External Independent Reviews - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

External Independent Reviews

Description:

2006. Project. Management. Workshop. External Independent Reviews. Catherine Santana ... Add Value to the Department, Programs and Projects ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 11
Provided by: s730
Category:

less

Transcript and Presenter's Notes

Title: External Independent Reviews


1
External Independent Reviews
  • Catherine Santana
  • November 14, 2006

2
Improving the EIR Process
  • EIRs Should Not be One Size Fits All
  • Develop Risk Based EIR Plans
  • Match Team Expertise to Review Requirements
  • Increase Review Team Resources
  • Strive to Shorten Review Period
  • Develop Consistent Processes and Criteria

3
Goals
  • Add Value to the Department, Programs and
    Projects
  • Help to Improve Projects Success in Executing to
    the Established Baseline
  • Increase EIR and Project Credibility
  • Reduce EIR Costs
  • Work Collaboratively

While Remaining Objective and Independent
4
One Size Fits All
  • Same Level of Effort and Same Costs, Regardless
    of Complexity and Scope of Project
  • Tailoring Considerations
  • Project Risk and Complexity
  • Project Tailoring Strategy
  • Breadth and Depth of the Review
  • Lines of Inquiry
  • Paper Review/Site Review

Just as you Tailor the Project so Shall we Tailor
the Review
5
Consistent Results
  • Quality
  • Report
  • Findings and Recommendations
  • Interpretation of DOE O 413.3A and DOE M 413.3-1
  • Level of Program/Project Knowledge
  • Collaborative Approach

6
Next Steps
  • Revamp the EIR Process
  • Conduct Facilitated Process Reviews
  • Capture Lessons Learned
  • Evaluate Existing Contract
  • Develop Contractor Performance Measures
  • Develop EIR Statistics
  • Costs
  • Time to Validate
  • Baseline Cost and Schedule Impacts
  • Common Findings/Recommendations

7
What Have We Learned?
  • Major Findings and Other Findings are Often
    Significant
  • Baselines Cannot be Validated with the Initial
    Review
  • Corrective Action Plans are Often Almost
    Always Required
  • Satisfactorily Resolving Findings Extends the EIR
    Timeline

8
Common Findings
  • Funding Profiles do not Support the Project
    Baselines
  • Cost and Schedule Contingencies are Under
    Estimated
  • Critical Paths are Often Obscured by Level of
    Effort Activities
  • Risk Management Plans are Deficient
  • Assumptions are Invalid or Too Optimistic
  • Management Reserve is not Defined or Included

Often Identify Inadequate Project Management
Infrastructures Necessary to Execute the Baseline
9
Risk Management Plans
  • Many common risk events that are normally
    associated with projects are not included in
    the risk management plan
  • The risk register does not indicate the
    probability and consequence rankings for each
    risk
  • Mitigation strategies are not specifically shown
    as discrete activities in the project schedule
  • The risk/contingency analysis is not risk based
  • Lack of quantitative contingency analysisto
    address the occurrence of risk events.

10
Impact Can Be Significant
Incomplete Risk Management Plans
Faulty Assumptions
Inadequate Management Reserve and Contingency
Under Estimated Baselines
Write a Comment
User Comments (0)
About PowerShow.com