Title: P1250095194cEJNU
1Southeast Cass Water Resource District, City of
Fargo Southside Flood Protection Project
Update, Assessment Methodology March 3, 2009
2Interstate Hwy 94
Fargo
Southside Flood Control
Moorhead
West Fargo
Preliminary 100 500 Year Floodplains Red and
Wild Rice Rivers
Interstate Hwy 29
Horace
Oxbow
3Southside Flood Control
Wild Rice River Levee Alternative with Preferred
Features
- FEMA levees and Floodwalls
- Channel extensions
- (Red River drain improvements)
- Storage inside of project
4Southside Flood Control
Wild Rice River Levee Alternative Selected
Plan River Stage Changes 100 Year Flood
5Interstate Hwy 94
Fargo
Southside Flood Control
Moorhead
West Fargo
Existing Sheyenne River Preliminary Red Wild
Rice River 100 Year Floodplains with Line of
Protection
Interstate Hwy 29
Horace
6Interstate Hwy 94
Fargo
Southside Flood Control
Moorhead
West Fargo
After Project Existing and Preliminary 100 Year
Floodplains
Interstate Hwy 29
Horace
7Southside Flood Control
Wild Rice River Levee Alternative with Preferred
Features
8Southside Flood Control
Wild Rice River Mini-Bypass
Base Alignment Levee Cost - 16.8M Preferred
Alignment Mini-Bypass Cost - 31.8M
9Mini-Bypass
Heritage hills
Ulphie Subdivision
Red River
Wild Rice River Estates
Cass County Highway 81
100th Ave
Kensington Place
10Southside Flood Control
32nd to 40th Avenues
Base Alignment University Drive Cost -
7.6M Riverside Protection Options Cost 34.4M
37.0M
1132nd to 40th Avenue
- Base Option University Drive
- Components
- Alignment generally parallel University Drive
- Permanent Floodwall (BFE3)
- Earthen Levee (BFE4)
- Approx. 350 Structures Remain Unprotected
(99.M) - Emergency Operation Required
- Cost Estimate
- Construction 6.6M
- Real Estate 1.0M
- Total Project Cost 7.6M
1232nd to 40th Avenue
- Riverside Protection Options
- Protect Approx. 350 Additional Structures
- Options
- Option 1 River Side Permanent
- FW w/ Openings
- Option 2 River Side
- Combination FW w/ Openings
- Option 3 River Side Permanent
- FW w/o Openings
- Cost Estimate
- Total Project Cost 34.4-37.0M
13Floodwall Example
14- Example Wall Concepts
- Option A Prairie Style
- Option B Simulated Brick and Cedar Fence
15Option 1 - River Side Permanent FW w/ openings
Option 2 - River Side Combo FW w/ openings
16Closure Types (Invisible FW vs. Gates)
- Invisible Floodwall (Oak Grove)
- Photos from Flood Control America, Inc
Lower Cost Off-site Storage
- Hinged Flood Gates
- Photos from Presray, Inc. and Walz and Krenzer,
Inc.
Quicker Install On-site Storage Less Seepage
17Pros-Cons
18Southside Flood Control
River Vili
Riverside Protection Options Cost 5.1M 6.1M
19River Vili
20River Vili
- Similar Issues to River Drive Area
- Smaller area 41 properties
- Last presented to the public 11/13/08
- Comment Summary
- 36 comments received
- 19 of 20 Interior Respondents Supportive
- 8 of 16 River Respondents Supportive
- 27 of 36 Support Flood Protection (75)
- Includes 3 potential floodwall openings
- Meet again in March
21Southside Flood Control
Chrisan East
Riverside Protection Options Cost 4.85M
22Southside Flood Control
Chrisan East
23Project Schedule Ongoing Activities
- Environmental Assessment
- Conditional Letter of Map Revision (CLOMR)
- Assessment Analysis
Next Steps
24Southside Flood Control Estimated Cost Summary
25Preliminary Assessment Analysis
Preliminary Assessment District Base
Area Number of Properties 11,810 Area of
Property 23,100 Acres 37.50 Sections
Value of Property 2.42 Billion
26Preliminary Assessment Analysis
- DIRECT BENEFIT CATEGORIES
- Developed / Undeveloped
- Preliminary 100 Yr Floodplain (100 Benefit)
- Preliminary 500 Yr Floodplain (20 30
Benefit) - Above Prelim. 500 Yr Floodplain (10 Benefit)
- INDIRECT BENEFITS
- Transportation
- Infrastructure protection (sanitary sewer)
27Preliminary Assessment Analysis
Preliminary Assessment Categories Map Direct
Benefits - 45.31 Million
88TH AVE S
DRAIN 27
CASS CO HWY 17
28Preliminary Assessment Analysis
- Undeveloped (Ag) Property
- Total cost per acre 100.00
- Total cost per quarter 16,000.00
- Average annual cost per acre 8.20
- Total cost per quarter 1,312.00
- Assumed a 25 year payment schedule at 6.50
interest
29Preliminary Assessment Analysis
100 Benefit, 100 year elev. lt25 feet from
structure
30 Benefit 100 year elev. gt25 feet from structure
30SOUTHSIDE FLOOD CONTROL
31SOUTHSIDE FLOOD CONTROL
32Southside Flood Control
Estimated Costs to 150,000 Home
- Cost of flood insurance
- 1,500/- Annually
- Total paid during life of a 20 year loan-30,000
- Cost of special assessment
- 3,000 Total Assessed
- 250 Annually includes interest
- Total paid over 25 years - 6,250 including
interest
33SOUTHSIDE FLOOD CONTROL
34SOUTHSIDE FLOOD CONTROL
35Southside Flood Control Estimated Cost Summary
36Preliminary Assessment Analysis
37Southside Flood Control Estimated Cost Summary
38Southside Flood Control Estimated Cost Summary
39Water Resource District Assessment District
Process
- Create assessment district
- Prepare a preliminary assessment list
- Send ballots to all property owners on assessment
list. - One ballot per parcel owned
- Ballot value based on proposed assessment
- Conduct a project hearing
- Ballots returned by mail
40Water Resource District Assessment District
Process
- Count all ballots returned
- Weighted by amount you pay
- If more than 50 of ballots returned vote yes
project may proceed - Conduct an assessment hearing
- Finalize assessment list
41Water Resource District Assessment District
Process
Reassessment of Benefits As the undeveloped
properties in the assessment district get
developed, the WRD can reassess the benefits so
all properties pay for similar benefits.
42Informational Public Meetings Assessments
- March 16, Discovery School 700 PM
- March 18, Horace Community Center 700 PM
- March 24, Discovery School 700 PM
- April 2, Discovery School 700 PM
- Additional meetings to be announced.
43Southside Flood Control
Questions / Discussion