ISQM 410 - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

ISQM 410

Description:

ISQM 410 Project Management – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 12
Provided by: markfontai
Category:
Tags: isqm

less

Transcript and Presenter's Notes

Title: ISQM 410


1
ISQM 410 Project Management
  • Chapter 5 Estimating Project Costs and Times

2
Estimating Cost Time
  • Estimating Project Costs Times
  • Estimating process of forecasting or
    approximating the time and cost of completing
    project deliverables
  • Unique to the organizations there is no off the
    shelf process
  • 2 types
  • Macro top-down derived by analogy or
    mathematical relationships (parametric)
  • Most useful for strategic decision making, high
    uncertainty, small, internal projects, unstable
    scope
  • Micro bottoms-up based on estimates of
    elements found in the WBS
  • Most useful when cost/time are important, fixed
    price contracts and when customers want details
  • Accuracy increase with time spent e.g., they
    cost
  • Cost, time, budget estimates are the lifeline
    to controlling projects prime mechanism to
    control cost, schedule performance

3
Estimating Cost Time
  • Factors Influencing Estimate Quality
  • Planning horizon accuracy decreases over time
  • Project duration new technology expands in a
    nonlinear fashion
  • People skill level critical to accuracy
  • Project structure organization dedicated
    teams improves accuracy
  • Padding estimates accuracy key to
    competitiveness
  • Organizational culture value placed on
    estimates and accuracy
  • Non-project factors equipment downtime,
    holidays, legal limits, etc

4
Estimating Cost Time
  • Macro vs. Micro Estimating
  • Macro (parametric) approaches
  • Ratio method used in the concept (need)
    phase. Ex. - 110/SF. x 2,700 SF 297,000
  • Apportion method extension of ratio method
    based on past projects/costs require good
    historical accuracy to ensure accuracy. Ex.
    Construction loan payouts 3 for foundation,
    25 for framing, 15 for plumbing/heating, etc.
    Can apportion costs to WBS deliverables based on
    history.
  • Function Point Methods for SW and IT projects
    function points are weighted macro variables or
    major parameters such as no. of inputs/outputs,
    number of inquiries, data files and interfaces.
    Usually adjusted for complexity and added.
    Provide basis for estimating labor.
  • Learning Curves used for repetitious projects
    of similar scope. Recognize that learning occurs
    with repetition. Each time the output quantity
    doubles, the unit labor hours are reduced at a
    constant rate. 60 significant improvement
    100 no improvement.

5
Estimating Cost Time
  • Macro vs. Micro Estimating
  • Micro approaches
  • Template methods uses past, similar projects as
    a starting point and then adjusted for
    differences. Permits development of schedule,
    cost and budget estimates in a short period of
    time.
  • Parametric methods applied to specific tasks
    similar to parametric techniques, but applied to
    WBS tasks. Ex. Wallpaper estimate (5/SY paper
    x 2SY installation 7SY)
  • Detailed estimates for WBS work packages based
    on experience of personnel doing the work. If
    significant uncertainty exist, often use low,
    avg. high estimates
  • Phase estimating (hybrid) begins with macro
    estimate and refines it for phases of the
    project. Breakdowns may include concept
    definition, design production, deliverables, work
    package definition, etc.

6
Estimating Cost Time
  • Estimating Level of Detail
  • Rule 1 Level of detail should be no lower than
    necessary sufficient
  • Senior management total project and major
    milestone level generally sufficient
  • Middle management project segments (phase) of
    milestone level
  • Level of detail in WBS will vary with project
    complexity, need for control (related to risk),
    size, cost, duration
  • Can use different levels based on need

7
Estimating Cost Time
  • Budget estimates
  • Not the same as cost estimates.
  • Cost estimate becomes a budget when it is
    time-phased.
  • WBS work packages require time-phased budgets
  • Includes duration and start/end dates
  • Types of costs include direct labor, materials,
    equipment, overhead, GA

8
Estimating Cost Time
  • Types of Cost
  • Direct Costs
  • Clearly chargeable to one or more work packages
    project/work package specific
  • Include direct labor, materials, equipment,
    POs/subcontracts, computer SW/HW
  • Direct O/H Costs
  • Functional organization O/H expenses that benefit
    the project directly (can come from line
    organizations or project organization indirect
    costs
  • Generally expressed as a ratio percent or
    rate/hour
  • Typically applied to a direct cost (labor or
    materials)
  • GA Overhead Costs
  • Organizational costs not directly linked to a
    specific project
  • Typically applied throughout the project (may
    include marketing, HR, accounting, etc.)
  • Generally allocated as a percent of total costs
    or total direct costs

9
Estimating Cost Time
  • Estimating guidelines
  • Responsibility at work package level, should be
    done by person most familiar with work
  • Use several people to estimate all should have
    relevant experience
  • Normal conditions should be based on normal
    conditions, efficient methods and normal level of
    resources (Ex. 8 hours for shift work)
  • Time units all time estimates need consistent
    time units
  • Independence should assume independence of
    tasks
  • Contingencies should not include allowances for
    contingencies (should be estimated separately at
    a higher level)
  • Add risk assessments to estimates to avoid
    surprises new technology vs. proven process.
    Use optimistic, most likely and pessimistic
    estimates.

10
Estimating Cost Time
  • Refining Estimates Contingency Funds
  • Required (and a god business practice) because of
    unknowns present in all projects
  • Adjustments may range from 10 to gt 100
  • Why
  • Hidden interaction costs dependencies,
    hand-offs, etc.
  • Normal conditions do not always apply differing
    site conditions on construction projects
  • Things go wrong - Murphys Law
  • Changes in scope and plans often resulting from
    better knowledge as project progresses
  • Adjusting estimates should be part of normal
    project management activities risks, resource
    availability
  • Contingency Funds can be project level, work
    package level, or phase specific gt the more
    specific, the more effective

11
Estimating Cost Time
  • Creating an Estimating Database
  • Based on the PDCA cycle in TQM
  • Utilizes lessons learned
  • Accumulates historical data (actuals estimates)
    to provide a knowledge base for improving time
    and cost estimates
  • Best practice benchmark
Write a Comment
User Comments (0)
About PowerShow.com