Overview of the CDA Procurement Process - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Overview of the CDA Procurement Process

Description:

HRM Consultants. Highlights of Cintra-Zachry Proposal ... High Priority Corridor (Port Huron, Michigan to Texas/Mexico border) ... – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 26
Provided by: steveh96
Category:

less

Transcript and Presenter's Notes

Title: Overview of the CDA Procurement Process


1
Regional Border Economic Development
Forum September 3, 2005
2
TTC Purpose and Need
  • Move people and goods across Texas faster, safer
    and more reliably
  • Rapid population growth
  • Increase in registered vehicles
  • Increase in international truck traffic
  • Forecasts indicate transportation demand will
    continue

3
(No Transcript)
4
Concentration of Truck Traffic
1998 Texas Truck Flows
5
TTC Phased Development
  • Plans call for TTC to be developed over the next
    50 years or so
  • Built as needed and as private sector funding
    makes it feasible

6
TTC Conceptual Development
7
Current Transportation Needs
  • Provide alternative to I-35 - Oklahoma to
    Mexico/Gulf Coast Element
  • Develop I-69 Northeast Texas to Mexico element

8
TTC Priority Routes
9
TTC-35 Milestones
  • Comprehensive Development Agreement
  • July 03 to November 04 Reviewed conceptual and
    detailed proposals from three developer
    teams
  • December 16, 2004 Commission Action and Award
  • March 11, 2005 CDA signed with Cintra-Zachry
  • Environmental Study
  • February 2004 Official kick-off/Notice of Intent
  • Spring 2004 First round of public meetings (26)
  • Fall 2004 Second round of public meetings
    (44)
  • Spring 2005 Third round of public meetings (47)

10
TTC-35 Preliminary Corridor Alternatives
11
TTC-35 Environmental Study Continues
  • Preliminary alternatives to be narrowed to
    preferred corridor alternative
  • Fall 2005 Public hearings to get comments on
    the preferred corridor
  • Spring 2006 - Expected completion of Initial
    environmental study
  • Additional studies needed to determine route and
    authorize construction

12
TTC-35 Schedule Two Concurrent Processes
CDA Process Select Long-term Partner (Dec. 16
04) Initial Scope of Work Facility
Development Project 1 Project 2 Project
3 Environmental Process Tier One
(Ongoing) Project 1 Tier Two Project 2 Tier
Two Project 3 Tier Two
13
TTC-35 CDA Contractual Relationship
Separate Contracts. Some Negotiated with
Developer and Others Publicly Procured.
14
Cintra-Zachry Team
  • Cintra, Concesiones de Infraestructuras de
    Transporte, S.A. (Spain)
  • Zachry Construction Corp. (San Antonio, TX)
  • OTHON, Inc.
  • Railroad Industries Incorporated
  • Amey
  • Mercator
  • Public Resources Advisory Group
  • Southwestern Capital Markets
  • National Corporate Network
  • HRM Consultants
  • Ferrovial-Agromán
  • Earth Tech, Inc.
  • PriceWaterhouseCoopers
  • JP Morgan Securities
  • Bracewell Patterson
  • Pate Engineers, Inc.
  • Aguirre Fields LP
  • Rodriguez Transportation Group

15
Highlights of Cintra-Zachry Proposal
  • A 50-year partnership with near, mid, and long
    term projects to develop the Trans-Texas Corridor
    from Oklahoma to Mexico
  • Anticipates over 6 billion in near-term
    transportation construction projects
  • Anticipates a payment in excess of 1 billion to
    TxDOT for additional transportation projects
    within the Corridor
  • Negotiate the right to operate and collect tolls
    for up to 50 years

16
Highlights are Conceptual
  • All proposed Facility alignments, locations,
    financing, and schedules shown in the following
    slides are conceptual and subject to the
    following
  • NEPA process and public input
  • Environmental approvals
  • FHWA approvals
  • TxDOT review and approvals
  • Final traffic and revenue forecasts and financial
    modeling

17
Near-, Mid-, and Long-Term Facilities
Near Term (2005 2010)
Mid Term (2010 2025)
Long Term (2025 - )
Conceptual
18
Proposed Cintra Near-Term FacilitiesEstimated
Construction and Right of Way Costs
? 710,000,000
? 1,793,000,000
? 775,000,000
? 986,000,000
? 1,694,000,000
? 489,000,000
? 852,000,000
Estimates are subject to the environmental
process and final terms.
19
Proposed Cintra Near-Term Facilities Concession
Fees
? 36,700,000
? 580,000,000
? 407,900,000
? 116,300,000
? 32,300,000
Estimates are subject to the environmental
process and final terms.
20
I-69/TTC - Milestones
  • Background
  • ISTEA and TEA 21 Designated as Congressional High
    Priority Corridor (Port Huron, Michigan to
    Texas/Mexico border)
  • 1998 FHWA approval for environmental
    streamlining
  • 2000 I-69 national corridor divided into 32
    subsections
  • 2001 TxDOT selects engineering consultant
  • Environmental Study
  • January 2004 Official kick-off/Notice of Intent
  • Spring 2004 First round of public
    meetings (11)
  • Spring 2005 Expanded study area

21
I-69/TTC ExpandedStudy Area

22
I-69/TTC Environmental Study Continues
  • Identifying reasonable corridor alternatives is
    ongoing
  • Summer 2005 Public meetings to get comments on
    the reasonable corridor alternatives
  • Winter 2005 - Identify preferred corridor
    alternative based on comments from previous
    public meetings
  • Spring 2006 Public hearings to get comments on
    the preferred corridor
  • Winter 2006 - Expected completion of initial
    environmental study
  • Additional studies needed to determine route and
    authorize construction

23
I-69/TTC Comprehensive Development Agreement
  • It will likely be modeled after the CDA for
    TTC-35
  • No proposals have been submitted

24
Trans-Texas Corridor
  • Questions and Discussion

25
Amadeo Saenz, Jr., P.E.Assistant Executive
DirectorEngineering Operations
Contact Information
125 East 11th Street Austin, TX
78701-2483 Phone (512) 305-9504 FAX (512)
463-0283
Write a Comment
User Comments (0)
About PowerShow.com