Keynote Overcoming Barriers to School Efficiency - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Keynote Overcoming Barriers to School Efficiency

Description:

Hybrid Electric Car Of Energy Resources Team. Montgomery County Public Schools, Maryland ... Cost Constraints New Buildings. Resource Constraints Existing ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 31
Provided by: CEE15
Category:

less

Transcript and Presenter's Notes

Title: Keynote Overcoming Barriers to School Efficiency


1
Keynote -- Overcoming Barriers to School
Efficiency
  • Richard G. Hawes, Director
  • Department of Facilities Management

2
We Walk The Walk..
Hybrid Electric Car Of Energy Resources Team
3
Common Barriers
  • Lack of Awareness
  • Lack of Motivation
  • Controlling New School Design
  • Cost Constraints New Buildings
  • Resource Constraints Existing Buildings

4
Overcoming Lack of
Awareness
  • Track Utility Costs And Communicate To CFO
  • Utilize Free Resources To Compare Your Energy
    Performance To Benchmarks
  • Are You Significantly Below Average?

5
Energy Star Ratings for Sampled MCPS Schools
6
Overcoming Lack of
Awareness
  • Show Potential Savings
  • Use Free Resources
  • State And Federal Programs / Tools / Websites
  • Beware Of Vendor Claims, Credibility
  • Average Retrofit Program Among County Agencies
    Has ROI gt 20
  • Energy Use In New Schools Has Decreased Up To 30
    Without Increasing First Costs

7
Overcoming Lack of
Motivation
  • Green Sells
  • Even When Energy Savings Isnt Understood
  • Award / Reward Systems
  • Share Of Savings Returned To School (SERT)
  • Operated By Contractor For MCPS
  • Looking At External Awards This Year Energy
    Star Plaques, Earth Apple Awards

8
Overcoming Lack of
Motivation
  • Curriculum Units On Energy
  • Developing Units In All Disciplines
  • Create A Culture Of Energy Conservation
  • Example Photovoltaic Unit At Goshen ES

9
(No Transcript)
10
Overcoming Lack of
Motivation
  • Curriculum Modules Being Tied Directly Into
    System Wide Instructional Planning Model
  • Must Complement, Not Compete With Basic
    Instructional Goals

11
(No Transcript)
12
(No Transcript)
13
Controlling New School Design
  • Legislation For Life Cycle Cost Analysis / Energy
    Budgets
  • If You Have It On The Books, Enforce It
  • County Code 8-14A New Building Design
  • Originated In Montgomery County By Community
    Advisory Groups
  • Public Schools Construction Program In Maryland
    Also Requires Life Cycle Cost Analysis

14
Controlling New School Design
  • Adopt Guidelines To Direct A/E Firms On Critical
    Points
  • Official Energy Codes Are Weak
  • Enforce IES Design Light Levels
  • Standardize On Selected High Efficiency Lamps
  • Enforce Energy Efficient HVAC Types, Standardize
  • Standardization Improves Maintenance

15
Cost Constraints New Buildings
  • Efficient Buildings Are Not Necessarily More
    Expensive
  • Based On DOE Research, And Local Experience Over
    The Past 15 Years, Integrated Designs Improve
    Quality And Efficiency, Without Increasing Total
    Cost Of Project
  • Efficiency Requires More Thinking, Not More Money

16
Cost Control By Integrated Design
17
Early Involvement Pays

Savings Potential
Cost to Include
SD
DD
CD
PD
18
Cost Constraints New Buildings
  • Exception Geothermal Energy Exchange
  • 0 to 20 Higher HVAC System Cost
  • Rapid Payback Through Combined Energy And
    Maintenance Savings.

19
(No Transcript)
20
Geothermal/Ground Source Heat Pump Systems dont
actually create heat. Instead, they move heat
that already exists. Water is circulated through
a closed Ground Loop system consisting of HDPE
pipes buried beneath the ground.
21
Geothermal Meets Challenges of Customers
  • Improved Operating Efficiencies
  • Energy Reduced 25 To 50
  • Maintenance Reduced 66
  • Maximize Building Comfort
  • Room By Room Control
  • Heating Or Cooling Always Available
  • Quiet Operation
  • Credit Toward LEED Certification

22
Installing The Geo Heat Exchanger
Drilling The Boreholes 100 To 300 May Be Needed
23
Resource Constraints Existing Buildings
  • Energy Capital Improvement Program
  • Since 1978 Has Demonstrated Positive Cash Flow
    Over Each 6-year Funding Cycle
  • Find The Smoking Ballast?
  • Use Utility Operating Funds For Incentive
    Programs, And Quick Payback Projects (lt1 Year)

24
Resource Constraints Existing Buildings
  • New Funding Options Were Looking At This Year
  • QZAB Funding
  • Aging School Funds
  • Lease Agreements (Through MCPS Master Lease With
    Bank Of America)
  • Federal School Renovation Program
  • Community Energy Loan Program (Maryland)

25
Successes To Date
  • 70 Of Schools Have Lighting Retrofits
  • 85 Of Schools Have Energy Management Control
    Systems
  • 3.5 Million Saved Through Occupant Awareness
    Programs
  • All New Buildings Meet Energy Guidelines
  • One Geothermal School Open, One In Design

26
New Initiatives
  • Energy Resources Team Created
  • Energy Manager Position Created
  • Utility Analyst Position Created
  • Energy Now Reports To Directors Office
  • With Existing Five Energy Management Technicians,
    And New Customer Service Specialist

27
New Initiatives
  • Energy Resources Team Created (2001)

Energy Control Central For 170 Schools
28
New Initiatives
  • Pursue Outside Funding Opportunities Of Energy
    Improvements
  • Utility Deregulation
  • Contracts For Electricity And Natural Gas Proving
    Very Rewarding
  • Internet Based Automation Systems For SERT And
    Energy Management

29
The End
Hybrid Electric Car Of Energy Resources Team
30
For More Information
  • Please Visit Out Website At
  • WWW.MCPS.K12.MD.US/Departments/Facilities/GreenSch
    oolsFocus