As-built floor plans. Detailed drawings of problem areas in buildings ... Produce floor plans. Solution design. Cost Estimate. Project Approach ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 15
Provided by: LaptopSoft
Category:

less

Transcript and Presenter's Notes

Title: Prepared by: HHKL Consultants September 27, 2000


1
Prepared byHHKL ConsultantsSeptember 27, 2000
  • Proposal for Rehabilitation of Downtown
  • Clay City, Indiana

2
Team Members
  • Bob Ladisich - Project Manager
  • Austin Holcomb - Project Engineer
  • Nathan Knies - Project Engineer
  • Jamia Haenggi - Project Engineer

3
Presentation Overview
  • Bob - Introduction Problem Statement
  • Austin - Project Scope
  • Nathan - Project Approach
  • Jamia - Cost Analysis Timeline

4
Introduction
  • Description of Clay City, Indiana
  • Clay City USA Foundation
  • Background
  • Objectives

5
Problem Statement
  • Dilapidated Buildings
  • Flooding
  • Undesirable Streetscape

6
Project Scope
  • Structural evaluation
  • Local flooding investigation solution
  • Streetscape evaluation solution

7
Project Scope
  • Deliverables
  • As-built floor plans
  • Detailed drawings of problem areas in buildings
  • Topographic map of downtown
  • Solution design for flooding
  • Streetscape suggestions
  • Cost analysis for proposed solutions

8
Project Scope
  • Constraints
  • Uniform Building Code
  • Standards Guidelines for Rehabilitating
    Historic Buildings
  • Indiana Drainage Standards
  • INDOT regulations
  • Client
  • Environmental

9
Project Approach
  • Structural Evaluation Solution
  • Detailed visual inspection
  • Measure for as-built drawings
  • Produce floor plans
  • Solution design
  • Cost Estimate

10
Project Approach
  • Local Flooding Investigation Solution
  • Gather historic rainfall data
  • Site survey
  • Produce topographic map
  • Model analysis using HEC-HMS
  • Solution design
  • Cost Estimate

11
Project Approach
  • Streetscape Evaluation Solution
  • Visual inspection
  • Site survey
  • Produce plan map
  • Solution design
  • Cost Estimate

12
Design Cost
13
Timeline
  • October 18 - Proposal to client
  • January 17 - Progress report to client
  • May 2 - Final presentation to client

14
Summary
  • Problems of downtown Clay City
  • Project scope
  • Project approach
  • Project cost estimate timeline
  • Questions?