reference (for service
    contracts) and Technical Specifications (for
    supply and work contracts) provide instructions
    and guidance to contractors at the tendering
    stage about the nature of the activity (services,
    works, supplies) tendered for.
  • These documents are key to the success of a
    project, and must be followed thoroughly, to
    ensure that the project has been properly
    conceived, that the work will be carried out on
    schedule and that resources will not be wasted.

14
Contract award procedures
  • The basic principal governing the award of
    contracts is competitive tenderingThis is aimed
    at ensuring transparency and the desired quality
    of services, supplies and works at the best
    possible price.
  • The best technical offer within the available
    budget will be selected.
  • Feedback to applicants
  • You will receive written feedback on your
    application. This will allow you to identify the
    strengths and weaknesses of your application. If
    your application has not reached the minimum
    level in a question, you will be told.
  • If your application is not successful, you will
    be able to appeal. You can base your appeal only
    on the information you originally provided in the
    application no new information is allowed.

15
Examples of questions for applicants
  • Please provide details of the objectives of your
    Project, making it clear how they fit with the
    Programme theme you have chosen. Eight marks are
    allocated to this question. you must reach the
    minimum level of 5 out of 8 in this section to be
    eligible for selection.
  • Full answer (8 marks) Your project has clear
    objectives that fit wholly with the priorities of
    your chosen theme and the leading principles of
    the European programme.
  • Less-full answer (5 marks) There is the type of
    evidence listed above, but it is general rather
    than sharply focused or is incomplete (or both).
  • Part answer (fewer than 5 marks) There is little
    evidence that your projects objectives fit well
    with the priorities of the programme (so your
    proposal does not justify support).

16
  • Please provide an overview of the nature of
    activities you will be delivering and indicate
    the main outputs you expect (500 words). Four
    marks are allocated to this question.
  • Full answer (4 marks) You have identified some
    clearly-focussed and appropriate activities that
    fit well with the priorities of the programme.
  • Less-full answer (3 marks) The response outlines
    the type of activities listed in the terms of
    reference, but the activities you have identified
    are less well focused and less appropriate to
    your project.
  • Part answer (2 marks) There is little evidence
    that the activities you have identified fit well
    with the priorities of your project.
  • No answer (0 marks) There is no evidence that
    the activities fit well with the priorities of
    your project.

17
PART THREE
  • Follow-up

18
Recording and keeping evidence of the outputs and
outcomes of the project
  • It is important to remember that every project
    totally or part-financed by European funds must
    deliver outputs, such as qualifications, jobs,
    business creation You must keep records to prove
    that these outputs have been achieved.
  • The project application form will specify the
    outputs of the project. However, you need to
    check your contract and any relevant guidance
    notes to make sure that you are aware of any
    extra outputs needed to get the grant.
  • To help track the performance of the project it
    may be beneficial to profile the forecast outputs
    on a monthly or quarterly basis. These profiles
    can then be compared with actual results and you
    can then take action if they are not on track. If
    you forecast the outputs are going to vary by
    more than 15 you must report this to the
    Authorities as a significant change and ask for
    their approval.
  • Examples of appropriate evidence are
  • Copies of reports or publications
  • All financial records such as copy of invoices,
    as well as proof of payment
  • Minutes of meetings or other relevant
    correspondence.

19
Evaluating the effectiveness a European project
ex. Improving the situation of disadvantaged
target groups
Did it work?
Did we do what we planned?
Disadvantaged people situation
Is the situation of the disadvantaged improved?
PROJ. PURPOSE
Purpose achieved?
Process/product perspective
Have we improved our offering?
Has it enabled better products and services?
Internal process perspective
Have our activities been changed or added to?
Has it enabled better processes?
PROJ. RESULTS
Capabilities perspective
Have we changed or added to our tangible and
intangible capital?
Effectiveness evaluation provides information and
evidence concerning "have better capabilities
really helped to improve the processes and have
the improved processes really helped deliver
better products/services and thus more satisfied
clients?"
Write a Comment
User Comments (0)
About PowerShow.com