Title: NCRA Board Presentation Eureka


1
NCRA Board PresentationEureka
  • November 12, 2008

2
Agenda
  • Status of Construction Projects
  • Signal Contract No. S-1 S-2
  • Urgent Repair Contract No. 2 (King Salmon)
  • Urgent Repair Contract No. 3 (Schellville)
  • Timber Bridge Contract No. T3
  • Brazos Bridge

3
Signal Contract No. 1 Mass Electric
  • Repair 28 Signals Lombard to Santa Rosa
  • TCRP Project 32.9
  • Awarded July 11, 2007
  • Contract Amount 5,818,640
  • Net Change Orders 145,000 (2.5)
  • 25 Signals Complete
  • 3 Signals on Hold Waiting Preemption Design

4
East Railroad, Rohnert Park
5
Payran
6
Main Street Penngrove
7
Signal Contract No. 2 Mass Electric
  • Repair 27 Signals Petaluma to Windsor
  • TCRP Project 32.9
  • Awarded November 1, 2007
  • Contract Amount 4,482,504
  • Net Change Orders (50,000)
  • 20 Signals Complete
  • 2 Signals Deleted
  • 5 Remaining Signals Waiting Equipment

8
(No Transcript)
9
King Salmon Urgent Repair Contract No 2
  • TCRP Project 32.4
  • Awarded September 12, 2007
  • Contract Amount 558,928
  • Net Change Orders Zero
  • All Revetment Placed Phase 12
  • Track Replaced
  • Project Complete.

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
South End Repaired
17
(No Transcript)
18
Schellville Embankment RepairContract G1
  • TCRP 32.4
  • Ghilotti Bros / Cooper Crane
  • Awarded December 21, 2007
  • Contract Amount 1,267,000
  • Net Change Orders 300,388 (24)
  • Major Cost due to Additional 2008 Storm Damage
    after Award Additional Culvert Work
  • All Work Complete Except Slope Protection

19
Timber Bridge Contract T3 Ghilotti Bros./Cooper
Crane
  • Repair 42 Timber Bridges
  • TCRP Project 32.9
  • Awarded November 7, 2007
  • Contract Amount 3,927,700
  • Repairs Completed at RR Slough and Wingo
  • Work Started At Novato Bridge MP 26.93

20
Timber Bridge Contract T3
  • Repairs In-kind
  • No Capacity Increase from Original Design Load of
    E50
  • Deteriorated Creosoted Timber Members replaced
    with Non-Creosoted Timber over waterways

21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
Brazos Bridge
  • Arrested Copper Thieves
  • Repaired damage to gas powered engine
  • Successfully Lowered Bridge 90 feet
  • Key bridge for the Track Contractor to bring in
    material by rail

30
(No Transcript)
31
(No Transcript)
32
(No Transcript)