Mountaineer Wind Energy Center
  • Phil Stiles Engineer
  • North Carolina Wind Summit
  • 9 December 2002

2
Aerial Visualization
3
Aerial Visualization
4
Mountaineer Overview
  • 66 MW Wind Power Plant
  • 44 Wind Turbines
  • NM72c
  • 72 meter diameter rotor
  • 1.5 MW
  • Largest wind farm east of the Mississippi
  • First wind farm in West Virginia
  • Backbone Mountain ridgeline near Thomas, West
    Virginia

5
Team Members
  • Developer - Atlantic Renewable Energy Corporation
  • Owner and Operator - Florida Power and Light
  • Construction - Mortenson
  • Turbine Supplier - NEG Micon
  • Power Purchaser Exelon Corporation
  • Power Consumers
  • National Geographic Society
  • U.S. Army
  • Catholic University
  • Many others

6
Project Milestones
  • 1998 Development Begun by Atlantic Renewable
    Energy Corporation
  • Climate Measurements
  • Land Leases
  • Permits
  • Interconnect Agreement
  • Power Purchase Agreement
  • Project Engineering
  • June 2002 - Project Purchased by FPL
  • Summer 2002 Construction begins
  • Roads
  • Substation
  • Interconnect
  • August 2002 First Turbine Constructed
  • 20 December Commercial Operation
  • 2023 Planned Re-powering or Decommissioning

7
What are the challenges being faced?
  • Wind Power is New to West Virginia
  • traditionally a coal energy state
  • Topography
  • Transportation
  • Aggressive Construction Schedule
  • Weather
  • Mud
  • Snow
  • Rain
  • Wind

8
Uniqueness of a Ridgeline Project
  • Inflow angle
  • Turbulence intensity
  • Temperature extremes
  • Site access for maintenance

9
Land Use and Neighbors
  • Privately owned land
  • Forestry
  • Mining
  • City of Thomas, West Virginia
  • Blackwater Falls State Park
  • Fairfax Stone State Monument State Park
  • Monongahela National Forest

10
NM72C
  • Generator 1500 kW
  • Hub Height 70 meters (230 feet)
  • Rotor
  • Diameter 72 meters (236 feet)
  • Active Stall Power Regulation
  • Blades
  • 35 meters (115 feet)
  • Manufactured in North Dakota by LM Glasfiber
  • Tower
  • 3 Section
  • Manufactured in North Dakota by DMI

11
Active Stall Animation
12
WindMan Server Solution
  • Level 1 Turbine controllers
  • Control and protect the turbines
  • Controller works autonomously
  • Historical data
  • stored in controllers
  • collected by SCADA system 
  • Level 2 Site server (SCADA system)
  • collects historical data from the turbines
    (10-minute values, event logs etc.)
  • present and process wind farm data
  • operation of the individual turbines
  • Level 3 Remote client/server
  • accessed remotely
  • similar to the software used at the site

13
NEG Micon Overview - Global
  • Based in Randers, Denmark
  • 2000 Employees
  • 1979 Begun Building Wind Turbines
  • More than 10,500 Wind Turbines Installed
  • 18 of all Turbines Installed
  • Manufacturing in 8 Countries
  • Installations in 32 Countries
  • Traded on the Copenhagen Stock Exchange

14
NEG Micon N. America Overview
  • Based in Chicago, Illinois
  • Service Center in Champaign, Illinois
  • 70 Employees
  • 10 Service Offices
  • Palm Springs, California to Quebec, Canada
  • Thomas, West Virginia is the newest service
    office
  • Broad Product Line
  • Installation
  • Warranty
  • Service

15
Thank You for Your Attention