Title: Article Review
1- Article Review
- Scheduling Resources and Project Cost
- Presented by
- Joanne Hiu-Yan Pak, Ashwin Jain, Rodrigo De Lara,
David Beyer
2Presentation Agenda
- Purpose
- To review and understand the importance of
scheduling resources and estimating time and
cost as necessary activities before the start of
a project. More specifically to present methods
for and problems of these activities and to link
them to a latest journal article. - Agenda
- Review (Chapter 5, 8, 9(partial))
- Synopsis Article
- Analysis Article
- Conclusion Article
-
3Scheduling Resources
- Project network times are not a schedule
- until resources have been assigned
- 2 situations
- Resources are adequate but the demand varies over
life of the project - -gt resource leveling / smoothing
- Resources are not adequate to meet peak demands
- -gt resource-constrained scheduling
4Scheduling Resources
Time Constrained
Resource Constrained
- Classification of a Scheduling Problem as
- Must be completed by an imposed date
- Time is fixed
- Resources are flexible
- Additional resources are required toensure
project meets schedule
- Must be completed withavailable resources
- Time is flexible
- Resources are fixed
- Level of resources availablecannot be exceeded
5Scheduling Resources
- Resource Allocation Method for
- time-constrained projects
- Balancing or smoothing resource demands by using
positive slack - Three goals of smoothing
- Reduce peak of demand for the resource.
- Reduce resources over life ofthe project.
- Minimize fluctuation in resource demand.
- Resource Allocation Method for
- resource-constrained projects
6Scheduling Resources
7Scheduling Resources
- Resource Allocation Method for time-constrained
projects - Balancing or smoothing resource demands by using
positive slack - Three goals of smoothing
- Reduce peak of demand for the resource.
- Reduce resources over life ofthe project.
- Minimize fluctuation in resource demand.
- Resource Allocation Method for resource-constraine
d projects - Scheduling of activities requires the use of
heuristics - Prioritize activities by
- Minimum slack
- Smallest duration
- Lowest activity identification number
8Scheduling Resources
- Minimum slack
- Smallest duration
- Lowest activity ID
2
2
2
2
1
1
1
1
1P
1P
3P
3P
9Scheduling Resources
Resource allocation generally occurs in a
multiproject environment and is linked to three
common problems
Resourcebottlenecks
Overall scheduleslippage
Inefficient resourceutilization
10Cost Estimating
- What is estimating?
- process of forecasting or approximating the time
andcost of completing project deliverables - Task of balancing the expectations of
stakeholders - Need for control while the project is implemented
- Types of estimating
- Top-Down (macro)
- Bottom-Up (micro)
11Cost Estimating
- Macro Approaches for Estimating
Apportion Method
Ratio Methods
Consensus Methods
Learning Curves
Function point methods
12Cost Estimating
- Micro Approaches for Estimating
Detailed Estimates for the WBS Work Packages
Parametric Procedures Applied to Specific Tasks
Phase Estimating
Template Method
13Cost Estimating
- Several factors influence
- the quality of estimates
14Cost Estimating
- Refining estimates
- Why?
- Interaction costs are hidden in estimates, normal
conditions do not apply, things go wrong in
projects and any change in the scope or plans - Adjusting the new estimates.
- Estimates on specific activities ? adjusted as
they become more
defined - A BASELINE is needed.
- Contingency Funds and Time Buffers
- Changing Baseline Schedule and Budget
15Project Cost Overruns
- Article The Amoebic Growth of Project Costs
- In both public and private sector, projects
always suffer massive cost overruns - Although management already acknowledges and
anticipates the uncertainty in projects, there is
a high probability of unexpected events - Surprise overruns are out of managements
expectation - It is just like the growth of an amoeba
16Seven Stages of Project Expenditure
- Authors provide an analysis of many large
projects for whose involved delay and disruptive
claims - They highlight Seven Stages for extraordinary
project expenditures - 1st stage Estimating for the bid - general
estimation for project cost, - set up maximum and minimum cost for
different part of project - 2nd stage The planning or control estimator -
ensuring that the project follows the project
plan and managing remaining uncertainty - 3rd stage Unexpected growth external changes -
contingency is required to estimate for
additional time and cost
17Seven Stages of Project Expenditure
- 4th stage Growing further impact of naughty
customer and silly contractor - One or both
parties cause change to the product, thus change
to the project - 5th stage Customer behavior dealing with
inference beyond whats anticipated both
parties do not behave the way the contractor/
customer expect them to behave - 6th Stage Systemicity the whole produces more
than the sum of its part one department delay,
lead to other departments delay (the growth of
Amoeba) - 7th stage Accelerating to compensate - high
investment and sunk cost - Lastly, they provide lessons and state that
clients, contractors and project managers are all
responsible
18Time Cost
UNCERTAINTY
19Why and how is project cost amoebic?
- Multiple arenas that can be affected.
- Not linear, dependant on each other.
- Initially prepared for uncertainty but savings
quickly eaten up
20Why and how is project cost amoebic?
- For example
- Arena A - Giveaway costs
- To add value
- Arena C - Acceleration Techniques
- For the project to remain on time
- Plausible solution - Reduce the Scope
- To save time money
- But what about naughty customer
- interpreted the qualityand deliverables to
allowfor change in scope.
21Why and how is project cost amoebic?
- Result is the Amoeba shape
- Project costs far beyond expectationseven with
contingencies (padding) - Project suffers massive reworkingproblems.
22Parallels and Divergences in Theory
- Estimating is the beginning and the root of most
problems - Use Macro approach to estimating because of
- Size of project
- High uncertainty
- Unstable Scope
- Use several estimators
- Bring back estimators when there are changes to
constraints - Eden More Realistic
- Gray More Theoretical
23Parallels and Divergences in Theory
- Accelerating to Compensate
- The psychological NPV calculation
- Contradicting Methodology
- Fast Tracking, Adding Resources, and Scheduling
Overtime are good means to catch up (Gray). - Forgot about Reducing Project Scope
- Fear of losing value
- Taking back your words (leads to unhappy customer)
24Conclusion
Resource Schedulling
Great Importance to a Project
Cost Estimations
Time Estimation
Seven Stages of Project Expenditure
- The planning or control estimate
- Accelerating to compensate
25Amoebic Nature
Projects Orignal Shape
Transformation due to Unexpected costs
Amoebic Shape
26Critique
- Not ground breaking theories.
- Warns against common pitfalls for largecomplex
projects. - More relevant as companies become projectized.
27- Do you think their theories are sound?
- Have you experienced any of these stages inyour
project management experience? - Thank you for your attention.